N6264919Q0063_Attachment_(I)_Contractors_Performance_Evaluation_Sheet.doc
DOC document 35 KB Posted
- Attached to
- Oily Waste Water Purification Services Federal contract opportunity
- Solicitation number
- N6264919Q0063
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N62649/N6264919Q0063Combined_Synopsis_Solicitation_19Q0063-P0001.docx | DOCX document | |
| Combined_Synopsis_Solicitation_19Q0063.docx | DOCX document | |
| N6264919Q0063_Attachment_(II)_Financial_Info_Data_Sheet.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTOR’S PERFORMANCE EVALUATION SHEET
1. NAME OF CONTRACTOR:
2. CONTRACT NO.:
3. PERFORMANCE PERIOD OR DATE OF OPERATION:
AREAS TO BE EVALUATED
| Exceptional |
| Very Good |
| Satisfactory |
| Marginal |
| Unsatisfactory |
Schedule Compliance
Regulation Compliance
Timeliness and Accuracy of Invoices
COMMENTS:
Name and Title of Evaluator:
Phone No.:
Signature:
Date:
ADJECTIVAL RATINGS:
(a) Exceptional (E): The services performed by the Contractor are considered to have exceeded the performance standards described under “Performance Based Service Contract (PBSC)” and demonstrates a high probability of success without any problems during the remaining period of the contract.
(b) Very Good (VG): The services performed by the Contractor are considered to have satisfied the performance standards and demonstrates a good probability of success during the remaining period of the contract. Even if the Contractor had minor problems on its performance, the Contractor has demonstrated that it could correct such problems without any damage to the Government.
(c) Satisfactory (S): The Contractor’s performance is considered to have substantially met the stated performance standards and demonstrates a good probability of success during the remaining period of the contract. Even if the Contractor had minor problems on its performance, the Contractor has demonstrated that it could correct such problems with minimal damage to the Government. Although some minor inconsistency or weakness exists, it can be readily corrected.
(d) Marginal (M): The Contractor’s performance is considered to have partially failed meeting the stated performance standards, and the response to correct the deficiency was marginal. That is, a substantial number of the Contractor’s performance records responses “good,” but a deficiency or weakness exists, and it/they may be susceptible or correction through the exchange of information. There is marginal probability of success during the remaining period of the contract.
(e) Unsatisfactory (U): The Contractor failed meeting one or more of the stated performance standards, and the failure was considered “major.” Even if the failure was minor, the Contractor did not or could not correct the deficiency properly and/or it adversely affected the Government operation. In such a case, probability to success during the remaining period of the contract is minimal unless a proper corrective action is made.