This is a Standard Form 30 (SF 30) Amendment of Solicitation issued by Puget Sound Naval Shipyard IMF on February 11, 2026, for solicitation N4523A26Q4004. The amendment extends the response due date from February 11, 2026 at 1400 hours to February 18, 2026 at 1400 hours, providing offerors one additional week to submit proposals. The amendment was issued by the Puget Sound Naval Shipyard in Bremerton, Washington and administered under code N4523A, with contact information for Andrew Smith at the facility.

The amendment modifies delivery schedules outlined in FAR clause 52.211-9 (Desired and Required Time of Delivery). The desired delivery schedule remains 20 weeks after receipt of order (ARO) for both CLIN 0001 (4 each) and CLIN 0002 (1 group), while the required delivery schedule has been extended from 20 weeks ARO to 26 weeks ARO for both line items. Offerors unable to meet the desired schedule may propose alternative delivery dates but must not exceed the required 26-week ARO deadline, with proposals exceeding this period subject to rejection as nonresponsive. Acknowledgment of this amendment is required prior to the new proposal submission deadline through completion of amendment items, acknowledgment on offer copies, or separate written communication referencing the solicitation and amendment numbers.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section A - Solicitation/Contract Form

The following changes have been made:

INFORMATION FROM TO

Response Due Date 11 Feb 2026 18 Feb 2026

N4523A26Q40040001

Section F - Deliveries or Performance

The following clauses were modified:

52.211-9 Desired and Required Time of Delivery. Jun 1997 hereby reads as follows:

Desired and Required Time of Delivery (June 1997)

(a) The Government desires delivery to be made according to the following schedule:

Desired Delivery Schedule

Item No. Quantity Delivery Date

CLIN 0001 4 EACH 20 Weeks ARO

CLIN 0002 1 GROUP 20 Weeks ARO

If the offeror is unable to meet the desired delivery schedule, it may, without prejudicing evaluation of its offer, propose a delivery schedule below.

However, the offeror's proposed delivery schedule must not extend the delivery period beyond the time for delivery in the Government's required delivery schedule as follows:

Required Delivery Schedule

Item No. Quantity Delivery Date

CLIN 0001 4 EACH 26 Weeks ARO

CLIN 0002 1 GROUP 26 Weeks ARO

Offers that propose delivery of a quantity under such terms or conditions that delivery will not clearly fall within the applicable required delivery period specified above, will be considered nonresponsive and rejected. If the offeror proposes no other delivery schedule, the desired delivery schedule above will apply.

Offeror's Proposed Delivery Schedule

Item No. Quantity Within Days After Date of Contract

CLIN 0001 4 EACH ____

CLIN 0002 1 GROUP ____

(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed or otherwise furnished to the successful offeror results in a binding contract. The Government will mail or otherwise furnish to the offeror an award or notice of award not later than the day the award is dated. Therefore, the offeror shall compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the Contractor's date of receipt of the contract or notice of award by adding (1) five calendar days for delivery of the award through the ordinary mails, or (2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically. (The term "working day" excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered nonresponsive and rejected.

(End of clause)

IDCode: J
Page: 1
Pages: 4
AmendNo: 0001
EffDate: 11 Feb 2026
ReqNo: See Continuation Sheet
ProjNo:
IssCode: N4523A
AdmCode:
IssuedBy: PUGET SOUND NAVAL SHIPYARD IMF

1400 FARRAGUT AVE, BREMERTON WA 98314-5001

BREMERTON, WA 98314-5001

UNITED STATES

Andrew Smith, Email: andrew.r.smith7.civ@us.navy.mil Telephone: 360-277-7905 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: N4523A26Q4004
SolDate: 30 Jan 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: This Amendment is issued to change the Block 8 offer due date and time from Wednesday,11 February 2026, 1400 hours, to Wednesday,18 February 2026, 1400 hours. Also, the delivery dates in Section F - Deliveries or Performance, Clause 52.211-9 are being changed as follows; the "Desired Delivery Schedule" is being changed from 1 April 2026, to "20 Weeks ARO." The "Required Delivery Schedule" is being changed from "20 Weeks ARO," to "26 Weeks ARO."
ContNameTitle:
CoNameTitle: EDWIN BALDORIA
ContDate:
CODate: 11 Feb 2026