QUESTION:

Can you confirm that line item 0001 of RFI N6227118Q1217 includes the complete GPS based “hot wire” based deflation device, and not just the wire only?

ANSWER:

The hot-wire installed in the HeliKite must be compatible with the Allsopp GPS Controlled Balloon Cutdown system (HCS-03M) See link: http://www.allsopp.co.uk/index.php?mod=page&id_pag=17 This procurement does not cover the GPS Controlled Balloon Cutdown system.

QUESTION:

On CLIN 0004, is NPS looking for a 34 cu or a 36 cu Polyurethane Balloon Replacement?

0004
Allsopp
Desert Start 34 cu. m. Polyurethane Balloon Replacement

a. Direct replacement for the polyurethane balloon inside the 36 cu. m Allsope Helikite Desert Star

b. All parts and instructions included to replace the balloon

1
EA

ANSWER: 34 cu. m., please excuse the typo.