N55236-15-R-0002.pdf

PDF 695 KB Posted

Attached to
Commercial Industrial Services Hullboard Lagging
Solicitation number
N55236-15-R-0002
Issued by

About this file

Standard Form 33

View the file

Other files

File Type Posted
CDRLS_Combined.pdf PDF
Exhibit_A-E.xls.xlsx XLSX spreadsheet
J-1_-_Reference_Information_Sheet.docx DOCX document
J-2_-_Request_for_Specification_Clarification_Form.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 11:00 AM local time 2 Jul 2015

X

A X B X C X D

E X X

G F 61 - 69

70 - 79 X H 80 - 85 jane.pamintuan@navy.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

DO-A3 1 82

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE 15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N55236 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 1 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and

NBSD, Bldg 77, Room 108 conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

JANE PAMINTUAN (619) 556-1166

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 7

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

8 - 28

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

30 - 33 34 - 35

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 36 - 38 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 39 - 47 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL: TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

48 - 59

PART II - CONTRACT CLAUSES

SOUTHWEST REGIONAL MAINTENANCE CENTER

PCO CODE 410 ,3755 BRINSER ST. STE 1

SAN DIEGO CA 92136-5025

619-556-5989

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.

N5523615RXXXXX

5. DATE ISSUED

2 Jun 2015

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N55236-15-R-0002

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

CLIN

Number

UNDEFINED Dollars, U.S.

BASE YEAR EFFORT

FFP

REFERENCE EXHIBIT A FOR BASE YEAR EFFORT.

BASE YEAR TOTAL ESTIMATED AMOUNT: $

FOB: Destination

PURCHASE REQUEST NUMBER: N5523615RXXXXX

MAX

NET AMT

See Exhibit A

UNIT UNIT PRICE MAX AMOUNT

CLIN

UNDEFINED N/A NSP

CONTRACT DATA REQUIREMENTS LIST

Not Seperately Priced

Data for Item 0001 and (if Option(s) are exercised) Items 1001 through 4001 (see

DD Form 1423, Contract Data Requirements Lists (CDRLs) attached hereto - Not

Separately Priced. Price included in Items 0001 and (if Option(s) are exercised)

Items 1001 through 4001, as set forth in individual Delivery Orders.

See Note A.

NSP

See Exhibit F

UNIT UNIT PRICE MAX AMOUNT

CLIN

OPTION OPTION ONE (SECOND YEAR EFFORT)

REFERENCE EXHIBIT B FOR OPTION 1 - SECOND YEAR EFFORT.

OPTION 1 TOTAL ESTIMATED AMOUNT: $

SEE EXHIBIT B

See Note B.

See Exhibit B

UNIT UNIT PRICE MAX AMOUNT

CLIN

OPTION OPTION TWO (THIRD YEAR EFFORT)

REFERENCE EXHIBIT C FOR OPTION 2 - THIRD YEAR EFFORT.

OPTION 2 TOTAL ESTIMATED AMOUNT: $

See Exhibit C

UNIT UNIT PRICE MAX AMOUNT

CLIN

OPTION OPTION THREE (FOURTH YEAR EFFORT)

REFERENCE EXHIBIT D FOR OPTION 3 - FOURTH YEAR EFFORT.

OPTION 3 TOTAL ESTIMATED AMOUNT: $

See Exhibit D

UNIT UNIT PRICE MAX AMOUNT

CLIN

OPTION OPTION FOUR (FIFTH YEAR EFFORT)

REFERENCE EXHIBIT E FOR OPTION 4 - FIFTH YEAR EFFORT.

OPTION 4 TOTAL ESTIMATED AMOUNT: $

See Exhibit E

CLAUSES INCORPORATED BY FULL TEXT

HQ B-2-0004 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (DEC 1995)

(a) As part of the negotiated fixed price or total estimated amount of this contact, both the Government and the

Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $500 or less at the time of final contract closeout. The term “residual dollar amount” shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.

(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.

HQ B-2-0009 CDRL NOTE (NAVSEA)(SEP 1990)

NOTE A - Offeror shall complete the "Price Group" and "Estimated Total Price" blocks of each data item on the

Contract Data Requirements List(s), attached hereto.

HQ B-2-0010 OPTION NOTE (NAVSEA)(SEP 1990)

NOTE B - Option item to which the option clause in SECTION I-2 applies and which is to be supplied only if and to the extent said option is exercised.

HQ B-2-0016 PROVISIONING TECHNICAL DOCUMENTATION – WITHHOLDING OF PAYMENT

(NAVSEA) (SEP 1990)

(a) For the purpose of paragraph (c) of the "PROGRESS PAYMENTS" clause of this contract, if included, the requirement that the Contractor develop and deliver Provisioning Technical Documentation (PTD) is considered to be a

"material requirement of this contract," and Contractor failure to make adequate progress in the development of PTD, or to deliver acceptable PTD on a timely basis, may result in reduction or suspension of Progress Payments as provided in said paragraph.

(b) The PTD is considered to be a part of the "Technical Data" specified to be delivered under this contract for the purposes of the "TECHNICAL DATA--WITHHOLDING OF PAYMENT" (DFARS 252.227-7030) clause. The terms and conditions of the clause entitled "LIMITATION ON WITHHOLDING OF PAYMENTS (FAR 52.232-9), if included in this contract, shall not apply to withholding of payment for failure to make timely delivery of the PTD or delivery of deficient PTD.

HQ B-2-0022 CONTRACT SUMMARY FOR PAYMENT OFFICE (FIXED PRICE) (FEB 1997)

This entire contract is fixed price.

Section C - Descriptions and Specifications

STATEMENT OF WORK

SCOPE:

The primary purpose of the Southwest Regional Maintenance Center (SWRMC) Commercial Industrial Services

(CIS) Hullboard Insulation Contract is to provide services, equipment, and materials for the removal, repair and installation of hullboard insulation onboard U.S. Navy ships and other US Government vessels within a 50-mile radius of San Diego, CA which may include Oceanside, CA.

C.1 REFERENCES:

C.1.1 The requirement of the following references and attachments shall be utilized in the execution of this contract unless otherwise stated herein. Whenever specifications, NAVSEA Standard Items (NSI), standards, drawings, publications or other documents undergo subsequent revisions the Contractor shall use the latest revised version during contract execution. If future revisions result in a change to the Contractor’s price, the Contractor shall promptly notify the contract administration office of the revision details and the expected impact. The

Administrative Contracting Officer (ACO) will then negotiate and incorporate the necessary changes via bilateral modification to the contract. When future revisions result in no change to the Contractor’s price, the Contractor shall utilize the latest version as soon as the change becomes known without a need for a contract modification.

C.1.2 If the Contractor does not have copies of the referenced documents, military standards, procedures, regulations etc., the Shipbuilding Specialist (SBS) must be notified so that copies can be disseminated.

a. Current NAVSEA Standard Items

Category I, NAVSEA STANDARD ITEMS may be viewed on the internet at http://www.navsea.navy.mil/CNRMC/SERMC/SSRAC1/default.aspx and are invoked on all delivery orders.

The following Category II, NAVSEA STANDARD ITEMS may be viewed on the internet at http://www.navsea.navy.mil/CNRMC/SERMC/SSRAC1/default.aspx and are invoked in this contract as required:

009-09 Process Control Procedure (PCP); provide and accomplish

009-11 Insulation and Lagging Requirements; accomplish

009-26 Deck Covering Requirements; accomplish

009-32 Cleaning and Painting Requirements; accomplish

b. Occupational Safety and Health Act (OSHA) 29 CFR 1910 and 1915.

c. Commander Fleet Forces Command Instruction (COMFLTFORCOMINST) 4790.3, Work Authorization

Form (WAF)

d. S9086-VH-STM-010/CH-CH635R2; Thermal, Fire and Acoustic Insulation

e. Naval Facilities (NAVFAC) P-307, Management of Weight Handling Equipment

f. Base Support Vehicle & Equipment Standard Operating Procedure (BSV & E SOP) #06-2, Naval Base

Coronado Contractor Crane Oversight Plan

g. Base Support Vehicle & Equipment Standard Operating Procedure (BSV&E SOP) #06-3, Naval Base San

Diego Contractor Crane Oversight Plan

h. Base Support Vehicle & Equipment Standard Operating Procedure (BSV&E SOP) #06-4, Naval Base Point

Loma Contractor Crane Oversight Plan

Note: Other documents not listed above may also be invoked, as required, for individual delivery orders. Specific references shall be identified on each delivery order and associated referenced technical documentation.

C.2 GENERAL REQUIREMENTS:

C.2.1 The quality of all services rendered shall conform to the highest standard in the relevant profession, trade or field of endeavor. Without additional expense to the Government, the Contractor shall be responsible for obtaining any necessary insurance, licenses and permits, and for complying with all applicable laws, codes and regulations, in connection with the performance of the work. The Contractor shall be responsible for ensuring that proper safety and health precautions are taken to protect the workers and the property of others and the costs thereof. Accomplish the requirements in accordance with (IAW) reference C.1.2.a.

C.2.2 All work being performed in this contract shall be accomplished IAW reference C.1.2.a as invoked.

C.2.3 The Contractor shall provide all management, administrative services, materials, tools, equipment, labor, rigging, scaffolding, utilities (i.e. air, water and electricity, etc.) and required services/support to accomplish the work specified in this contract.

C.2.4 The Contractor shall provide all cranes necessary to accomplish the work under this contract, including floating cranes when required and cranes with a boom capacity great enough to reach ships berthed second ship out

IAW reference C.1.2.a.

C.2.5 The Contractor may utilize government utilities available at the pier. It is the Contractor’s responsibility to arrange for, coordinate with, meet the requirements of, and pay Naval Facilities-Southwest (NAVFAC-SW) for use of government utilities.

C.2.6 The Contractor shall comply with the Occupational Safety and Health Standard for Shipyard Employment

(CFR, Title 29, Part 1915) promulgated under Public Law A85-742, Amended Section 41 of the Longshoremen’s and Harbor Workers Compensation Act (33 U.S.C.842) and adopted by the Department of Labor as Occupational

Safety and Regulations, for all work being performed under this contract on the navigable waters of the United

States including any dry-dock or marine railway. Nothing contained in this contract or any delivery order there under shall be construed as relieving the Contractor from any obligation, which it may have for compliance with the aforesaid regulations IAW reference C.1.2.b.

C.2.7 The Contractor shall notify the ACO and SBS verbally and in writing of difficulties that may jeopardize the completion of specified work.

C.2.8 The Government will not be responsible for work delays or stoppages caused by the Contractor’s failure to comply with registration and access requirements. Similarly, the Government shall monitor and take appropriate action against Contractor’s who repeatedly or egregiously violate access control requirements.

C.2.9 Work may be required outside normal working hours and on weekends. Normal working days are defined as

Sunday through Saturday.

C.2.10 The Contractor shall notify the Ship’s Authorized Representative (SAR) prior to start of work noting equipment and systems that require isolation so that tag outs can be accomplished as required.

C.2.11 The Contractor shall follow procedures for system tag-out IAW 009-24, reference C.1.2.a.

C.2.12 The Contractor shall notify the SAR immediately when all work required by the delivery order is completed and the system is ready for activation and removal of tags.

C.2.13 Nothing in this contract shall relieve the Contractor from complying with applicable federal, state and local laws, codes, ordinances and regulations in the performance of this contract.

C.2.14 The Contractor awarded a delivery order is required to submit a Test and Inspection Plan (TIP) and

Production Schedule specific to the delivery order within 24 hours of receipt of award. The TIP and Production

Schedule shall be submitted to the SBS and Quality Assurance Specialist (QAS) prior to start of work for all delivery orders under this contract.

C.2.15 The Contractor shall submit (when required) electronics copies of the Process Control Procedure (PCP) to the SBS for submission to SWRMC Engineering Department as soon as the delivery order is issued for review and approval.

C.2.16 When required, the Contractor shall attend ship checks as specified by the SBS to identify the initial scope of work and to determine the preliminary repair requirements. In the event the Contractor shall be delayed, the

Contractor must contact the SBS immediately.

C.2.17 The Contractor shall be responsible for the removal of all interferences. The Contractor shall reinstall and perform necessary tests to all previously removed interferences/equipment upon completion of repairs IAW 009-23 reference C.1.2.a.

C.3 STATEMENT OF WORK:

C.3.1 Prior to the start of work, the Contractor shall submit an initial Conditions Found Report (CFR) to the COR identifying discrepancies associated with the equipment/area specified in each delivery order. The contractor shall be responsible for any damages or discrepancies not noted in the initial CFR.

C.3.2 Submit one legible electronic copy of subsequent CFR’s identifying discrepancies or damages associated with the description of work to the SBS within four (4) hours of conditions found.

C.3.3 Prior to start of insulation repair work, the Contractor shall ensure that the required Work Authorization Form

(WAF) is properly filled out and authorized in accordance with the ships WAF Program . The authorized WAF shall be posted at the primary and secondary entrances to the location of work. In the event the ship does not have an established WAF program, the Contractor will provide the necessary documents.

C.3.4. For work on Aircraft Carriers, the Contractor shall submit WAFs in sufficient detail so that the ship can provide proper work area isolation. The Contractor shall initiate WAFs in the Information Management System

(IMS). Computer terminals will be made available by Newport News Shipbuilding (NNS) for maintenance providers to enter WAFs directly into this system. Once the WAF is entered in IMS, the Contractor shall print the

WAF, sign the WAF and submit the WAF to the Work Test Control/Maintenance Support Center (WTC/MSC) on the ship for processing and authorization. The Contractor shall be responsible for updating status of the WAF in

IMS as work is authorized and completed.

NOTE: Typical routing for Ship’s Force concurrence requires three (3) days. The Contractor shall establish an account in Electronic-Systems Operations Management System (E-SOMS) in order to produce an Electronic Work

Authorization Form (E-WAF) to obtain ship departmental concurrences via routing on the vessel.

C.3.5 The Contractor shall be responsible for clean-up of any spills or mitigation of hazards associated with the work being performed in accordance with all applicable regulations.

C.3.6 The Contractor shall be responsible for the cleanliness of the working area. All waste created by the

Contractor as a result of the repair work specified herein, shall be removed from the ship at the end of each shift.

C.3.7 All insulation material and mastic shall be considered Asbestos Containing Material (ACM) unless it can be established by laboratory analysis, visual inspection of marking (red adhesive, red dyed cloth, stenciling or affixed metal tag on lagging) or other reliable method(s) that the material does not contain asbestos. This includes all reusable covers.

C.3.8 The Contractor shall comply with the San Diego County Air Pollution Control District (APCD) Rules 361.145 and 361.146. Provide one (1) copy of each written notification submitted to the APCD to the SWRMC; Code 106

Safety Officer, prior to the start of work.

C.3.9 Use of elastomeric foam conforming to MIL-P-15280 and polyphosphazene conforming to MIL-I-24703 is not permitted.

C.3.10 MIL-PRF-22344 insulation shall not be installed on hot piping above one-inch nominal pipe size (nps) and shall be installed only on piping with a vertical orientation or in low traffic areas.

C.4 INSPECTION PROCEDURES:

C.4.1 “(I)” Inspections require verification and documentation by a separate individual, other than the person who has accomplished the work, who is qualified as an inspector and currently certified where required by the technical documents (e.g., NAVSEA Basic Paint Inspector {NBPI}, National Association of Corrosion Engineers {NACE}, nondestructive testing, electrical cable way inspections, etc.).

C.4.2 “(V)” Inspections require verification and documentation by the qualified tradesperson, trade supervisor, or inspector.

C.4.3 “(G)” A symbol inserted in a Work Item to establish a point in the sequence of accomplishment of work at which time the SUPERVISOR shall be notified by the prime contractor in all cases to permit observation of a specific test or inspection “I” “V” by the Government.

C.4.4 For (G) checkpoints scheduled during normal working hours, the Contractor shall notify the SBS of checkpoints via electronic method. Notification shall be at least four (4) hours, but not more than one (1) working day, prior to commencing the specific requirements in the paragraph annotated with the symbol (G). Notify the SBS not later than four (4) hours before the end of the last preceding day shift when tests or inspections following a (G) checkpoint is scheduled after normal day shift working hours, on a weekend, or on a federal holiday. Notify the SBS at least 48 hours, but not more than 72 hours, prior to commencing (G) checkpoints at the Contractor's/Sub-

Contractor’s plants located in excess of 50 miles by the most direct roadway nearest to the place of performance of the contract. Document the date, time, and identification of the SBS notified.

C.4.5 For (G) checkpoints scheduled during normal working hours, the Contractor shall notify the SBS for cancellation of the scheduled test or inspection as soon as known, but no later than one (1) hour prior to the scheduled check point.

C.4.6 For (G) checkpoints scheduled after normal working hours, on a weekend, or a federal holiday, notify the SBS to cancel a scheduled test or inspection as soon as known, but no later than two (2) hours prior to the scheduled check point.

C.5 INSTALLATION REQUIREMENTS:

C.5.1 Delivery orders that include removal of existing insulating materials shall be accomplished IAW 009-10 and

009-23 of reference C.1.2.a.

C.5.2 Remove and dispose of existing insulation materials including anti-sweat and vermiculate compounds.

(V) (G) “SURFACE PREPARATION”

C.5.3 Power tool clean each metal surface exposed by the removal of insulation materials, anti-sweat and vermiculate compounds, free of all loose mil scale, rust, loose paint and other loose foreign matter IAW 009-32 of reference C.1.2.a

C.5.3.1 For delivery orders that involve removal of elastomeric foamed plastic insulation. The Contractor shall remove all glue and tightly adhered remnants of insulation materials prior to SSPC-SP-3 requirements.

(V) (G) “COATING APPLICATION”

C.5.4 Apply primer to each surface prepared in C.5.3 to produce a dry film thickness as applicable to each coating

IAW ,009-32 of reference C.1.2.a.

C.5.4.1 Accomplish the requirements of 009-32 of reference C.1.2.a, as applicable for each coating.

C.5.5 Apply galvanizing repair paint, MIL-P-21035 to each existing zinc coated surface IAW the manufacturer instructions in C.5.4.

C.5.6 All paint applied shall be Volatile Organic Compounds (VOC) compliant.

C.5.7 Installation of new acoustic and thermal type insulation materials within compartments shall be IAW references C.1.2.a and C.1.2.d.

C.5.8 Installation of new acoustic and thermal type insulation materials on ducting shall be in accordance with 009-

11 of references C.1.2.a.

C.5.9 Secure reusable covers using snap fasteners or laced with copper, brass or soft steel galvanized wire through hooks or rings in accordance with 009-11 of reference C.1.2.a.

C.5.10 Accomplish the requirements of 009-32 of reference C.1.2.a for new insulation, lagging and reusable covers to match surrounding areas.

C.5.11 Verify completion of each work order in full and satisfactory condition IAW references C.1.2.a through

C.1.2.e.

C.6 DELAYS AND DISRUPTIONS:

C.6.1 The Contractor shall coordinate his work efforts on a daily basis with the SAR to schedule his work to avoid delays and disruptions. More than one (1) contractor working in the same area is a normal condition encountered during ship repair periods. Delays caused by these events will be at no cost to the Government.

C.6.2 Drills, shifting berths, inspections, serving of meals, ceremonies, additional security requirements, operation of equipment and scheduled meetings are to be considered normal evolutions to be encountered when working on board Naval installations and vessels rather than unusual occurrences. Delays caused by these events will be at no cost to the Government.

C.6.3 The Contractor shall be responsible for the relocation of own equipment in the event of berth shifts, repositioning of the ship and moored outboard another vessel.

C.6.4 The Contractor shall be responsible for coordinating work efforts with other Contractors working in the same or adjacent areas on board naval vessel to ensure no delays.

C.7 PROGRESS MEETINGS/REPORTS:

C.7.1 The Contractor shall participate in daily or weekly progress meeting(s) as required. The Contractor shall be prepared to address all facets of the work including but not limited to schedule and/or problems with the ongoing work and the proposed actions to be taken to resolve these problems.

C.7.2 The Contractor will provide a progress report of all active jobs to the SBS on Monday or the first business day of each week no later than 8:00 am.

C.7.2.1 For work on Aircraft Carriers, the Contractor shall also submit all initial production schedules to Newport

News Shipbuilding (NNS) via SWRMC Code 350, Randy Sopicki at randolph.sopicki@navy.mil, Oscar Ocampo at mailto:randolph.sopicki@navy.mil oscar.ocampo1@navy.mil and Dannie Rios at dannie.rios@navy.mil for integration into the topside schedule.

Initial schedules shall be submitted 3-5 business days prior to the planned start dates. Production schedules shall be developed in Microsoft Project 2000 (minimum), utilizing the Work Breakdown Guidelines (Attachment A). The production schedules shall be revised/updated on a weekly basis. Weekly updates shall be submitted to NNS no later than 1200 Thursday. On the occasion that a Federal Holiday lands on a Thursday, the weekly updates shall be submitted to NNS no later than the Wednesday preceding the Thursday Holiday.

C.8 DELIVERY OF SERVICE:

C.8.1 The Contractor shall commence work on each delivery order within 24 hours of the start of the Period of

Performance (POP). The Contractor must also be capable of performing multiple delivery orders at the same time.

C.8.2 The services to be furnished for the removal, repair, installation of hullboard insulation in the delivery order shall be completed within 12 calendar days after the date of each order placed, except that when the need of the

Government permits, the delivery order may provide a longer time of delivery.

C.9 SECURITY REQUIREMENTS:

C.9.1 The Contractor shall submit a list providing security information to the SWRMC Security Division no later than five (5) days after the contract award date. The data is to include the list of all Contractor personnel supporting the contract effort, social security numbers, addresses, citizenship, level of clearance and radiological controls indoctrination training documents (for CVN contracted work only). The Contractor shall submit a new list whenever there is any change in the security information listing.

C.9.2 The Contractor shall issue each employee an identification card containing the employee's picture, which shall be utilized for positive identification. The card shall be worn in a visible location when employee is on Government property.

C.10 HAZARDOUS WASTE:

C.10.1 All waste generated deemed non-hazardous shall be removed from the pier daily and will not be allowed to accumulate. Waste generated deemed as hazardous shall be removed from the pier no later than the last day of the assigned performance period.

C.10.2 The Contractor shall submit a copy of all reports of chemical analysis or other documents evidencing identification of the hazardous waste to SWRMC Environmental Department Code 106B upon completion of each delivery order.

C.10.3 The analysis of any waste requiring the services of a testing laboratory (e.g., liquids, used cleaning solvent material) shall be performed by a laboratory certified by the California Department of Public Health (CDPH) to be competent and equipped to conduct the specific type of analysis to be performed.

C.10.4 Control of all ACM shall be IAW 009-10 of reference C.1.2.a.

C.10.5 Hazardous waste generated in the performance of this contract shall be disposed of in accordance with

Federal, State and Local regulations.

C.10.6 The Contractor shall comply with the requirements of 40 CFR Part 262-264, Title 22 California Code of

Regulations Div 4.5, Resource Conservation and Recovery Act (RCRA), and other applicable Federal, State and local regulations.

C.10.7 Remove, handle, store, transport and dispose of all hazardous waste in accordance with RCRA.

C.10.8 Ensure that only haulers registered to perform such transportation by cognizant Federal and State agencies accomplish the transportation of hazardous waste.

mailto:oscar.ocampo1@navy.mil mailto:dannie.rios@navy.mil

C.11 STANDARDS OF WORKMANSHIP:

C.11.1 Unless otherwise specifically provided in this contract, the quality of all services rendered hereunder shall conform to the highest standards in the relevant profession, trade or field of endeavor. All services shall be rendered by or supervised directly by individuals fully qualified in the relevant profession, trade, or field, and holding any licenses required by law.

C.11.2 None of the services required by this contract shall be subcontracted to, or performed by persons other than the Contractor or the Contractor’s employees without the prior notification of the Contracting Officer

C.12 BILLING/INVOICING:

C.12.1 At the time of billing/invoicing, the Contractor shall provide to the SBS, two (2) hard copies of all information, (i.e., CFR, Inspection Discrepancy Reports {IDR}, TIP, WAF, check points, inspection reports, and operational test results) compiled during the performance of the work for each delivery order.

C.13 GOVERNMENT FURNISHED MATERIAL (GFM):

C.13.1 None

C.14 CONTRACTOR FURNISHED EQUIPMENT (CFE):

C.14.1 The Contractor shall furnish all necessary materials and equipment to perform work required by this contract.

C.14.2 The Contractor shall be responsible for maintaining all CFE. CFE shall be properly calibrated, tested and in state of repair that is ready for use, to the extent necessary to avoid impacting the performance requirements of this contract.

C.14.3 The Contractor shall ensure all CFE be located neatly out of walk ways and not be a trip hazard.

C.15 NON-NAVY OWNED CRANES:

C.15.1 The Contractor shall adhere to and follow the requirements of reference C.1.2.a, C.1.2.e, C.1.2.f, C.1.2.g and

C.1.2.h.

C.16 ADDITIONAL PROVISIONS:

C.16.1 The Contractor awarded a contract as a result of this solicitation will be required to have in place, no later than the contract award date, a SWRMC approved Quality Management System IAW reference C.1.2.a and the most current International Organization for Standardization (ISO).

C.16.2 The Contractor shall be required to only use products for preservation authorized on the Qualified Products

Database (QPD) in compliance with reference C.1.2.a.

HQ C-1-0001 DATA REQUIREMENTS (NAVSEA) (SEP 1992)

Item(s) 0002 - The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements

List, DD Form 1423, Exhibit(s) Exhibit F, attached hereto.

HQ C-2-0003 ACCESS TO THE NAVY SUPPLY SYSTEM (NAVSEA) (MAR 2011)

(a) In compliance with the comparability requirement of 10 U.S.C. 7314, Public and Private Shipyards will be provided equal access to the Naval Supply System. Use by private yards is permissive, not mandatory.

(b) Pursuant to the clause of this contract entitled "GOVERNMENT SUPPLY SOURCES" (FAR 52.251-1) the

Contracting Officer hereby authorizes the Contractor to place orders with the Navy Supply System for materials and equipment or other supplies necessary to perform the required work. The Naval Supply System shall process such orders in the same manner as it would for any other Navy supply user, and the Contractor shall make payment on account of materials and equipment and other supplies ordered and/or received in accordance with the normal requirements of the Naval Supply Systems Command, but in no event shall payment in full be any later than 30 days after receipt by the Contractor of each order. The Contractor shall pay the Naval Supply System any costs for materials, equipments, or other supplies obtained including any surcharges normally charged to any other Naval

Supply System user.

(c) This job order has been priced on the basis that, except as specifically provided elsewhere in this contract with regards to Government furnished property, the Contractor shall provide all necessary materials, equipments and supplies for performance of this contract. If the Contractor uses the Naval Supply System, it has elected to use the system for its own convenience to meet its contractual obligations to perform the work under this contract. The

Naval Supply System is considered to be an alternate source or vendor of contractor furnished material; therefore materials, equipments, or other supplies ordered and/or obtained from the Naval Supply System are specifically not considered to be Government furnished material, but are considered to be contractor furnished material. The

Government makes no representation as to the availability of materials, equipments, or other supplies for the performance of the work required under this contract, nor shall unavailability, late delivery, delivery of non-conforming supplies, higher costs of the Naval Supply System (if any), or any failure of the Naval Supply System to meet the expectations or requirements of the Contractor constitute excusable delay or grounds for equitable or any other adjustment to the contract or relief from the requirement to perform in accordance with the terms of the

HQ C-2-0004 ACCESS TO THE VESSEL(S) (AT) (NAVSEA) (JAN 1983)

Officers, employees and associates of other prime Contractors with the Government and their subcontractors, shall, as authorized by the Supervisor, have, at all reasonable times, admission to the plant, access to the vessel(s) where and as required, and be permitted, within the plant and on the vessel(s) required, to perform and fulfill their respective obligations to the Government. The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Supervisor to be given admission to the plant and access to the vessel(s) for office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of the respective responsibilities involved, and reasonable to their performance.

HQ C-2-0005 ACCESS TO VESSELS BY NON-U.S. CITIZENS (NAVSEA) (DEC 2005)

(a) No person not known to be a U.S. citizen shall be eligible for access to naval vessels, work sites and adjacent areas when said vessels are under construction, conversion, overhaul, or repair, except upon a finding by

COMNAVSEA or his designated representative that such access should be permitted in the best interest of the

United States. The Contractor shall establish procedures to comply with this requirement and NAVSEAINST

5500.3 (series) in effect on the date of this contract or agreement.

(b) If the Contractor desires to employ non-U.S. citizens in the performance of work under this contract or agreement that requires access as specified in paragraph (a) of this requirement, approval must be obtained prior to access for each contract or agreement where such access is required. To request such approval for non-U.S. citizens of friendly countries, the Contractor shall submit to the cognizant Contract Administration Office (CAO), an Access

Control Plan (ACP) which shall contain as a minimum, the following information:

(1) Badge or Pass oriented identification, access, and movement control system for non-U.S. citizen employees with the badge or pass to be worn or displayed on outer garments at all times while on the Contractor's facilities and when performing work aboard ship.

(i) Badges must be of such design and appearance that permits easy recognition to facilitate quick and positive identification.

(ii) Access authorization and limitations for the bearer must be clearly established and in accordance with applicable security regulations and instructions.

(iii) A control system, which provides rigid accountability procedures for handling lost, damaged, forgotten or no longer required badges, must be established.

(iv) A badge or pass check must be performed at all points of entry to the Contractor's facilities or by a site supervisor for work performed on vessels outside the Contractor's plant.

(2) Contractor's plan for ascertaining citizenship and for screening employees for security risk.

(3) Data reflecting the number, nationality, and positions held by non-U.S. citizen employees, including procedures to update data as non-U.S. citizen employee data changes, and pass to cognizant CAO.

(4) Contractor's plan for ensuring subcontractor compliance with the provisions of the Contractor's ACP.

(5) These conditions and controls are intended to serve as guidelines representing the minimum requirements of an acceptable ACP. They are not meant to restrict the Contractor in any way from imposing additional controls necessary to tailor these requirements to a specific facility.

(c) To request approval for non-U.S. citizens of hostile and/or communist-controlled countries (listed in Department of Defense Industrial Security Manual, DOD 5220.22-M or available from cognizant CAO), Contractor shall include in the ACP the following employee data: name, place of birth, citizenship (if different from place of birth), date of entry to U.S., extenuating circumstances (if any) concerning immigration to U.S., number of years employed by

Contractor, position, and stated intent concerning U.S. citizenship. COMNAVSEA or his designated representative will make individual determinations for desirability of access for the above group. Approval of ACP's for access of non-U.S. citizens of friendly countries will not be delayed for approval of non-U.S. citizens of hostile communist-controlled countries. Until approval is received, Contractor must deny access to vessels for employees who are non-U.S. citizens of hostile and/or communist-controlled countries.

(d) The Contractor shall fully comply with approved ACPs. Noncompliance by the Contractor or subcontractor serves to cancel any authorization previously granted, in which case the Contractor shall be precluded from the continued use of non-U.S. citizens on this contract or agreement until such time as the compliance with an approved

ACP is demonstrated and upon a determination by the CAO that the Government's interests are protected. Further, the Government reserves the right to cancel previously granted authority when such cancellation is determined to be in the Government's best interest. Use of non-U.S. citizens, without an approved ACP or when a previous authorization has been canceled, will be considered a violation of security regulations. Upon confirmation by the

CAO of such violation, this contract, agreement or any job order issued under this agreement may be terminated or default in accordance with the clause entitled "DEFAULT (FIXED-PRICE SUPPLY AND SERVICE)" (FAR

52.249-8), "DEFAULT (FIXED-PRICE RESEARCH AND DEVELOPMENT)" (FAR 52.249-9) or

"TERMINATION (COST REIMBURSEMENT)" (FAR 52.249-6), as applicable.

(e) Prime Contractors have full responsibility for the proper administration of the approved ACP for all work performed under this contract or agreement, regardless of the location of the vessel, and must ensure compliance by all subcontractors, technical representatives and other persons granted access to U.S. Navy vessels, adjacent areas, and work sites.

(f) In the event the Contractor does not intend to employ non-U.S. citizens in the performance of the work under this contract, but has non-U.S. citizen employees, such employees must be precluded from access to the vessel and its work site and those shops where work on the vessel's equipment is being performed. The ACP must spell out how non-U.S. citizens are excluded from access to contract work areas.

(g) The same restriction as in paragraph (f) above applies to other non-U.S. citizens who have access to the

Contractor's facilities (e.g., for accomplishing facility improvements, from foreign crewed vessels within its facility, etc.)

(h) An ACP which has been approved for specific Master Ship Repair Agreement (MSRA) or Agreement for Boat

Repair (ABR) or Basic Ordering Agreement (BOA), is valid and applicable to all job orders awarded under that agreement.

HQ C-2-0006 ADDITIONAL PROVISIONS RELATING TO GOVERNMENT PROPERTY (NAVSEA) (SEP

2009)

(a) For purposes of paragraph (h) of the clause entitled "GOVERNMENT PROPERTY" (FAR 52.245-1) in addition to those items of property defined in that clause as Government Property, the following shall also be included within the definition of Government Property:

(1) the vessel;

(2) the equipment on the vessel;

(3) movable stores;

(4) cargo; and

(5) other material on the vessel

(b) For purposes of paragraph (b) of the clause entitled "GOVERNMENT PROPERTY", notwithstanding any other requirement of this contract, the following shall not be considered Government Property:

(1) the vessel;

(2) the equipment on the vessel;

(3) movable stores; and

(4) other material on the vessel

HQ C-2-0007 APPROVAL BY THE GOVERNMENT (AT) (NAVSEA) (JAN 1983)

Approval by the Government as required under this contract and applicable specifications shall not relieve the

Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.

HQ C-2-0008 ASSIGNMENT AND USE OF NATIONAL STOCK NUMBERS (NAVSEA) (MAY 1993)

To the extent that National Stock Numbers (NSNs) or preliminary NSNs are assigned by the Government for the identification of parts, pieces, items, subassemblies or assemblies to be furnished under this contract, the Contractor shall use such NSNs or preliminary NSNs in the preparation of provisioning lists, package labels, packing lists, shipping containers and shipping documents as required by applicable specifications, standards or Data item

Descriptions of the contract or as required by orders for spare and repair parts. The cognizant Government Contract

Administration Office shall be responsible for providing the Contractor such NSNs or preliminary NSNs which may be assigned and which are not already in possession of the Contractor.

HQ C-2-0009 ASSIGNMENT OF SERIAL NUMBER(S) (NAVSEA) (SEP 1990)

The Contractor shall request serial number assignment, in writing, from the Cognizant Technical Program Office, with a copy to the cognizant Contract Administration Office. The request for serial number assignment shall contain the following minimum information:

(a) Contract number;

(b) Assigned line item number and description;

(c) Assigned type designation;

(d) Assigned model number;

(e) Top drawing number and ID (List of Drawings) number;

(f) Exact quantity for which serial numbers are being requested, including preproduction samples required by the contract; and

(g) National Stock Number

HQ C-2-0014 CONTRACTOR'S PROPOSAL (NAVSEA) (MAR 2001)

(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with detailed obligations to which the Contractor committed itself in their Proposal in response to SWRMC Solicitation No. N55236-

15-R-0002.

(b) The technical volume(s) of the Contractor's proposal is incorporated by reference and hereby made subject to the provisions of the "ORDER OF PRECEDENCE" (FAR 52.215-8) clause of this contract. Under the "ORDER OF

PRECEDENCE" clause, the technical volume of the Contractor's proposal referenced herein is hereby designated as item

(f) of the clause, following "the specification" in the order of precedence.

HQ C-2-0016 DEPARTMENT OF LABOR SAFETY AND HEALTH STANDARDS FOR SHIP REPAIR

(NAVSEA) (SEP 1990) (MODIFIED) (SEP 2012)

Attention of the Contractor is directed to the Occupational Safety and Health Act of 1970 (29 USC 651-678), and to the Safety and Health Regulations for Ship Repairing (29 CFR 1915), promulgated under Public Law 85-742, amending Section 41 of the Longshoremen's and Harbor Workers' Compensation Act (33 USC 941), and adopted by the Department of Labor as occupational safety or health standards under Section 6(a) of the Occupational Safety and Health Act of 1970 (See 29 CFR 1910.15). These regulations apply to all ship repair and related work, as defined in the regulations performed under this contract on the navigable waters of the United States including any dry dock and marine railway. Nothing contained in this contract shall be construed as relieving the Contractor from any obligations which it may have for compliance with the aforesaid regulations.

HQ C-2-0024 EXTENSION OF COMMERCIAL WARRANTY (NAVSEA) (NOV 1996)

The Contractor shall extend to the Government the full coverage of any standard commercial warranty normally offered in a similar commercial sale, provided that such warranty is available at no additional cost to the

Government. The Contractor shall provide a copy of the standard commercial warranty with the item. The standard commercial warranty period shall begin upon the final acceptance of the applicable material or software.

Acceptance of the standard commercial warranty does not waive the Government’s rights under the “Inspection” clause, nor does it limit the Government’s rights with regard to other terms and conditions of the contract. In the event of a conflict, the terms and conditions of the contract shall take precedence over the standard commercial warranty.

HQ C-2-0028 GOVERNMENT SURPLUS PROPERTY (NAVSEA) (SEP 1990)

No former Government surplus property or residual inventory resulting from terminated Government contracts shall be furnished under this contract unless (i) such property is identified in the Special Contract Requirements or (ii) is approved in writing by the Contracting Officer. Notwithstanding any such identification in the Special Contract

Requirements or approval by the Contracting Officer, the Contractor agrees all items or components described in this requirement shall comply in all respects with the specifications contained herein.

HQ C-2-0029 HEAVY WEATHER PLAN (NAVSEA) (JUN 1999)

In order to ensure that Naval vessels and material are protected during gales, storms, hurricanes and destructive weather, the Contractor is required to have a written Heavy Weather Plan (HWP) which assigns responsibilities and prescribes actions to be taken on the approach of and during heavy weather conditions as delineated in NAVSEA

Standard Item (SI) 009-69. In accordance with SI 009-69, the Contractor shall furnish to the cognizant

Shipbuilding, Conversion and Repair, U.S. Navy, a copy of such HWP, and shall make such changes in the plan as the Supervisor considers necessary and reasonable to protect and care for vessels and machinery and equipment to be installed therein.

In the event the Supervisor directs the Contractor to implement the HWP pursuant to SI 009-69 the Contractor may submit to the Contracting Officer a request for reimbursement for costs resulting from such actions together with any documentation that the Contracting Officer may reasonably require. The Government shall reimburse the

Contractor for all reasonable, allowable and allocable costs resulting from the Contractor's implementation of the

HWP based on such Government direction.

HQ C-2-0030 INFORMATION AND DATA FURNISHED BY THE GOVERNMENT (FIXED-PRICE)

(NAVSEA) (JAN 2008)

(a) Contract Specifications. The Government will furnish, if not included as an attachment to the contract, any unique contract specifications set forth in Section C.

(b) Contract Drawings and Data. The Government will furnish contract drawings, design agent drawings, ship construction drawings, and/or other design or alteration data cited or referenced in Section C or in the contract specification as mandatory for use or for contract performance.

(c) Government Furnished Information (GFI). GFI is defined as that information essential for the installation, test, operation, and interface support of all Government Furnished Material enumerated on NAVSEA Form 4205/19 or

Schedule A, as applicable, attached to the contract. The Government shall furnish only the GFI identified on the

NAVSEA Form 4340/2 or Schedule C, as applicable, attached to the contract. The GFI furnished to the contractor need not be in any particular format. Further, the Government reserves the right to revise the listing of GFI on the

NAVSEA Form 4340/2 or Schedule C, as applicable, as follows:

(1) The Contracting Officer may at any time by written order:

(i) delete, supersede, or revise, in whole or in part, data listed or specifically referenced in NAVSEA

Form 4340/2 or Schedule C, as applicable; or

(ii) add items of data or information to NAVSEA Form 4340/2 or Schedule C, as applicable; or

(iii) establish or revise due dates for items of data or information in NAVSEA Form 4340/2 or Schedule

C, as applicable.

(2) If any action taken by the Contracting Officer pursuant to subparagraph (1) immediately above causes an increase or decrease in the costs of, or the time required for, performance of any part of the work under this contract, the contractor may be entitled to an equitable adjustment in the contract price and delivery schedule in accordance with the procedures provided for in the clause of this contract entitled "CHANGES--FIXED-PRICE"

(FAR 52.243-1).

(d) Except for the Government information and data specified by paragraphs (a), (b), and (c) above, the

Government will not be obligated to furnish the Contractor any specification, standard, drawing, technical documentation, or other publication, notwithstanding anything to the contrary in the contract specifications, the GFI listed on the NAVSEA Form 4340/2 or Schedule C, as applicable, the clause of this contract entitled Government

Property (FAR 52.245-1) as applicable, or any other term or condition of this contract.

(e) Referenced Documentation. The Government will not be obligated to furnish Government specifications and standards, including Navy standard and type drawings and other technical documentation, which are referenced directly or indirectly in the contract specifications set forth in Section C and which are applicable to this contract as specifications. Such referenced documentation may be obtained:

(1) From the ASSIST database via the internet at…