04.PWS.pdf
PDF 103 KB Posted
- Attached to
- 55k Ultra High Pressure Diesel Husky Pump Repair
- Solicitation number
- N32253-25-SIMACQ-PHNS-970-0003
About this file
This Performance Work Statement (PWS) details maintenance and repair requirements for three 55K Ultra High Pressure Diesel Husky pumps at Pearl Harbor Naval Shipyard and Intermediate Maintenance Facility (PHNSY & IMF). The specific scope involves a Manufacturer Trained and Certified Technician performing maintenance services on three Flow Model Pumps (Serial Numbers 616-15981, 1116-16157, and 1116-16177), which includes comprehensive tasks such as overall condition review, pump inspection, PLC (Programmable Logic Controller) replacement, software upgrades, and providing detailed service reports.
Key performance requirements mandate 100% delivery and compliance, with the contractor responsible for troubleshooting, diagnostics, repair, and operational testing. The work will be performed on-site at Pearl Harbor Naval Shipyard in the Controlled Industrial Area during normal working hours (0630-1500), Monday through Friday, excluding federal holidays. Contractor personnel must be U.S. citizens, pass a background check, obtain proper access badges, and comply with all shipyard rules, regulations, and safety protocols. The contract includes specific requirements for quality control, reporting, workmanship, and adherence to safety, environmental, and security guidelines specified in attached appendices.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PEARL HARBOR NAVAL SHIPYARD AND INTERMEDIATE MAINTENANCE FACILITY
(PHNSY & IMF)
Shop 71 Flow Diesel Husky Pumps Maintenance and Repair
1. BACKGROUND
Pearl Harbor Naval Shipyard & Intermediate Maintenance Facility (PHNSY & IMF) is a US Navy regional industrial center that maintains, overhauls, and repairs various vessels of the US Navy. Its industrial operations provide the US Naval forces with a wide range of services and resources located on the island of Oahu, Hawaii with direct and indirect support to SSN 688 class and Virginia class submarines, surface vessels and shore based activities in the Pacific. To accomplish some of our work, there is a need for sound functioning equipment that requires maintenance and repairs.
2. OBJECTIVE AND SCOPE
PHNSY & IMF, Code 970, Shop 71 Painters/Blasters seeks a contractor to provide the required maintenance and repairs on three 55K Ultra High Pressure Diesel Husky pumps. Contractor shall be a
Manufacturer Trained and Certified Technician. Contractor shall provide services to include troubleshooting/diagnostics, repair, and operational testing of the following equipment:
FLOW Model Pumps to be serviced:
55K #4 (S/N 616-15981)
55K #5 (S/N 1116-16157)
55K #6 (S/N 1116-16177)
3. PERFORMANCE REQUIREMENTS
The contractor shall provide repair services. Contractor shall perform PLC replacement on the units listed in section 2. The repair schedule to be determined by government representative and coordinated with the contractor for the following equipment:
55K #4 (S/N 616-15981)
55K #5 (S/N 1116-16157)
55K #6 (S/N 1116-16177)
4. MAINTENANCE REQUIREMENTS
A. Overall Condition Review
B. Inspect Husky pump
C. Inspect and identify problems with PLC (Programmable Logic Controller) and all parts recommended to be replaced
D. Software upgrades
E. Replace PLC F. Provide service report of work performed, with any recommendations for additional repairs needed
4.1 Repair Parts: The contractor shall advise the Contracting Officer’s Representative (COR) if any parts replacement is not covered under this contract. Contractor shall not proceed with any repairs not covered under this contract without authorization from the Contracting Officer (KO).
4.2 Workmanship: The contractor shall ensure work is performed by qualified, certified, and/or trained personnel to service equipment listed in, “3. PERFORMANCE REQUIREMENTS.”
4.3 Reports: The contractor shall provide maintenance logs for all serviced equipment listed in, “3.
PERFORMANCE REQUIREMENTS” to Technical Point of Contact (TPOC). Reports shall be received within 14 business days from the completion of work. Contractor to invoice within 7 calendar days of maintenance service visit. 100% delivery and compliance.
5. SERVICE DELIVERY SUMMARY
Performance Requirement PWS Paragraph Notes Performance Threshold
1. Perform Maintenance Paragraph 4.A thru 4.F
100% delivery and compliance.
2. Maintenance Logs Paragraph 4.3
100% delivery and compliance.
6. QUALITY ASSURANCE
6.1 If requested by government, the contractor is responsible for implementing and maintaining a Quality
Control Plan (QCP), which shall consist, at a minimum, a written report identifying any repairs/adjustment performed for correction of potential and actual problems. The report shall also state any initial “out of tolerance” measurements identified.
6.2 The QCP shall outline the contractor’s plan to ensure the quality of deliverables as outlined in this PWS.
The QCP shall address what will be reviewed and outline actions to be taken by the contractor.
7. CONTRACTOR QUALIFICATIONS/REQUIREMENTS
7.1 The contractor shall ensure the necessary employee level of expertise for performance of the deliverables described by this PWS and the necessary management and administrative support associated with personnel, equipment and services provided.
7.2 Contractor shall comply with Safety and Health work practices specified in Appendix I.
7.3 Contractor shall comply with environmental guidelines specified in Appendix II.
7.4 Contractor shall comply with Security requirements specified in Appendix III.
7.5 The contractor shall pass a background check to gain access onto the base and obtain a PHNSY & IMF
“Green” unescorted standard access control badge.
8. GOVERNMENT FURNISHED UTILITIES AND SERVICE
8.1 GENERAL: None provided. The Government will not provide any additional services, material, or government furnished equipment as part of this PWS.
8.2 UTILITIES: The contractor may utilize existing facility electrical, water, and/or low pressure air outlets to perform the work. However, the contractor shall be responsible for any damages that may result from the operation of contractor’s equipment.
9. SECURITY
9.1 The contractor shall pass a background check to gain access onto the base. The contractor will coordinate with the TPOC or COR to obtain a gate pass at building 3455 Pass Office. It is not unusual for the pass process to take an hour or more. Contractor shall be a U.S. citizen and pass a security background check.
Only those individuals with favorable investigations shall be utilized on this contract. Prior to the start of work, the contractor shall provide the COR (on company letterhead) a request for access and include the following information – full name of all personnel working on this contract; social security number; date of birth, place of birth, and citizenship. The contractor shall state that the information has been verified and shall have supporting records on file if required for examination. The contractor’s employees must be a
U.S. citizen and registered with the Defense Biometric Identification System (DBIDS).
9.2 Contractor personnel shall follow all procedures in requesting and obtaining a PHNSY & IMF “Green” unescorted standard access control badge for all contractor personnel performing work. Sufficient time shall be allowed by the contractor to obtain the necessary badges prior to work.
9.3 Contractor will coordinate with PHNSY Security Office and COR in the completion of Visit Request for
Pearl Harbor Naval Shipyard (Form PH-SYD 5512/28). Should contractor personnel receive or suspect they have learned classified information beyond their level of clearance; the contractor shall identify and immediately report suspicions to the COR.
9.4 Security Requirements: This contract does not require a security clearance level and clearance granted by the Defense Security Service (DSS). Contractor shall comply with Security requirements specified in
Appendix III.
10. CONTRACTOR PERSONNEL
10.1 The contractor shall comply with Public Law 105-270, Section 5(2)(A), which states that contractors will not perform inherently governmental functions. Section 5(2)(A) of this Public Law defines the term
“inherently governmental function” as “a function that is so intimately related to the public interest as to require performance by Federal Government employees.” Per Section 5(2)(B), inherently governmental functions include management of Government programs requiring value judgments, conduct of foreign relations, selection of program priorities, and the direction of intelligence and counter-intelligence operations. Per Section 5(2) (C), inherent governmental functions DO NOT include, (i) gathering information for or providing advice, opinions, recommendations, or ideas to Federal Government officials;
or (ii) any function that is primarily ministerial and internal in nature.”
10.2 Contractor personnel shall not establish an employee-employer relationship with Government personnel under this contract.
10.3 Contractor personnel shall not manage, supervise, or task Government employees or military personnel.
Contractor personnel may not make any commitment to non-DoD personnel, including a foreign official, which commits the expenditure of U.S. Government resources.
10.4 The contractor shall not provide personal services.
10.5 Contractor personnel shall make clear to all individuals they engage with that they are contractor employees and not Government employees. When participating and introducing themselves during official events wherein Government, non-Government, or foreign personnel are present, contractor personnel shall identify themselves as employees of the contractor. Contractor personnel must be clearly identified (i.e.
company shirt, pin, visible company ID, etc.) in a visible location as to who their employer is.
10.6 Facilities may close due to local or national emergencies, administrative closings, or other Government directed facility closings. Contractor access to Government facilities during closures is not permitted.
10.7 Personnel: In accordance with current Department of Defense and Homeland Security requirements, performance of all work under this contract is restricted to US citizens. Contractor personnel performing services shall be required to comply with all Pearl Harbor Naval Shipyard and IMF rules, regulations, and training that is applicable to conduct, safety, security, and procedures governing site entry and exit. All regulations, procedures and access/security requirements shall be obtained prior to the first day of contract performance. It is the responsibility of the Contractor to process and obtain all approvals and allow for sufficient processing time to secure access and entry to PHNSY & IMF.
11. PLACE OF PERFORMANCE
The place of performance shall be on-site at Pearl Harbor Naval Shipyard, in the Controlled Industrial Area
(CIA).
HOURS OF OPERATION: All work shall be performed during the normal working hours of 0630 to 1500 hours, daily Monday through Friday, excluding Federal Holidays.
New Year’s Day 1st of January
Dr. Martin Luther King’s Birthday 3rd Monday in January
President’s Day 3rd Monday in February
Memorial Day 4th or 5th Monday in May
Juneteenth 19th of June
Independence Day 4th of July
Labor Day 1st Monday in September
Columbus Day 2nd Monday in October
Veteran’s Day 11th of November
Thanksgiving Day 4th Thursday in November
Christmas Day 25th of December
If the Federal holiday falls on a Saturday, the holiday is observed on the preceding Friday. If the Federal holiday falls on a Sunday, the holiday is observed on the following Monday.
12. ATTACHMENTS
APPENDIX I – SAFETY AND HEALTH WORK PRACTICES FOR CONTRACTORS WORKING
WITH PEARL HARBOR NAVAL SHIPYARD AND INTERMEDIATE MAINTENANCE FACILITY
(PHNSY & IMF) (REV. JULY 2024)
APPENDIX II – CONTRACTOR ENVIRONMENTAL SPECIFICATION GUIDELINES (REV. OCT 16,
2019)
APPENDIX III – SECURITY REQUIREMENTS APPLICABLE FOR PEARL HARBOR NAVAL
SHIPYARD & IMF’S CONTROLLED INDUSTRIAL AREA, OTHER SENSITIVE AREAS,
CONTROLLED NUCLEAR INFORMATION AREAS, AND/OR NUCLEAR WORK AREAS (REV.
MAY 2024)