This project table of contents outlines the specifications for repairs to Substation 7 at Portsmouth Naval Shipyard. The project provides for updating several electrical components in Substation 7, including three-phase pad-mounted transformers, SF6/high-firepoint fluids insulated pad-mounted switchgear, switchboards, electric meters, and lightning protection systems. Minor repairs are also required for Building 165. Relevant work includes excavation and filling, foundation drilling and grouting, hot-mix asphalt paving, and chain link fencing and gates. The solicitation was issued by the Department of the Navy Naval Facilities Engineering Command for project number N4008520B2556. Completion of the work will improve the reliability of electrical systems at the naval shipyard facility.

View the file

Other files for this federal contract opportunity

Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

100% Final Design Submission RM 16-1224 Repairs to Substation 7 February 2020

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 15 LIST OF DRAWINGS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00.00 22 WORK RESTRICTIONS (PWD ME) PNSY PROJECTS

01 20 00.00 22 PRICE AND PAYMENT PROCEDURES (PWD ME) DESIGN-BID-BUILD

PROJECTS

01 30 00.00 22 ADMINISTRATIVE REQUIREMENTS (PWD ME)

01 31 23.13 22 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT

MANAGEMENT SYSTEM

01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES

01 33 00 SUBMITTAL PROCEDURES

01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES

01 35 26.00 22 GOVERNMENTAL SAFETY REQUIREMENTS (PWD ME)

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.10 22 QUALITY CONTROL FOR MINOR CONSTRUCTION PWD ME

01 50 00.00 22 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS (PWD ME)

01 57 19.00 22 TEMPORARY ENVIRONMENTAL CONTROLS - PORTSMOUTH NAVAL

SHIPYARD (PWD ME)

01 74 19.00 22 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT (PWD ME)

01 78 00.00 22 CLOSEOUT SUBMITTALS (PWD ME)

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 24.00 22 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT

INFORMATION (eOMSI)

01 86 26.07 40 RELIABILITY CENTERED ACCEPTANCE FOR ELECTRICAL SYSTEMS

DIVISION 02 - EXISTING CONDITIONS

02 32 00 SUBSURFACE DRILLING, SAMPLING, AND TESTING

02 41 00 DEMOLITION

02 42 91 REMOVAL AND SALVAGE OF HISTORIC CONSTRUCTION MATERIALS

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

02 82 00.00 22 ASBESTOS REMEDIATION (PNS PROJECTS)

02 83 00 LEAD REMEDIATION

02 83 00.00 22 LEAD, CHROMIUM, AND CADMIUM REMEDIATION (PNS PROJECTS)

02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs)

DIVISION 03 - CONCRETE

03 01 00 REHABILITATION OF CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

03 45 33 PRECAST STRUCTURAL CONCRETE

DIVISION 04 - MASONRY

04 03 00 CONSERVATION TREATMENT FOR PERIOD MASONRY

DIVISION 05 - METALS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 60 00 FLASHING AND SHEET METAL

PROJECT TABLE OF CONTENTS Page 1

100% Final Design Submission RM 16-1224 Repairs to Substation 7 February 2020

07 84 00 FIRESTOPPING

DIVISION 08 - OPENINGS

08 01 52 OPERATION AND MAINTENANCE OF WOOD WINDOWS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

DIVISION 09 - FINISHES

09 01 90.50 PREPARATION OF HISTORIC WOOD AND METAL SURFACES FOR

PAINTING

09 06 00 SCHEDULES FOR FINISHES

09 90 00 PAINTS AND COATINGS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 82 46.00 40 ELECTRIC UNIT HEATERS

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 33 DOCKSIDE POWER CONNECTION STATIONS

26 08 00 APPARATUS INSPECTION AND TESTING

26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS

26 13 00 SF6/HIGH-FIREPOINT FLUIDS INSULATED PAD-MOUNTED SWITCHGEAR

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 13 SWITCHBOARDS

26 27 13.10 30 ELECTRIC METERS

26 41 00 LIGHTNING PROTECTION SYSTEM

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 10 00 CLEARING FOR CIVIL WORKS

31 23 00.00 22 EXCAVATION AND FILL

31 32 23 FOUNDATION DRILLING AND GROUTING

31 60 00 FOUNDATION PREPARATION

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 31 13 CHAIN LINK FENCES AND GATES

DIVISION 33 - UTILITIES

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 23.19 MONORAIL HOISTS

PROJECT TABLE OF CONTENTS Page 2

CUSTOM SUPPLEMENTAL SPECIFICATION SECTIONS

N/A N/A

VOLTAGE REGULATORS

TRANSPORTABLE BREAKER LIFT SYSTEM

-- End of Project Table of Contents --