C09.0 Amendment 0002 Questions and answers for N4523A23Q5734 15 Ton Crane Supply.pdf
PDF 57 KB Posted
- Attached to
- PSNS IMF Bremerton WA 15 Ton Crane
- Solicitation number
- N4523A23Q5734
About this file
This document contains questions and answers regarding solicitation N4523A23Q5734 for a 15 Ton Crane Supply at PSNS IMF Bremerton WA. CLIN 0002 in the solicitation allows pricing for the manufacture and fabrication of the crane at the contractor's facility, including shop testing. CLIN 0003 allows pricing for shipping, installation, and testing of the crane once delivered. The Navy confirmed that no bid bond is required for this requirement. Dimensions of building interferences could not be provided, as contractors are required to perform their own crane envelope survey to obtain this information per the specification.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C09.0 N4523A23Q5734 Amendment 001.pdf | ||
| C08.0 Attachment 1 SOW 6.14.23.pdf | ||
| C08.0 N4523A23Q5734.pdf | ||
| C08.0 Attachment 2 Badging and Access Requirements.pdf | ||
| C08.0 Attachment 3 Corporate Experience Data Sheet.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and answers for N4523A23Q5734 15 Ton Crane Supply
Question 1: The RFP does not have a Contract Line Item Number (CLIN) for the purchasing from manufacturing subcontractors, fabrication & Shipping of the crane. Can you please inform us which of the three CLIN on the project should include the manufacture, fabrication and shipping?
Answer 1: CLIN 0002 allows pricing for the manufacture and fabrication of the crane. CLIN 0002 states: Shop Test 15 Ton Min Capacity Crane/Perform assembly at Contractor's Facility and perform all shop tests of 15 ton crane in accordance with the Statement of Work.
CLIN 0003 allows pricing for shipping of the crane. CLIN 0003 states: Installation Of 15 Ton Min Capacity Crane/ Perform removal of existing crane, perform installation and supply of 15 Ton crane in accordance with the Statement of Work. Provide testing, inspection and training for final acceptance of installed crane IAW the SOW.
Question 2: Can you please confirm that this project requires a bid bond?
Answer 2: This requirement does not require a bid bond.
Question 3: Per section 2.2.3 Crane Requirements: “The cab shall be located to afford a minimum of 3 inches clearance from all fixed structures within its area of possible movement.”
Can PSNS please provide the dimensions for building light above the finished floor, the height from the finished floor to the highest building equipment interfaces/ measurement from ground to highest obstruction to create estimates that include requirements of section 2.2.3.
Answer 3: No, we cannot provide those dimensions as that information is held by 980/NAVFAC. But the spec puts this in the contractor's hands to get this information themselves in section 1.6.3 of the specification. They will get this info for themselves when they do their crane envelope survey.
File details come from the government source that posted it. Updated .