N3904026Q5724_ LSJ_Redacted.pdf
PDF 162 KB Posted
- Solicitation number
- N3904026Q5724
About this file
This is a Justification for Use of Other Than Full and Open Competition memorandum for a simplified acquisition threshold procurement.
The government seeks to purchase 22 APC Uninterruptible Power Supply (UPS) batteries, Part #SYBT5, with a required delivery date of September 1, 2026. The justification for single-source procurement is based on brand name requirements. The batteries are specifically designed by APC as direct replacements for the UPS unit installed within the ESE-1 system, which supports security operations for refueling projects. The memorandum states that these batteries cannot be substituted with equivalent products and that their replacement is manufacturer-required due to battery lifecycle limitations. The procuring agency determined that market research indicates other companies' similar products or products lacking the particular APC specifications do not meet the agency's needs and cannot be modified to satisfy requirements.
The memorandum was technically certified by Joseph Zagami on June 11, 2026, and approved by Contracting Officer Michael L. McCluskey on June 22, 2026. This documentation fulfills FAR 13.106-3(b)(3)(i) requirements to justify the absence of competition for this acquisition under the simplified acquisition threshold.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N3904026Q5724_ RFQ.pdf | ||
| N3904026Q5724_ Attachment 2 OPSEC.pdf | ||
| N3904026Q5724_Attachment 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(This is only applicable to acquisitions under the Simplified Acquisition Threshold. Acquisition using FAR Subpart 13.5 shall follow the special documentation requirements at FAR 13.501.)
USE OF OTHER THAN FULL AND OPEN COMPETITION FOR AN ACQUISITION
UNDER THE SIMPLIFIED ACQUISITION THRESHOLD
I. BACKGROUND:
1. FAR 13.106-1(b)(1)(i) states for purchases not exceeding the simplified acquisition threshold, Contracting Officers may solicit from one source if the Contracting Officer determines that the circumstances of the contract action deem only one source reasonably available (e.g., urgency, exclusive licensing agreements, brand-name or industrial mobilization).
2. As required by FAR 13.106-3(b)(3)(i), this memorandum explains the absence of competition for this acquisition, as only one source will be solicited for this requirement (or for a portion of the requirement) and the requirement is not expected to exceed the simplified acquisition threshold.
II. DESCRIPTION OF ITEM OR SERVICE:
Provide a description of the item or service required, to include its intended use, the name of the required source or brand name, and the required delivery date/period of performance.
Item to purchase is (22) brand name APC Uninterruptible Power Supply (UPS) batteries Part#SYBT5. RDD is 9/1/2026
III. THE DETERMINATION FOR USE OF OTHER THAN FULL AND OPEN
COMPETITION IS BASED ON THE FOLLOWING (select all that apply):
A. ___ ONLY ONE RESPONSIBLE SOURCE (select all that apply):
1. ___ RESTRICTIVE RIGHTS. The source has established proprietary rights, limited rights in data, patent rights, copyrights or secret processes in the item or service required.
Explain what rights are restricted, why the restrictive rights make the required item or service available from only one source, and why another company could not satisfy the Government�s need.
2. ___ EXCLUSIVE LICENSING AGREEMENTS. The item or service is only available from the Original Equipment Manufacturer (OEM), or there is only one authorized distributor or technical representative for the OEM.
Identify the OEM and explain the circumstances surrounding why the item or service is only available from the OEM.
OR
Identify the distributor(s)/authorized technical representative(s) for the item or service. Provide evidence of the exclusive licensing agreement as an attachment to this document. NOTE: If there is more than one distributor/authorized technical representative for an OEM part, then Part B, BRAND NAME SOLE SOURCE, is applicable, and Part A, ONLY ONE RESPONSIBLE SOURCE, should be left blank).
3. ___ OTHER REASONS. Other reason not identified above. Provide details on mission impact if requirement is not solicited from only one source.
B. _X__ BRAND NAME. Item required must be a brand name product, or feature of a product, particular to one manufacturer. Discuss why you are precluding consideration of a product manufactured by another company. Describe how the particular brand name, product, or feature is essential to the Government�s requirements and why a �brand name or equal� purchase description cannot be used (see FAR 11.104). Describe how market research indicates other companies� similar products or products lacking the particular feature do not meet, or cannot be modified to meet, the agency�s needs.
The requested (22) APC UPS Part #SYBT5 batteries are specific to the UPS that is installed within the ESE-1. The UPS is used to support security operations for refueling projects. These batteries are specifically designed by the manufacturer of the UPS to be a direct replacement and cannot be substituted. Replacement of the batteries is required by the manufacturer due to battery lifecycles.
C. ___UNUSUAL AND COMPELLING URGENCY. The supplies or services are of such unusual and compelling urgency that the Government would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits bids or proposals.
Urgent requirements are supplies or services that will result in a work stoppage, or are mission critical and the routine processing time would result in injury to the Government. The determination that the procurement for the above item/service is an urgent and compelling requirement is based on the following:
1. Date on which the requirement was first identified:
2. Required delivery date/period of performance:
3. Explanation of why delivery/commencement of services by the date mentioned above is required: Explain the impact to the mission if the date above is not met, any special circumstances or conditions that exist which validate the requirement as �urgent,� estimated production lead time for the item, etc.
4. If appropriate, include any additional pertinent information:
IV. CERTIFICATIONS/APPROVALS: