Statement_of_Work_(WARTSILA_SEALS)_Redacted.pdf
PDF 59 KB Posted
- Attached to
- Wartsila Defense Shaft Seal Maintenance
- Solicitation number
- N39040-17-T-0126
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) for Shaft Seal Work onboard
1. Introduction
1.1. Scope/Brief description of the project
Observe Portsmouth Naval Shipyard (PNS) employees as they replace shaft seals in order to provide consultation and prevent potential problems and liability.
1.2. Place of Performance
, Portsmouth Naval Shipyard, shaft seal assembly.
1.3. Estimated Period of Performance for the following CLINs/TGIs:
CLIN0001: and ‐
CLIN0002: ‐
CLIN0003: and ‐
CLIN0004: ‐
Note: One day prior and one day after the PoP is assumed for travel. At the beginning of the PoP for CLIN0001, one additional day preceding the work is needed for security badging and training
(6010 Bells and Whistles) on‐site.
1.4. References
1.4.1 SUBSAFE Memorandum of Agreement
1.4.2 NAVSEA 0924‐062‐0010 Rev C, CHG‐5, Submarine Safety (SUBSAFE) Requirements
Manual
2. Contractor Requirements
2.1. On award of this contract, meet with Portsmouth Naval Shipyard (PNS) Code 200S (SUBSAFE
Program Office) to review and sign a Memorandum of Agreement (MOA). Reference 1.4.1 shall be signed by all parties prior to start of this Work Item in accordance with Reference 1.4.2.
2.2. This Statement of Work contains SUBSAFE work as defined by 1.4.2. SUBSAFE work may not be outsourced to a non‐NAVSEANOTE 5000 activity without prior PNS Code 200S and NAVSEA approval.
2.3. SUBSAFE interference removed and reinstalled under this Work Item requires Reentry Controls
(REC) in accordance with Reference 1.4.2.
2.4. The contractor is present as a technical consultant to observe and advise as the seals are replaced to prevent potential problems and liability, specifically during the following TG!s:
Statement of Work (SOW) for Shaft Seal Work onboard
2.4.1.
2.4.2.
2.4.3.
2.4.4.
2.4.5.
2.4.6.
3. Qualifications (as required per contract)
4. Base Access/Security requirements
4.1. Security clearance is required at yellow badge level minimum, red badge preferred.
4.2. Rapidgate procedures to acquire clearances for all workers will be followed.
5. Applicable documents
5.1. TGIs as listed in part 2 above, Contractor Requirements, which include Installation Instructions.
File details come from the government source that posted it. Updated .