N4215821QS033 Questions and Answers.pdf
PDF 114 KB Posted
- Attached to
- Vertical Lift Module (VLM) and Carousel Assembly
- Solicitation number
- N4215821QS033
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Statement of Work.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTION 1: In order to complete the assembly as requested in solicitation N4215821QS033 of the equipment listed below it will be necessary for the Shipyard to provide one
(1) temporary power drop for each of the assembly areas (see voltage requirement in red). Is this possible?
ANSWER 1: YES.
Equipment Electrical Specification:
1. Kardex Remstar Vertical Lift Module for Tool Cage. 480VAC 3Phase 15A
2. Kardex Remstar Vertical Lift Module for Nuclear Area. 480VAC 3Phase 15A
3. Kardex Remstar Flange Storage vertical carousel unit, Model number RS
350.1.3050.6.305.40., for Nuclear use. 480VAC 3Phase 6A
4. Kardex Remstar Flange Storage vertical carousel unit, Model number RS
350.1.3050.6.305.40., for Non-nuclear use. 480VAC 3Phase 6A
QUESTION 2: Can all four machines be installed within the same install interval or would the
VLM's need to be installed, then the Carousels?
ANSWER 2: All four machines shall be installed within the same install interval.
QUESTION 3: These machines require quite a bit of packaging, oversize pallets and crates so do we need to provide pricing for our own dumpsters (30 yd. per machine) or is the Navy responsible for providing these dedicated dumpsters?
ANSWER 3: The Navy is responsible for providing these dedicated dumpsters.
QUESTION 4: It is my understanding these machines were received some time ago? If the case, all items would need to be delivered to the jobsite in order for us to determine if any parts are missing. We cannot determine if parts are missing until we totally de-palletize and unbox each item. This must be done at the install site, not at the current offsite staging location.
ANSWER 4: All items will be delivered to the jobsite in order for the contractor to determine if any parts are missing.
QUESTION 5: To verify, Offers’ must only submit a capabilities package? Or is there a Section
B or pricing sheet for a Price quote as well?
ANSWER 5: No, quotes must include price(s), FOB destination, a point of contact, name and phone number, business size, and payment terms. Quotes shall be submitted in either Microsoft
Word, Excel Spreadsheet, or Adobe PDF. Vendors shall provide a detailed (unpriced) capabilities statement for review and acceptance by the Technical POC.
QUESTION 6: Is there an incumbent for this effort? If so, who are they, what was their winning bid, contract number, and the former SOW?
ANSWER 6: There is no incumbent.