Quality Assurance Surveillance Plan (QASP)

Project: Repair Oily Water Treatment System Tanks 3C and 6A

Place of Performance: Puget Sound Naval Shipyard and Intermediate Maintenance Facility.

Requirement PWS

Paragraph

Performance Standards Allowable Deviation Surveillance Method Correction Procedures

Completed Pre-Work Documents prior to Notice-to-Proceed

1.4.1 Contractor shall provide a

Quality Management Plan (QCP) to Post Award Conference for in-person review/edits

Contractor shall not deviate from the requirement.

Contracting Officer, COR, Contract Specialist, and other applicable Government Personnel will review finalized copy of QCP submitted within one business day after Post Award Conference

Failure to submit the QCP by the deadline will result in a delay of Notice to Proceed, this will not be a basis for Period of Performance Extension.

Cleaned and prepared tank for weld repairs.

1.4.2 Contractor shall clean and

prepare the interior tank to the cleanliness level required for welding/hot work in the oily water tanks.

Contractor shall not deviate from the requirement.

COR will perform weekly inspections and at delivery of a cleaned and prepared tank ready for weld repairs.

Government will not accept nonconforming services and require corrections to be made prior to acceptance. A delay from rework is not a basis for a period of performance extension. No additional cost will be charged to the Government for rework and Government will seek an equitable price reduction of 1% of this work item if delay exists.

Completed Tanks meet all PWS standards.

1.4.3 Contractor shall perform the

weld repair, maintain STI certification, install cathodic protection, perform pneumatic pressure test, maintain certifications to perform industrial tank lining work, install tank lining system, provide an independent STI/NACE qualified inspector to certify tank lining is acceptable, and complete ASTM F718-07.

Contractor shall not deviate from the requirement

COR will perform weekly inspections and at delivery of completed weld repairs, completed cathodic protection, completed pneumatic pressure test, completion of tank lining system installation.

Government will not accept nonconforming services and require corrections to be made prior to acceptance. A delay from rework is not a basis for a period of performance extension. No additional cost will be charged to the Government for rework and Government will seek an equitable price reduction of 1% of this work item if delay exists.

Requirement PWS

Paragraph

Performance Standards Allowable Deviation Surveillance Method Correction Procedures

Install the high-level alarm sensor, high-level alarm, stainless steel guide cables and the emergency shut-off valve system

1.4.4 Contractor shall obtain and

install the equipment following the manufacturer’s instructions.

Contractor shall not deviate from the requirement

COR will perform weekly inspections and at completion of high-level alarm sensor high-level alarm, stainless steel guide cable, and emergency shut-off valve system installation.

Government will not accept nonconforming services and require corrections to be made prior to acceptance. A delay from rework is not a basis for a period of performance extension. No additional cost will be charged to the Government for rework and Government will seek an equitable price reduction of 1% of this work item if delay exists.