N55236-16-R-0003_ManLift_ScissorLift_IDIQ.pdf
PDF 278 KB Posted
- Solicitation number
- N55236-16-R-0003
About this file
N55236-16-R-0003 ManLift ScissorLift IDIQ
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment__1_N55236-16-R-0003.pdf | ||
| Attachment_3_Exhibit_A_-_E.xls | XLS spreadsheet | |
| Attachment_2_Request_for_Specification_Clarification_Form.doc | DOC document | |
| Attachment_3_Exhibit_A_-_E.xls | XLS spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until 11:00 AM local time 27 May 2016
X
A X B X C X D
EX
X
G F 39 - 47
48 - 55 X H 56 - 59 billie.crockett@navy.mil
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
DO-A3 1 59
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
N55236 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 1 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and
NBSD, Bldg 77, Room 108 conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
BILLIE P CROCKETT 619-556-4855
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 5
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
6 - 16
J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
18 - 19
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 21 - 24 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 25 - 31 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIONS AND INSTRUCTIONS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
32 - 37
PART II - CONTRACT CLAUSES
SOUTHWEST REGIONAL MAINTENANCE CENTER
CODE 410 3755 BRINSER STREET, STE 1
SAN DIEGO CA 92136
(619) 556-5664
(619) 556-2331FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.
N5526216RQDMANLIFT
5. DATE ISSUED
27 Apr 2016
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
N55236-16-R-0003
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
CLIN
Number
UNDEFINED Dollars, U.S.
BASE YEAR EFFORT
FFP
REFERENCE EXHIBIT A FOR BASE YEAR EFFORT.
BASE YEAR TOTAL ESTIMATED AMOUNT: $
FOB: Destination
PURCHASE REQUEST NUMBER: N5526216RQDMANLIFT
MAX
NET AMT
See Exhibit A
UNIT UNIT PRICE MAX AMOUNT
CLIN
OPTION OPTION ONE (SECOND YEAR EFFORT)
REFERENCE EXHIBIT B FOR OPTION 1 - SECOND YEAR EFFORT.
OPTION 1 TOTAL ESTIMATED AMOUNT: $
See Note B.
See Exhibit B
UNIT UNIT PRICE MAX AMOUNT
CLIN
OPTION OPTION TWO (THIRD YEAR EFFORT)
REFERENCE EXHIBIT C FOR OPTION 2 - THIRD YEAR EFFORT.
OPTION 2 TOTAL ESTIMATED AMOUNT: $
See Note B.
See Exhibit C
UNIT UNIT PRICE MAX AMOUNT
CLIN
OPTION OPTION THREE (FOURTH YEAR EFFORT)
REFERENCE EXHIBIT D FOR OPTION 3 - FOURTH YEAR EFFORT.
OPTION 3 TOTAL ESTIMATED AMOUNT: $
See Note B.
See Exhibit D
UNIT UNIT PRICE MAX AMOUNT
CLIN
OPTION OPTION FOUR (FIFTH YEAR EFFORT)
REFERENCE EXHIBIT E FOR OPTION 4 - FIFTH YEAR EFFORT.
OPTION 4 TOTAL ESTIMATED AMOUNT: $
See Note B.
See Exhibit E
CLAUSES INCORPORATED BY FULL TEXT
HQ B-2-0004 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (DEC 1995)
(a) As part of the negotiated fixed price or total estimated amount of this contact, both the Government and the Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $500 or less at the time of final contract closeout. The term “residual dollar amount” shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.
(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.
NOTE B - Option item to which the option clause in SECTION I-2 applies and which is to be supplied only if and to the extent said option is exercised.
HQ B-2-0022 CONTRACT SUMMARY FOR PAYMENT OFFICE (FIXED PRICE) (FEB 1997)
This entire contract is fixed price.
RMC B-2-0002 PROGRESS PAYMENT RATES (DEC 2015)
The progress payment rate for this contract is 90 percent for large business and 95 percent for small business in accordance with 10 USC 23007(g).
Section C - Descriptions and Specifications
STATEMENT OF WORK
SCOPE:
The primary purpose of the Southwest Regional Maintenance Center (SWRMC) Commercial Industrial Services (CIS) Man-lift Contract is to provide various sized man-lifts and scissor-lifts in support of the repair and upgrade of U.S. Naval ships and other Government vessels within a 50-mile radius of San Diego, CA which may include Oceanside, CA.
C.1 REFERENCES:
C.1.1 The requirements of the following references and attachments shall be utilized in the execution of this contract unless otherwise stated herein. Whenever specifications, Naval Sea Systems Command (NAVSEA) Standard Items, standards, drawings, publications or other documents undergo subsequent revisions, the contractor shall use the latest revised version during delivery order execution. If future revisions result in a change to the contractor’s price, the contractor shall promptly notify the contract administration office of the revision details and the expected impact. The Administrative Contracting Officer (ACO) will then negotiate and incorporate the necessary changes via bilateral modification to the contract. When future revisions result in no change to the contractor’s price, the contractor shall utilize the latest version as soon as the change is promulgated without a need for a contract modification.
C.1.2 If the Contractor does not have copies of the referenced documents, military standards, procedures, and regulations etc., the Shipbuilding Specialist (SBS) must be notified so that copies can be disseminated.
a. NAVSEA Standard Items
Category I NAVSEA STANDARD ITEMS (NSI) may be viewed on the internet at http://www.navsea.navy.mil/CNRMC/SERMC/SSRAC1/default.aspx and are invoked on all delivery orders.
b. Occupational Safety and Health Act (OSHA) 29 CFR 1910 and 1915
c. NAVFAC P-307, Management of Weight Handling Equipment.
d. Base Support Vehicles and Equipment (BSV&E) Standard Operating Procedure (SOP) #06-2, Naval Base Coronado Contractor Crane Oversight Plan.
e. BSV&E SOP #06-3, Naval Base San Diego Contractor Crane Oversight Plan
f. BSV&E SOP #06-4, Naval Base Point Loma Contractor Crane Oversight Plan
g. Naval Base San Diego Instruction 5450.8Q
C.1.3 Other documents not listed above may also be invoked, as required, for individual delivery orders.
C.2 GENERAL REQUIREMENTS:
C.2.1 Without additional expense to the Government, the Contractor shall be responsible for obtaining any necessary insurance, licenses, and permits for complying with all applicable laws, codes, and regulations, in connection with the performance of the work. The Contractor shall be responsible for ensuring that proper safety and health precautions are taken to protect the workers and the property of others.
C.2.2 All work being performed in this contract shall be accomplished IAW reference C.1.2.a
C.2.3 The Contractor shall provide all management, administrative services, materials, tools, equipment, labor, and any required services/support to accomplish the work specified in this contract.
C.2.4 The Contractor shall deliver/pickup/service all man-lifts and scissor lifts listed in this solicitation in accordance with the terms of the contract.
C.2.5 The Contractor shall comply with the Occupational Safety and Health Standard for Shipyard Employment (CFR, Title 29, Part 1915) promulgated under Public Law A85-742, Amended Section 41 of the Longshoremen’s and Harbor Workers Compensation Act (33 U.S.C.842) and adopted by the Department of Labor as Occupational Safety and Regulations for all work being performed under this contract on the navigable waters of the United States including any dry-dock or marine railway. Nothing contained in this contract or any delivery order there under shall be construed as relieving the Contractor from any obligation, which it may have for compliance with the aforesaid regulations IAW reference C.1.2.b.
C.2.6 All Contractor personnel and equipment must be licensed/registered/certified to operate/maintain/service all equipment involved in the performance of the requirements of this contract.
C.2.7 The Contractor shall notify the Administrative Contracting Officer (ACO) and SBS verbally and in writing of difficulties that may jeopardize the completion of specified work.
C.2.8 The Government will not be responsible for work delays or stoppages caused by the Contractor’s failure to comply with registration and access requirements. Similarly, the Government shall monitor and take appropriate action against Contractors who repeatedly or egregiously violate access control requirements.
C.2.9 Deliveries and pick-ups may be required outside normal working hours and on weekends. Normal working days are defined as, Sunday through Saturday.
C.2.10 The Government anticipates that the majority of the orders placed will require gasoline, diesel, or battery powered models; however, the need could arise for propane powered models.
C.2.11 The Government shall have the option to select the type of man-lift or scissor-lift as referred to C.2.10.
C.2.12 The Contractor shall ensure that the fuel (gasoline, diesel, or propane) levels are maintained on a regular basis for the equipment listed in the delivery order.
C.2.13 The Contractor shall be responsible to provide fuel for all equipment for the entire rental period listed on the delivery order as required at no additional cost to the government. (Estimate 10 gallons of fuel use per man-lift/scissor-lift, per week)
C.2.14 Nothing in this contract shall relieve the Contractor from complying with applicable federal, state and local laws, codes, ordinances and regulations in connection with hazardous waste handling and disposal in the performance of this contract.
C.3 STATEMENT OF WORK
(V)(G) CHECK POINT (Delivery and Inspection)
C.3.1 The Contractor shall conduct an inspection of all equipment upon delivery and submit a Conditions Found Report (CFR) to the SBS on the same day of delivery listing the inspection results of damaged and/or missing parts.
C.3.1.1 The approximate amount of paint that is found present on the existing equipment upon delivery, (i.e., basket/boom) shall be documented on the CFR.
C.3.1.2 The serial number of the man-lift and/or scissor-lift shall be documented on the CFR.
C.3.1.3 The Contractor must visually inspect fuel and oil levels to verify both are full upon delivery of the equipment.
C.3.1.4 The Contractor must verify that equipment is free of all leaks (fuel/oil/air) upon delivery of the equipment to the government.
C.3.1.5 Upon delivery of the equipment, the contractor must obtain the signed/printed name and Rank/Rate/Grade of the individual signing for receipt and inspection of the equipment.
(I)(G) FINAL CHECK POINT (Pick-up Verification Report)
C.3.2 The Contractor shall conduct an inspection of all equipment upon pick-up and submit a CFR to the SBS on the same day of pick-up listing the inspection results of damaged and/or missing parts.
C.3.2.1 The approximate amount of paint that is found present on the existing equipment upon pick-up, (i.e., basket/boom) shall be documented on the CFR.
C.3.2.2 The serial number of the man-lift or scissor-lift shall be documented on the Final Check Point sheet.
C.3.2.3 Upon pick-up of the equipment, the Contractor must obtain signed/printed name and Rank/Rate/Grade of the individual signing for the release and inspection of the equipment.
C.3.2.4 The Contractor shall provide hard copy or electronic media photos of damaged areas or missing parts on all equipment assigned to the delivery order and shall be submitted with the CFR.
C.4 MAINTENANCE AND REPAIR
C.4.1 The Contractor shall be responsible for the maintenance and repair of man-lifts and scissor-lifts to ensure proper operation of all equipment as required.
C.4.2 In the event that repairs cannot be performed in a 4-hour period for the equipment listed on the delivery order, the Contractor shall change-out equipment with another rental and submit a new Conditions Found Report to the SBS on the same day of delivery.
C.4.3 The Contractor shall be responsible for the cleanup of any spills or mitigations of hazards associated with the repair/maintenance being performed in accordance with all applicable regulations.
C.4.4 The Contractor shall be responsible for the cleanliness of the working area. All waste created by the Contractor as a result of the repair work specified herein, shall be removed from the pier at the end of each shift in accordance with C.1.2.g.
C.5 INSPECTION PROCEDURES
C.5.1 (I) Inspections require verification and documentation by a separate individual, other than the person who has accomplished the work, who is qualified as an inspector in accordance with the Contractors Quality Management System
(QMS).
C.5.2 (V) Inspections require verification and documentation by the qualified tradesperson, trade supervisor, or inspector.
C.5.3 (G) A symbol inserted in a Work Item to establish a point in the sequence of accomplishment of work at which time the SUPERVISOR shall be notified by the prime contractor in all cases to permit observation of a specific test or inspection (I)(V) by the government.
C.5.4 For (G) checkpoints scheduled during normal working hours, the Contractor shall notify the SBS of checkpoints via electronic method. Notification shall be at least four hours, but not more than one working day, prior to commencing the specific requirements in the paragraph annotated with the symbol (G). Notify the SBS not later than four hours before the end of the last preceding day shift when tests or inspections following a (G) check point is scheduled after normal day shift working hours, on a weekend, or on a federal holiday. Notify the SBS at least 48 hours , but not more than 72 hours, prior to commencing (G) check points at the Contractor’s/Sub-Contractor’s plants located in excess of 50 miles by the most direct roadway nearest to the place of performance of the contract. Document the date, time, and identification of the SBS notified.
C.5.5 For (G) check points scheduled during normal working hours, the Contractor shall notify the SBS for cancellation of the scheduled test or inspection as soon as known, but no later than one hour prior to the scheduled check point.
C.5.6 For (G) check points scheduled after normal working hours, on a weekend or a federal holiday, notify the SBS to cancel a scheduled test or inspection as soon as known, but no later than two hours prior to the scheduled check point.
C.6 DELAYS AND DISRUPTIONS
C.6.1 The Contractor shall coordinate his work efforts on a daily basis with the Ship’s Authorized Representative (SAR) in advance of evolutions that may impact delivery/pick-up of equipment.
C.6.2 Delay and disruption due to drills, shifting berths, inspections, serving of meals, ceremonies, operation of equipment, additional security requirements, and scheduled meetings are to be considered normal evolutions to be encountered when working on board Naval installations and vessels rather than unusual occurrences. Delays caused by these events will be at no cost to the Government.
C.6.3 The Contractor shall be responsible for coordinating work efforts with other Contractors working in the same or adjacent areas to ensure no delays.
C.7 PROGRESS MEETINGS/REPORTS
C.7.1 The Contractor shall participate in daily or weekly progress meeting(s) as required. The Contractor will provide a progress report of all active jobs to the SBS on Monday or the first business day of each week no later than 8:00am.
C.7.2 The Contractor shall be prepared to address all facets of the work including but not limited to schedule and/or problems with the ongoing work and proposed actions to be taken to resolve problems.
C.8 BILLING/INVOICING
C.8.1 At the time of billing/invoicing, The Contractor shall provide to the SBS, two hard copies of all information, (i.e., delivery order, modifications, CFR’s, inspection discrepancy reports (IDR), TIP, check points, and inspection reports) compiled during the performance of the work for each delivery order.
C.9 DELIVERY OF SERVICE
C.9.1 The Contractor shall deliver each man-lift before 0730 on the start of the period of performance and pick-up each man-lift after 1530 on the end of the period of performance (POP).
C.9.2 The Contractor shall deliver each man-lift within four hours of the receipt of delivery orders that are awarded on the same day of the start of POP.
C.10 SECURITY REQUIREMENTS
C.10.1 The Contractor shall submit a list providing security information to SWRMC Security no later than five days after the contract award date. The data is to include the list of all Contractor personnel supporting the contract effort, social security numbers, addresses, citizenship, level of clearance and radiological controls indoctrination training documents (for CVN contracted work only). The Contractor shall submit a new list whenever there is any change in the security information listing.
C.10.2 The Contractor shall issue each employee an identification card containing the employee's picture, which shall be utilized for positive identification. The card shall be worn in a visible location when employee is on Government property.
C.11 HAZARDOUS WASTE:
C.11.1 All waste generated deemed non-hazardous shall be removed from the pier daily and will not be allowed to accumulate. Waste generated deemed as hazardous shall be removed from the pier no later than the last day of the assigned performance period.
C.11.2 The Contractor shall submit a copy of all reports of chemical analysis or other documents evidencing identification of the hazardous waste to SWRMC Environmental Department Code 106B and SBS upon completion of each delivery order.
C.11.3 The analysis of any waste requiring the services of a testing laboratory (e.g., liquids, used cleaning solvent material) shall be performed by a laboratory certified by the California Department of Public Health (CDPH) to be competent and equipped to conduct the specific type of analysis to be performed.
C.12 CONTRACTOR FURNISHED EQUIPMENT (CFE):
C.12.1 The Contractor shall furnish all necessary materials and equipment to perform work required by this contract.
C.12.2 The Contractor shall be responsible for maintaining all CFE. CFE shall be properly calibrated, tested and in state of repair that is ready for use, to the extent necessary to avoid impacting the performance requirements of this contract.
C.12.3 The Contractor is responsible for the relocation of own equipment in the event of berth shifts or repositioning of the ship at no additional cost to the government.
C.13 GOVERNMENT FURNISHED MATERIAL (GFM):
None
C.14 NON-NAVY OWNED CRANES:
C.14.1 The Contractor shall adhere and follow the requirements IAW reference C.1.2.a, C.1.2.c, C.1.2.d, C1.2.e, C.1.2.f and C.1.2.g.
C.15 ADDITIONAL PROVISIONS:
C.15.1 The Contractor(s) awarded a contract as a result of the solicitation will be required to have in place, no later than the contract award date, a SWRMC approved Quality Management System IAW reference C.1.2.a and the most current ISO.
HQ C-2-0005 ACCESS TO VESSELS BY NON-U.S. CITIZENS (NAVSEA) (DEC 2005)
(a) No person not known to be a U.S. citizen shall be eligible for access to naval vessels, work sites and adjacent areas when said vessels are under construction, conversion, overhaul, or repair, except upon a finding by COMNAVSEA or his designated representative that such access should be permitted in the best interest of the United States. The Contractor shall establish procedures to comply with this requirement and NAVSEAINST
5500.3 (series) in effect on the date of this contract or agreement.
(b) If the Contractor desires to employ non-U.S. citizens in the performance of work under this contract or agreement that requires access as specified in paragraph (a) of this requirement, approval must be obtained prior to access for each contract or agreement where such access is required. To request such approval for non-U.S. citizens of friendly countries, the Contractor shall submit to the cognizant Contract Administration Office (CAO), an Access Control Plan (ACP) which shall contain as a minimum, the following information:
(1) Badge or Pass oriented identification, access, and movement control system for non-U.S. citizen employees with the badge or pass to be worn or displayed on outer garments at all times while on the Contractor's facilities and when performing work aboard ship.
(i) Badges must be of such design and appearance that permits easy recognition to facilitate quick and positive identification.
(ii) Access authorization and limitations for the bearer must be clearly established and in accordance with applicable security regulations and instructions.
(iii) A control system, which provides rigid accountability procedures for handling lost, damaged, forgotten or no longer required badges, must be established.
(iv) A badge or pass check must be performed at all points of entry to the Contractor's facilities or by a site supervisor for work performed on vessels outside the Contractor's plant.
(2) Contractor's plan for ascertaining citizenship and for screening employees for security risk.
(3) Data reflecting the number, nationality, and positions held by non-U.S. citizen employees, including procedures to update data as non-U.S. citizen employee data changes, and pass to cognizant CAO.
(4) Contractor's plan for ensuring subcontractor compliance with the provisions of the Contractor's ACP.
(5) These conditions and controls are intended to serve as guidelines representing the minimum requirements of an acceptable ACP. They are not meant to restrict the Contractor in any way from imposing additional controls necessary to tailor these requirements to a specific facility.
(c) To request approval for non-U.S. citizens of hostile and/or communist-controlled countries (listed in Department of Defense Industrial Security Manual, DOD 5220.22-M or available from cognizant CAO), Contractor shall include in the ACP the following employee data: name, place of birth, citizenship (if different from place of birth), date of entry to U.S., extenuating circumstances (if any) concerning immigration to U.S., number of years employed by Contractor, position, and stated intent concerning U.S. citizenship. COMNAVSEA or his designated representative will make individual determinations for desirability of access for the above group. Approval of ACP's for access of non-U.S. citizens of friendly countries will not be delayed for approval of non-U.S. citizens of hostile communist-controlled countries. Until approval is received, Contractor must deny access to vessels for employees who are non-U.S. citizens of hostile and/or communist-controlled countries.
(d) The Contractor shall fully comply with approved ACPs. Noncompliance by the Contractor or subcontractor serves to cancel any authorization previously granted, in which case the Contractor shall be precluded from the continued use of non-U.S. citizens on this contract or agreement until such time as the compliance with an approved ACP is demonstrated and upon a determination by the CAO that the Government's interests are protected. Further, the Government reserves the right to cancel previously granted authority when such cancellation is determined to be in the Government's best interest. Use of non-U.S. citizens, without an approved ACP or when a previous authorization has been canceled, will be considered a violation of security regulations. Upon confirmation by the CAO of such violation, this contract, agreement or any job order issued under this agreement may be terminated or default in accordance with the clause entitled "DEFAULT (FIXED-PRICE SUPPLY AND SERVICE)" (FAR 52.249-8), "DEFAULT (FIXED-PRICE RESEARCH AND DEVELOPMENT)" (FAR 52.249-9) or "TERMINATION (COST REIMBURSEMENT)" (FAR 52.249-6), as applicable.
(e) Prime Contractors have full responsibility for the proper administration of the approved ACP for all work performed under this contract or agreement, regardless of the location of the vessel, and must ensure compliance by all subcontractors, technical representatives and other persons granted access to U.S. Navy vessels, adjacent areas, and work sites.
(f) In the event the Contractor does not intend to employ non-U.S. citizens in the performance of the work under this contract, but has non-U.S. citizen employees, such employees must be precluded from access to the vessel and its work site and those shops where work on the vessel's equipment is being performed. The ACP must spell out how non-U.S. citizens are excluded from access to contract work areas.
(g) The same restriction as in paragraph (f) above applies to other non-U.S. citizens who have access to the Contractor's facilities (e.g., for accomplishing facility improvements, from foreign crewed vessels within its facility, etc.)
(h) An ACP which has been approved for specific Master Ship Repair Agreement (MSRA) or Agreement for Boat Repair (ABR) or Basic Ordering Agreement (BOA), is valid and applicable to all job orders awarded under that agreement.
HQ C-2-0007 APPROVAL BY THE GOVERNMENT (AT) (NAVSEA) (JAN 1983)
Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.
HQ C-2-0014 CONTRACTOR'S PROPOSAL (NAVSEA) (MAR 2001)
(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with detailed obligations to which the Contractor committed itself in Proposal dated in response to SWRMC Solicitation No.
N55236-16-R-0003.
(b) The technical volume(s) of the Contractor's proposal is incorporated by reference and hereby made subject to the provisions of the "ORDER OF PRECEDENCE" (FAR 52.215-8) clause of this contract. Under the "ORDER OF PRECEDENCE" clause, the technical volume of the Contractor's proposal referenced herein is hereby designated as item
(f) of the clause, following "the specification" in the order of precedence.
HQ C-2-0016 DEPARTMENT OF LABOR OCCUPATIONAL SAFETY AND HEALTH STANDARDS FOR
SHIP REPAIR (NAVSEA) (SEP 1990)
Attention of the Contractor is directed to the Occupational Safety and Health Act of 1970 (29 USC 651-678), and to the Safety and Health Regulations for Ship Repairing (29 CFR 1915), promulgated under Public Law 85-742, amending Section 41 of the Longshoremen's and Harbor Workers' Compensation Act (33 USC 941), and adopted by the Department of Labor as occupational safety or health standards under Section 6(a) of the Occupational Safety and Health Act of 1970 (See 29 CFR 1910.13). These regulations apply to all ship repair and related work, as defined in the regulations performed under this contract on the navigable waters of the United States including any dry dock and marine railway. Nothing contained in this contract shall be construed as relieving the Contractor from any obligations which it may have for compliance with the aforesaid regulations.
HQ C-2-0030 INFORMATION AND DATA FURNISHED BY THE GOVERNMENT (FIXED-PRICE)
(NAVSEA) (JAN 2008)
(a) Contract Specifications. The Government will furnish, if not included as an attachment to the contract, any unique contract specifications set forth in Section C.
(b) Contract Drawings and Data. The Government will furnish contract drawings, design agent drawings, ship construction drawings, and/or other design or alteration data cited or referenced in Section C or in the contract specification as mandatory for use or for contract performance.
(c) Government Furnished Information (GFI). GFI is defined as that information essential for the installation, test, operation, and interface support of all Government Furnished Material enumerated on NAVSEA Form 4205/19 or Schedule A, as applicable, attached to the contract. The Government shall furnish only the GFI identified on the NAVSEA Form 4340/2 or Schedule C, as applicable, attached to the contract. The GFI furnished to the contractor need not be in any particular format. Further, the Government reserves the right to revise the listing of GFI on the NAVSEA Form 4340/2 or Schedule C, as applicable, as follows:
(1) The Contracting Officer may at any time by written order:
(i) delete, supersede, or revise, in whole or in part, data listed or specifically referenced in NAVSEA Form 4340/2 or Schedule C, as applicable; or
(ii) add items of data or information to NAVSEA Form 4340/2 or Schedule C, as applicable; or
(iii) establish or revise due dates for items of data or information in NAVSEA Form 4340/2 or Schedule C, as applicable.
(2) If any action taken by the Contracting Officer pursuant to subparagraph (1) immediately above causes an increase or decrease in the costs of, or the time required for, performance of any part of the work under this contract, the contractor may be entitled to an equitable adjustment in the contract price and delivery schedule in accordance with the procedures provided for in the clause of this contract entitled "CHANGES--FIXED-PRICE"
(FAR 52.243-1).
(d) Except for the Government information and data specified by paragraphs (a), (b), and (c) above, the Government will not be obligated to furnish the Contractor any specification, standard, drawing, technical documentation, or other publication, notwithstanding anything to the contrary in the contract specifications, the GFI listed on the NAVSEA Form 4340/2 or Schedule C, as applicable, the clause of this contract entitled Government Property (FAR 52.245-1) as applicable, or any other term or condition of this contract.
(e) Referenced Documentation. The Government will not be obligated to furnish Government specifications and standards, including Navy standard and type drawings and other technical documentation, which are referenced directly or indirectly in the contract specifications set forth in Section C and which are applicable to this contract as specifications. Such referenced documentation may be obtained:
(1) From the ASSIST database via the internet at http://assist.daps.dla.mil/; or
(2) By submitting a request to the Department of Defense Single Stock Point (DoDSSP) Building 4, Section D 700 Robbins Avenue Philadelphia, Pennsylvania 19111-5094 Telephone (215) 697-2179 Facsimile (215) 697-1462.
Commercial specifications and standards, which may be referenced in the contract specification or any sub-tier specification or standard, are not available from Government sources and should be obtained from the publishers.
NOTES:
These requirements do not apply with respect to nuclear propulsion plant systems and other matters under the technical cognizance of the Deputy Commander, Nuclear Propulsion Directorate, Naval Sea Systems Command.
HQ C-2-0033 LIMITATION OF LIABILITY - HIGH VALUE ITEMS (NAVSEA) (JUN 1992)
The following items are subject to the clause of this contract entitled "LIMITATION OF LIABILITY--HIGH
VALUE ITEMS" (FAR 52.246-24):
HQ C-2-0034 MINIMUM INSURANCE REQUIREMENTS (NAVSEA) (SEP 1990)
In accordance with the clause of this contract entitled "INSURANCE--WORK ON A GOVERNMENT INSTALLATION" (FAR 52.228-5), the Contractor shall procure and maintain insurance, of at least the kinds and minimum amounts set forth below:
(a) Workers' Compensation and Employer's Liability coverage shall be at least $100,000, except as provided in FAR 28.307(a).
(b) Bodily injury liability insurance coverage shall be written on the comprehensive form of policy of at least $500,000 per occurrence.
(c) Automobile Liability policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.
HQ C-2-0038 PERMITS AND RESPONSIBILITIES (NAVSEA) (SEP 1990)
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any applicable Federal, State, and Municipal laws, codes, and regulations, in connection with any movement over the public highways of overweight/overdimensional materials.
HQ C-2-0044 PROTECTION OF THE VESSEL (NAVSEA) (SEP 1990)
(a) The Contractor shall exercise reasonable care, as agreed upon with the Supervisor, to protect the vessel from fire, and shall maintain a system of inspection over the activities of its welders, burners, riveters, painters, pipe fitters, and similar workers, and of its subcontractors, particularly where such activities are undertaken in the vicinity of the vessel's magazines, fuel oil tanks, or store rooms containing inflammable materials. All ammunition, fuel oil, motor fuels, and cleaning fluids shall have been off-loaded and the tanks cleaned, except as may be mutually agreed upon between the Contractor and the Supervisor prior to work on the vessel by the Contractor. Fire hose lines shall be maintained by the Contractor ready for immediate use on the vessel at all times while the vessel is berthed alongside the Contractor's pier or in dry dock. All tanks under alteration or repair shall be cleaned, washed, and steamed out or otherwise made safe to the extent necessary, and the Contractor shall furnish the vessel's Gas Free Officer and the Supervisor with a "Gas Chemists' Certificate" before any hot work is done. The Contractor shall maintain a fire watch aboard the vessel in areas where the Contractor is working. All other fire watches aboard the vessel shall be the responsibility of the Government.
(b) Except as otherwise provided in contractually invoked technical specifications or NAVSEA furnished directives, while the vessel is at the Contractor's plant and when the temperature becomes as low as thirty-five degrees Fahrenheit, the Contractor shall assist the Government when requested in keeping all pipe-lines, fixtures, traps, tanks, and other receptacles on the vessel drained to avoid damage from freezing, or if this is not practicable, the vessel shall be kept heated to prevent such damage. The vessel's stern tube and propeller hubs shall be protected by the Contractor from frost damage by applied heat through the use of a salamander or other proper means.
(c) The work shall, whenever practicable, be performed in such manner as not to interfere with the work performed by military personnel attached to the vessel, and provisions shall be made so that personnel assigned shall have access to the vessel at all times, it being understood that such personnel will not unduly interfere with the work of the Contractor's workmen.
(d) The Contractor shall at all times keep the site of the work on the vessel free from accumulation of waste material or rubbish caused by its employees, or the work performed by the Contractor in accordance with this contract, and at the completion of such work shall remove all rubbish from and about the site of the work, and shall leave the work in its immediate vicinity "broom clean", unless more exactly specified by the Supervisor.
HQ C-2-0051 SPECIFICATIONS AND STANDARDS (NAVSEA) (AUG 1994)
(a) Definitions.
(i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments).
(ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing.
(b) Requirements.
All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only.
HQ C-2-0059 UPDATING SPECIFICATIONS AND STANDARDS (NAVSEA) (AUG 1994)
If, during the performance of this or any other contract, the contractor believes that any contract contains outdated or different versions of any specifications or standards, the contractor may request that all of its contracts be updated to include the current version of the applicable specification or standard. Updating shall not affect the form, fit or function of any deliverable item or increase the cost/price of the item to the Government. The contractor should submit update requests to the Procuring Contracting Officer with copies to the Administrative Contracting Officer and cognizant program office representative for approval. The contractor shall perform the contract in accordance with the existing specifications and standards until notified of approval/disapproval by the Procuring Contracting Officer. Any approved alternate specifications or standards will be incorporated into the contract.
RMC C-2-0010 NON SMOKING POLICY
For bidding purposes, contractors are advised that in light of the Navy's policy regarding smoke-free facilities, the entire vessel, topside and below decks, is to be considered a "No Smoking Area" unless otherwise indicated by shipboard policy.
Section D - Packaging and Marking
HQ D-1-0001 DATA PACKAGING LANGUAGE (NAVSEA)
Data to be delivered by Integrated Digital Environment (IDE) or other electronic media shall be as specified in the contract.
All unclassified data to be shipped shall be prepared for shipment in accordance with best commercial practice.
Classified reports, data, and documentation shall be prepared for shipment in accordance with National Industrial Security Program Operating Manual (NISPOM), DOD 5220.22-M dated 28 February 2006.
HQ D-2-0008 MARKING OF REPORTS (NAVSEA) (SEP 1990)
All reports delivered by the Contractor to the Government under this contract shall prominently show on the cover of the report:
(1) name and business address of the Contractor
(2) contract number
(3) contract dollar amount
(4) whether the contract was competively or non-competively awarded
(5) sponsor:
Commanding Officer Southwest Regional Maintenance Center San Diego, CA 92136
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 1001 Destination Government Destination Government 2001 Destination Government Destination Government 3001 Destination Government Destination Government 4001 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-2 Inspection Of Supplies--Fixed Price AUG 1996 52.246-4 Inspection Of Services--Fixed Price AUG 1996 52.246-16 Responsibility For Supplies APR 1984
52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)
(a) The Contractor shall comply with the higher-level quality standard selected below.
Title Number Date Tailoring
ANSI/ISO/ASQ Q9001 2008 See NAVSEA SI 009-04
(b) The Contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph
(a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in--
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require--
(i) Control of such things as design, work operations, in-process control, testing, and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
(End of clause)
HQ E-2-0002 ADDITIONAL PROVISIONS RELATING TO CORRECTION OF DEFECTS (NAVSEA) (OCT 1990)
In case any work done or materials or supplies furnished by the Contractor under this contract for any vessel, or the equipment thereof, shall within sixty (60) days of delivery of the vessel to the Government, or the date of final acceptance, whichever occurs first, prove defective or deficient, such defects or deficiencies shall, as required by the Government, be corrected or repaired by the Contractor to the satisfaction of the Contracting Officer; provided, however, that with respect to any individual work item which is incomplete or deficient at the time of delivery or acceptance, the Contractor's obligation under this requirement to correct or repair such deficiency shall extend sixty
(60) days from the date of such correction or repair, whichever occurs first. The Contractor shall be entitled to allowable costs for corrections or repairs performed in accordance with this requirement but shall not be entitled to any additional fee for such work.
HQ E-2-0015 QUALITY MANAGEMENT SYSTEM REQUIREMENTS (NAVSEA) (SEP 2009)
Quality Management System Requirements. The Contractor shall provide and maintain a quality management system that, as a minimum, adheres to the requirements of ANSI/ISO/ASQ 9001-2008 Quality Management Systems and supplemental requirements imposed by this contract. The quality management system procedures, planning, and all other documentation and data that comprise the quality management system shall be made available to the Government for review. Existing quality documents that meet the requirements of this contract may continue to be used. The Government may perform any necessary inspections, verifications, and evaluations to ascertain conformance to requirements and the adequacy of the implementing procedures. The Contractor shall require of subcontractors a quality management system achieving control of the quality of the services and/or supplies provided. The Government reserves the right to disapprove the quality management system or portions thereof when it fails to meet the contractual requirements.
HQ E-2-0015 QUALITY MANAGEMENT SYSTEM REQUIREMENTS (NAVSEA) (SEP 2009)
Quality Management System Requirements. The Contractor shall provide and maintain a quality management system that, as a minimum, adheres to the requirements of ANSI/ISO/ASQ 9001-2008 Quality Management Systems and supplemental requirements imposed by this contract. The quality management system procedures, planning, and all other documentation and data that comprise the quality management system shall be made available to the Government for review. Existing quality documents that meet the requirements of this contract may continue to be used. The Government may perform any necessary inspections, verifications, and evaluations to ascertain conformance to requirements and the adequacy of the implementing procedures. The Contractor shall require of subcontractors a quality management system achieving control of the quality of the services and/or supplies provided. The Government reserves the right to disapprove the quality management system or portions thereof when it fails to meet the contractual requirements.
Section F - Deliveries or Performance
52.242-15 Stop-Work Order AUG 1989 52.242-17 Government Delay Of Work APR 1984 52.247-34 F.O.B. Destination NOV 1991 52.247-48 F.O.B. Destination--Evidence Of Shipment FEB 1999
RMC F-1-0001 EFFECTIVE DATE OF THE CONTRACT (RMC)
Delivery orders will be issued under the terms and conditions of this Contract during the period of performance specified herein:
Base Period: Item 0001 is one (1) year from effictive date of award.
Option One: (Item 1001) if exercised by the Government, is one (1) year from effictive date of execution.
Option Two: (Item 2001) if exercised by the Government, is one (1) year from effictive date of execution.
Option Three: (Item 3001) if exercised by the Government, is one (1) year from effictive date of execution.
Option Four: (Item 4001) if exercised by the Government, is one (1) year from effictive date of execution.
NOTE 1: SEE FAR CLAUSE 52.217-9, OPTION TO EXTEND THE TERM OF THE CONTRACT, IN SECTION
“I” OF THIS CONTRACT
NOTE 2: SEE FAR CLAUSE 252.216-7006, ORDERING AND FAR CLAUSE 52.216-19, ORDER
LIMITATIONS, IN SECTION “I” OF THIS CONTRACT.
Section G - Contract Administration Data
252.204-7006 Billing Instructions OCT 2005 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
JUN 2012
252.246-7000 Material Inspection And Receiving Report MAR 2008
252.204-0001 LINE ITEM SPECIFIC: SINGLE FUNDING. (SEP 2009)
The payment office shall make payment using the ACRN funding of the line item being billed.
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
Invoice and Receiving Report Combo (FFP Supply)
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
Inspection: Destination – N55262 Acceptance: Destination – N55262
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC N68732 Issue By DoDAAC N55236 Admin DoDAAC N55236 Inspect By DoDAAC To be specified in each task order.
Ship To Code To be specified in each task order.
Ship From Code To be specified in each task order.
Mark For Code To be specified in each task order.
Service Approver (DoDAAC) To be specified in each task order.
Service Acceptor (DoDAAC) To be specified in each task order.
Accept at Other DoDAAC To be specified in each task order.
LPO DoDAAC To be specified in each task order.
DCAA Auditor DoDAAC To be specified in each task order.
Other DoDAAC(s) To be specified in each task order.
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
To be specified in each delivery order
(g) WAWF point of contact.