Text version

Pre-Solicitation Conference Motor Gear Assembly Questions and Answers 2/7/2017 Q #1: Is testing required for the Motor or for M&G assembly?

A #1: Testing is for the Motor only, per the specs.

Q #2: Delivery of 50 units per month, is this the expected requirement (Min or max)?

A #2: It is anticipated that a minimum delivery of 50 units per month will be required.

Q #3: Will testing be done on units from the lot or additional units produced just for test?

A #3: Per the spec, testing will occur from random samples pulled from the production lot. The CLIN structure is still TBD so production and destructive testing production units may be separate CLINs.

Q #4: When was the last time the MGAs were procured?

A #4: The MGAs were last purchased in the mid-1980s as part of a larger system.

Q #5: When does the Government expect to determine whether the solicitation for N61331-17-SN-Q04, Motor Gear Assemblies will be a small business set-aside?

A #5: Within the next two weeks (by 2/24/17).