J-13_NSE_Pier_Load_Limit_Summary.pdf

PDF 127 KB Posted

Attached to
USS SAMPSON 8C1 DSRA Federal contract opportunity
Solicitation number
N4523A-18-R-0550
Issued by
Department of the Navy Naval Sea Systems Command

View the file

Other files for this federal contract opportunity

Other files attached to USS SAMPSON 8C1 DSRA, newest first.
File Type Posted
BQ_029_-_J-14_Section_B_Note_A_Redacted.pdf PDF
SA_82710K_HED_Notional_POAM_from_DDG_101_-_HED_MSProj_19Jan16.pdf PDF
J-18_Access_and_User_Agreement_rev_003_02122018.pdf PDF
BQ_028_980-90-007_clarification_Redacted.pdf PDF
555-8749121_Rev_A,_HYBRID_ELEC_DRIVE_PIPING_-_FIRE_PROTN_MODS_&_ML.pdf PDF
262-8749116_Rev_A,_HYBRID_ELEC_DRIVE_PIPING_-_OIL_SYS_MODS_&_ML.pdf PDF
505-8718348-PIPE20_REV-A_SANITARY_PIPE_MODS.pdf PDF
512-8718350-VENT52_REV-A_VENTILATION_MANUFACTURING_DETAILS.pdf PDF
N4523A-18-R-0550_Amendment_0008.pdf PDF
BQ_21_123-21-001_-_Redacted.pdf PDF
BQ_023_Missing_Refs_-_Redacted.pdf PDF
BQ_018_123-10-001_-_Redacted.pdf PDF
BQ_024_Missing_Ref_-_Redacted.pdf PDF
BQ_008_Extension_Request_-_Answered_01-16-18_Redacted.pdf PDF
J-1_Work_Package_Errata_5_-_Addendum_1.pdf PDF
J-1_Work_Package_Errata_5_-_Addendum_1.pdf PDF
BQ_017_992-31-001_-_Answered_1-16-18_Redacted.pdf PDF
N4523A-18-R-0550_J-12_Pre-Proposal_Information_(PPI)_Form_Q_008_-_Answered_09JAN18_Redacted.pdf PDF
BQ_003_J-2_Tech_Manuals_-_Answered_1-5-18_Redacted.pdf PDF
N4523A-18-R-0550_J-12_Pre-Proposal_Information_(PPI)_Form_Q_015_Map_3.pdf PDF
N4523A-18-R-0550_J-12_Pre-Proposal_Information_(PPI)_Form_Q_013_Redacted.pdf PDF
J-18_Access_and_User_Agreement_rev_001_01032018.pdf PDF
N4523A-18-R-0550_J-12_Pre-Proposal_Information_(PPI)_Form_Q_004_Redacted.pdf PDF
N4523A-18-R-0550_J-12_Pre-Proposal_Information_(PPI)_Form_Q_012_Redacted.pdf PDF
N4523A-18-R-0550_J-12_Pre-Proposal_Information_(PPI)_Form_Q_015_Redacted.pdf PDF
J-1_Work_Package_Errata_4.pdf PDF
NFPA_70,_National_Electrical_Code.pdf PDF
J-16_CDRL_A034_Technical_Report_-_Configuration.pdf PDF
J-16_CDRL_A009_Work_Completion_Certification.pdf PDF
J-8_Contractor_Proposal_Guide.pdf PDF
J-16_DIDs_Package.pdf PDF
59312-3-005_Rev_A,_VCHT_Tank_Level_Indicator_Sensor_Test.pdf PDF
J-9_Env_Guide_For_Contractors_at_NSE_-_May16.pdf PDF
J-19_Contractor_FRP_Matrix.xlsx XLSX spreadsheet
J-16_CDRL_A020_PCB_Risk_Assessment.pdf PDF
MIL-STD-2003-3A.pdf PDF
J-16_CDRL_A016_GFP_&_Forecasting_Report.pdf PDF
J-7_POAM_-_AIT.pdf PDF
49_U.S.C_5103,_Federal_Hazardous_Materials_Transportation_Act.pdf PDF
J-16_CDRL_A032_Key_Events_Schedule.pdf PDF
J-16_CDRL_A011_Training_&_Qual_Rprt.pdf PDF
J-16_CDRL_A012_KTR_Firewatch_Trng_Prgm.pdf PDF
J-16_CDRL_B007_Logistics_Mgmt_-_Data_Product.pdf PDF
J-16_CDRL_A015_GFP_Deficiency_Report.pdf PDF
AMRDEC_Instructions_for_Solicitation_N4523A-18-R-0550.docx DOCX document
J-16_CDRL_A023_List_of_Subcontractors_Rprt.pdf PDF
J-5_Schedule_Model_Review.pdf PDF
J-6_QASP.pdf PDF
J-16_CDRL_A008_Test_and_Inspection_Plan.pdf PDF
J-14_Pricing_Workbook_111517_(ECN).xlsx XLSX spreadsheet
Show all 50

USS SAMPSON 8C1 DSRA has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revision: 21 July 2010\TJC

Naval Station Everett, Washington

Pier A - Load Limit Summary Deck Loading Summary:

Uniform Load:

• 1000 psf(1)(2)

Truck Load:

• HS20-44(1)(2)

Mobile Cranes:

• 140-ton capacity, outrigger maximum 233.5 kips, see restrictions below.(1)(2)(3)

• 70- ton capacity, outrigger maximum 151 kips, no restricted areas.(1)(3)

• 70-ton and 140-ton travel lift, HS20-44 maximum single or dual axle loading.(1)

Restrictions:

• Do not place crane within 3’ of deck storm centerline or expansion joints(1)

• Do not place crane or outriggers on yellow striped areas.(1)

• Do not place crane on utility trench covers or pier electric vault roof(1)

• Use pads if outrigger placed on or adjacent to utility trench cover(4)

• Utility trench cover maximum outrigger load is 151 kips(2)(3)

Structural Inspection Summary:

• Waterfront Inspection 2009, Report #CR-6521-ONC dtd Jan. 2010

References:

(1) Pier A Contract # N62474-88-C-4438 Sheet S-02 As-Built dtd Oct. 1992

(2) Carrier Pier Basis of Design Vol IA Contract # N62474-85-C-5366 dtd Aug. 1986

(3) MIL-HNBK 1025/1 Piers and Wharfs Oct. 1987

(4) NAVFAC Navy Crane Center, P-307 Weight Handling Equipment Dec. 2009

Abbreviations/Definitions:

psf Pounds per Square Foot kips Kilo-Pounds or One Thousand Pounds Travel Lift Driving/traveling crane with a suspended load when permitted by OEM.(4)

HS20-44 Front single axle with single tires 8,000 lbs, rear axles with dual tires 32,000 lbs Each with multiple rear axle spacing 14 feet

Enclosure (5)

NAVSTAEVERETTINST 11450.1

Deck Loading Summary:

Uniform Load:

• 750 psf(1)(2)

Truck Load:

• HS20-44(1)(2)

Mobile Cranes:

• 140-ton capacity, outrigger maximum 187 kips, see restrictions below.(1)(2)(3)

• 90-ton capacity, out rigger maximum 187 kips, no restricted areas (1)(2)(3)

• 90-ton and 140-ton travel lift, HS20-44 maximum single or dual axle loading.(1) (3)

Restrictions:

• Do not place crane within 3’ of deck storm west side or expansion joints(2)

• Outrigger maximum 187 kips on utility trench covers(1)(2)

• Do not place crane or outriggers on yellow striped areas.(2)

• Use pads if outrigger placed on or adjacent to utility trench cover(3)

Structural Inspection Summary:

• Structural Waterfront Inspection 2009, Report #CR-6521-ONC dtd Jan. 2010

Reference:

(1) P-205 Breakwater Pier Basis of Design Calculations 100% Submittal Contract # N62474-85-C-5233 dtd Nov. 1993

(2) Pier B Contract # N62474-92-C-3518 Sheet S-01 As-Built dtd Dec. 1995

(3) MIL-HNBK 1025/1 Piers and Wharfs Oct. 1987

(4) NAVFAC Navy Crane Center, P-307 Weight Handling Equipment Dec. 2009

Abbreviations/Definitions:

psf Pounds per Square Foot kips Kilo-Pounds or One Thousand Pounds Travel Lift Driving/traveling crane with a suspended load when permitted by OEM.(4)

HS20-44 Front single axle with single tires 8,000 lbs, rear axles with dual tires 32,000 lbs Each with multiple rear axle spacing 14 feet.

Naval Station Everett, Washington

Pier B - Load Limit Summary

Uniform Load:

• 110 psf(1)

Truck Load:

• Light GOVs only as necessary (1)

• H155XL2 Fork Lift maximum lift limited to 9,000 lbs. (1)

• Pumper Truck gross vehicle weight limited to 29,000 lbs.(1)

Mobile Cranes:

• No Crane Operations(1)

Restrictions:

• No POVs(1)

• Due to the current state of Pier Delta concentrated loads are not permitted(1)

Structural Inspection Summary:

• Study Evaluation of Pier Delta and Echo, Contract # N44255-01-D-1035/0003 dtd Jun. 2003

• Waterfront Structural Inspection 2009: Pier D, Contract # N62473-06-D-3028 dtd Jan. 2010

Reference:

(1) Waterfront Structural Inspection 2009: Pier Delta, Contract # N62473-06-D-3028 dtd Jan. 2010

Abbreviations:

psf Pounds per Square Foot kips Kilo-Pounds or One Thousand Pounds GOV Government Owned Vehicles POV Privately Owned Vehicles

Naval Station Everett, Washington

Pier D - Load Limit Summary

Uniform Load:

• 225 psf(1)

Truck Load:

• Light GOVs only as necessary (1)

• H155XL2 Fork Lift maximum lift limited to 3,000 lbs.(1)

• Pumper Truck gross vehicle weight limited to 22,000 lbs

Mobile Cranes:

• No Crane Operations(1)

Restrictions:

• No POVs (1)

• Due to the current state of Pier Echo, no heavy point loads may be applied to the deck until further restoration or structure replacement has occurred(1)

Structural Inspection Summary:

• Study Evaluation of Pier Delta and Echo, Contract # N44255-01-D-1035/0003 dtd Jun. 2003

• Waterfront Structural Inspection 2009: Pier Echo, Contract # N62473-06-D-3028 dtd. Jan. 2010

Reference:

(1) Waterfront Structural Inspection 2009: Pier Echo Contract # N62473-06-D-3028 dtd Jan. 2010

Abbreviations:

psf Pounds per Square Foot kips Kilo-Pounds or One Thousand Pounds GOV Government Operated Vehicles POV Privately Owned Vehicles

Naval Station Everett, Washington

Pier E - Load Limit Summary

Uniform Load:

• 750 psf(1)

Truck Load:

• HS20-44(1)

Mobile Cranes:

• 140-ton capacity, outrigger maximum 187 kips, see restrictions below.(1)(2)

• 90-ton capacity, out rigger maximum 187 kips, no restricted areas (1)(2)

• 90-ton and 140-ton travel lift, HS20-44 maximum single or dual axle loading.(1)(2)

Restrictions:

• Do not place crane within 3’ of deck storm drains or expansion joints(1)

• Do not place crane or outriggers on yellow striped areas.(1)

• Outrigger maximum 187 kips on utility trench covers(1)

• Use pads if outrigger placed on or adjacent to utility trench cover

Structural Inspection Summary:

• Waterfront Structural Inspection 2009, Report #CR-6521-ONC dtd Jan. 2010

Reference:

(1) South Wharf; Contract # N62474-88-C-4438, Sheet S-02 As Built, dtd Oct. 1992

(2) MIL-HNBK 1025/1 Piers and Wharfs Oct. 1987

(3) NAVFAC Navy Crane Center, P-307 Weight Handling Equipment Dec. 2009

Abbreviations:

psf Pounds per Square Foot kips Kilo-Pounds or One Thousand Pounds Travel Lift Driving/traveling crane with a suspended load when permitted by OEM.(3)

HS20-44 Front single axle with single tires 8,000 lbs, rear axles with dual tires 32,000 lbs Each with multiple rear axle spacing 14 feet.

Naval Station Everett, Washington

South Wharf - Load Limit Summary

Uniform Load:

• 600 psf (1)

Truck Load:

• HS20-44(1)

Mobile Cranes:

• 90-ton capacity with a maximum outrigger load of 187 kips on a 5’x5’ footprint or designated area (1)

Restrictions:

• Crane outrigger and vehicle loads positioned 20 ft from Bent 1 , Row A and Bent 22, Row J due to deteriorated piling(2)

Structural Inspection Summary:

• Waterfront Structural Inspection, Report #CR-6521-OCN dtd Jan. 2010

References:

(1) North Wharf Contract 93-C-3507 Sheet G-1 As-Built dtd Dec. 1994

(2) Waterfront Structural Inspection, Report #CR-6521-OCN, B-17 Figure 5, dtd Jan. 2010

Abbreviations:

psf Pounds per Square Foot kips Kilo-Pounds or Thousand Pounds HS20-44 Front single axle with single tires 8,000 lbs, rear axles with dual tires 32,000 lbs Each with multiple rear axle spacing 14 feet.

Naval Station Everett, Washington

North Wharf - Load Limit Summary

Naval Station Everett, Washington