YTB_BID_Q_1).docx
DOCX document 22 KB Posted
- Attached to
- YTB-836 Habor Tug Federal contract opportunity
- Solicitation number
- N4523A-17-R-0009
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N4523A-17-R-0009_Amendment_4.pdf | ||
| 017_RFC_YTB-836.pdf | ||
| 013_RFC_YTB-836.pdf | ||
| 012_RFC_YTB-836.pdf | ||
| 009_RFC_YTB-836.pdf | ||
| 016_RFC_YTB-836.pdf | ||
| 014_RFC_YTB-836.pdf | ||
| 011_RFC_YTB-836.pdf | ||
| 010_RFC_YTB-836.pdf | ||
| 015_RFC_YTB-836.pdf | ||
| N4523A-17-R-0009_Amendment_3.pdf | ||
| 205-4563432A1_Stack_Detail.pdf | ||
| YTB_836__5-Way_Breakdown_Sheet_Erratta_1.xls | XLS spreadsheet | |
| 008_RFC.pdf | ||
| 007_RFC.pdf | ||
| Amend_2.pdf | ||
| 006_RFC.docx | DOCX document | |
| 004_RFC.docx | DOCX document | |
| 003._RFC.docx | DOCX document | |
| 005_RFC.docx | DOCX document | |
| REQUEST_FOR_SPECIFICATION_CLARIFICATION_0002.docx | DOCX document | |
| amend_1.pdf | ||
| Dec15YTB_836__5-Way_Breakdown_WKG.xls | XLS spreadsheet | |
| REQUEST_FOR_SPECIFICATION_CLARIFICATION.docx | DOCX document | |
| CDRL_&_DID.pdf | ||
| N4523A-17-R-0009.pdf | ||
| YTB_836__5-Way_Breakdown_WKG.xls | XLS spreadsheet | |
| SOW_YTB_836_FY17.pdf |
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR SPECIFICATION CLARIFICATION
| DATE OF REQUEST: 12/12/16 | QUESTION NO:001 | |
| REQUIREMENT: Docking & Undocking the Vessel | REQUISITION NO.: N4523A-17-R-0009 ITEM NO: 3.1 | ISSUING OFFICE POC(CODE 446): |
| TITLE: Docking Procedure | LeAundria Shaheed: (360) 476-4053 leaundria.shaheed@navy.mil |
PARA. NO: 3.1.2 PAGE NO: 22 CONTRACTOR: PLANNER 'S NAME: ATTACH. NO: NIA CONTRACTOR POC & PHONE:
CONTRACTOR QUESTION: (ONE QUESTION PER PAGE)
Ifawarded the contract, the contractor would dock the vessel at Port Townsend Boat Yard. However, the total weight of the vessel including the fwd & aft towing winches exceeds The boat lift limit. Would it be allowable to remove both winches at a pier at Naval Station Everett prior to docking and reinstall at Everett after undocking ? All this would be included Inthe contractors quote and completed within the POP.
DO NOT WRITE BELOW THIS LINE
| SPEC CHG: YIN | I DWG/REF CHG. YIN |
| I RQMTS CHG: YIN | I MAT'L CHG: YIN |
| TECHNICAL REVIEW: |
| I SERIAL NO: |
Government cannot accommodate work at Naval Station Everett.