Dust Collector Q A.docx

DOCX document 15 KB Posted

Attached to
Professional Engineer for Dust Collector
Solicitation number
N4215822QA001
Issued by

View the file

Other files

File Type Posted
N4215822QA001 Amendment.pdf PDF
Attachment 3 Workstation 3.doc DOC document
Attachment 4 Workstation 4.doc DOC document
Attachment 8 2021 Shop 57 IH Survey 49.pdf PDF
Attachment 6 Workstation 7.doc DOC document
Attachment 2 Bandsaw Room.docx DOCX document
Attachment 7 Workstation 10.doc DOC document
Attachment 5 Workstation 5.doc DOC document
N4215822QA001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Q:Not a licensed engineer as most of my non-government projects do not require. Would I be eligible for consideration?
A:No, you must have a Professional Engineering license valid in a state of the USA.

2. Q: Inspection of dust collectors is completed twice a year at other facilities, is this a service the base needs?

A:No, we need a PE to analyze our shop ventilation requirements, design a new system, and write specifications for a new dust collector and ducting that will provide the required ventilation for safe work operations.
3. Q:Is a Virginia PE license required to submit a proposal?

A: I am willing to accept a PE license that is valid in any state of the US.

4. Q: Are there existing system drawings available that can be viewed prior to issuing a proposal? We have referenced item 6.1.7., et al., and would like additional detail. At a minimum, our team would like to know the existing system flow rate, in addition to the number of collection points, to give a sense of how large the system is.

A: Yes, I will provide a drawing of the shop floor. I have attached drawings of the workstations from the Industrial Hygienists that show details of the collection points. I have attached an IH survey with flow rate readings.

5. Q: Are there existing AutoCAD layout drawings of the building, ductwork, and equipment that will be made available for use for potential demo and layout drawings?

A: Yes, I will provide these.

6. Q: When do they tentatively expect the field measurement to occur?

A: Anytime during the POP.

7. Q: When does the engineering phase need to be complete?

A: October 15, 2022