This document is an errata notice updating a federal contract specification package for roof repairs on a Navy barge. The errata replaces items in the original package and deletes or revises certain requirements. The work involves a visual inspection of the barge roof to identify discrepancies, installation of certified fall protection, and submission of an inspection report. It also requires filling depressions and irregularities, properly shaping the roof for drainage, and applying a new roof coating system and sealant to the entire roof area. The contractor must meet all security requirements and quality standards for working in the secure area where the barge is located.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THIS PERMANENT CHANGE UPDATES THE SPECIFICATION BID PACKAGE.
SHIP: IX-516 (RMC 22275)
SERM-016-20
ERRATA NUMBER:
SPECIFICATION NUMBER:
THE FOLLOWING ITEMS ARE REPLACED:
150-11-001
DATED: 12/12/2019 12:04:36PMPage 1 of 1
SHIP: IX-516 (RMC 22275) ITEM NO: 150-11-001 (E2)
COAR: 28 PCN: None
BWST FILE NO: 000-001 CMP: NONE
REVISED: 05 Apr 2019 PLANNER: See Attachment A
SSP: SERM-016-20 1 of 3 ITEM NO: 150-11-001
ERRATA NO. 2
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Re-seal Barge Roof; accomplish
1.2 Location of Work:
1.2.1 IX-516 Barge, 4th Level, Weather
1.3 Identification:
1.3.1 Quantity (18,720 SF); Sheathing, Roof, Detail One of 2.3
2. REFERENCES:
2.1 Standard Items
2.2 OSHA 1915, Maritime Requirements
2.3 150-6396670 Rev O, Details
2.4 150-6396666, Roof Secondary and Cross Section
2.5 150-6396667 Rev O, Roof Details
2.6 150-6396681, Bolt Schedule for Roof Framing
2.7 MIL-PRF-24667 Rev C, Coating DELETEDSystem, MS-880G Flexible Epoxy Nonskid Deck Coating
(E1)
3. REQUIREMENTS:
3.1 Accomplish DELETEDa visual inspection of the IX-516 roof area and identify each discrepancies found. Ensure all personnel wear fall protection equipment during the visual inspection of the roof area in accordance with 2.2. Install and certify fall protection equipment on the roof of the IX-516 in order to support work on the IX-516 barge in accordance with 2.2 through 2.6. Contractor shall ensure all anchoring points of the fall protection equipment installed are tested and certified in accordance with 2.2 through 2.6 prior to the start of the work.
(E2)
3.1.1 Submit DELETEDone legible copy in hard copy or approved transferrable media, of a report listing the requirements of 3.1 to the SUPERVISOR
(E2)
3.1.2 Accomplish DELETEDthe requirements of 009-09 of 2.1 for the reseal of roof coated in 1.3.
(E2)
3.2 Install DELETEDnew roof coating system and sealant to the entire roof area. Fill depressions, low spots, irregularities, and shape for proper drainage to the entire roof area listed in 1.3 and located in 1.2, using 2.3 through 2.6.
(E2)
3.2.1 Accomplish DELETEDan inspection of the newly installed roof coating system at location listed in.1.2. Verify all depressions, low spots, and irregularities are filled and properly shaped for drainage of the entire roof area listed in 1.3 and located in 1.2, (E2)
SSP: SERM-016-20 2 of 3 ITEM NO: 150-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
using 2.3 through 2.6. Ensure there is no standing water.
3.3 Accomplish DELETEDthe requirements of OO9-32 of 2.1 for new and disturbed surface.
(E2)
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
SSP: SERM-016-20 3 of 3 ITEM NO: 150-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.