This draft Performance Work Statement (PWS) details training requirements for Phased Array Ultrasonic Testing (PAUT) and Time of Flight Diffraction (TOFD) training for Non-Destructive Testing Inspectors at Pearl Harbor Naval Shipyard & Intermediate Maintenance Facility (PHNSY & IMF). The training requires a contractor to provide two training sessions on Oahu, Hawaii, delivering 96 hours of PAUT and 80 hours of TOFD training to 12 students over a 4-consecutive week period. The training must be BINDT accredited and utilize Olympus/Evident branded Phased Array Flaw Detectors and Software.
Key performance requirements include providing comprehensive training manuals, diagnostic hardware, props (including 20 butt welds in plate props), tools (6 OmniScan X3 Phased Array Machines, 12 sets of arrays and encoders), and delivering certificates of completion and assessment. The contract is structured as a base year with four option years, with training dates for option years to be determined. Contractor personnel must pass background checks, comply with shipyard security requirements, and be certified to BINDT/PCN standards. Training will be conducted Monday through Friday (and Saturday if necessary) between 0630-1700 hours, with specific timing varying slightly between PAUT and TOFD sessions.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
PAUT and TOFD Training for PEARL HARBOR NAVAL SHIPYARD (PHNSY & IMF)
1.0 BACKGROUND:
Pearl Harbor Naval Shipyard & Intermediate Maintenance Facilities (PHNSY&IMF), a US Navy industrial facility located on the island of Oahu, Hawaii maintains, overhauls and repairs various vessels of the US Navy. Over 4,500 militaries, civilian and contractor personnel work to keep the Navy, “Fit to Fight”.
2.0 SCOPE AND OBJECTIVE:
2.1 C135 NDT Inspectors are required to receive a minimum 96 hours of training for Phased Array Ultrasonic Testing (PAUT) and a minimum of 80 hours of training for Time of Flight Diffraction Ultrasonic Testing (TOFD). Contractor shall provide two training sessions in a government provided classroom on the island of Oahu at Pearl Harbor Naval Shipyard or similar facility. The contractor will provide PAUT (2 weeks) and TOFD (2 weeks) Training to 12 students in a 4 consecutive week period. The specific amount of students will be provided prior to scheduling of the training. Scheduled training dates will be coordinated with a government representative, in which contractor will be given 30 days’ notice prior to training start within the Period of Performance.
2.2 PAUT training is typically a 96 hour course that provides students the knowledge and skills needed to successfully complete certification testing.
2.3 TOFD training is typically an 80 hour course that provides students the knowledge and skills needed to successfully complete certification testing.
2.4 Period of Performance are for a Base year plus four (4) option years. For the option years, the PAUT and TOFD training dates are not predetermined and will be scheduled after or upon the exercising of the option.
3.0 PERFORMANCE REQUIREMENTS:
3.1 All training (PAUT & TOFD) shall be a BINDT accredited training course.
3.2 The Contractor shall provide all management and labor. In addition, contractor shall provide the following:
1. Tools to include a minimum of 6ea. OmniScan X3 Phased Array Machines, 12 sets of 64 element arrays complete with zero degree and refracting angle wedges, 12 sets of TOFD calipers to include transducers and wedges,12 String encoders
2. Props to include a minimum of 20 butt welds in plate props (300mm long with thicknesses varying from 12mm to 20mm
3. All diagnostic hardware needed for training.
4. Any additional materials, supplies, equipment deemed necessary by the Contractor.
5. Effective training instruction, to include: Full Comprehensive training manuals for both
PAUT and TOFD
6. PAUT and TOFD training material
7. Contractor to provide delivery of all training materials to training site.
DRAFT
3.3 The Contractor shall use Olympus/Evident branded Phased Array Flaw Detectors and Software.
3.4 Upon satisfactory completion of the PAUT and TOFD training course The Contractor shall provide certificates of completion for “Training” and certificates for “Assessment”(test scores) for the students.
3.5 SAFETY: The Contractor shall comply with all Safety Requirements as prescribed in APPENDIX I in paragraph 7.1
3.6 ENVIRONMENTAL: The Contractor shall comply with all Environmental Requirements as prescribed in APPENDIX II in paragraph 7.2
3.7 TRAVEL: Travel shall be in accordance with the Federal Acquisition Regulation (FAR) 31.205- 46 and current DOD Joint Travel Regulations (JTR).
3.8 SERVICE DELIVERY SUMMARY
Description Reference Performance
1. PAUT Training Paragraph 2.2 100% delivery and compliance.
2. TOFD Training Paragraph 2.3 100% delivery and compliance.
3. Certificate of Completion for Training and Certificate for Assessment
Paragraph 3.4 100% delivery and compliance.
4.0 GOVERNMENT FURNISHED UTILITIES AND SERVICE:
4.1 The Government will provide a training room, stand-alone projectors and electrical power for 12 students. The contractor may connect his laptop computer to the stand-alone projector/monitor.
The contractor is prohibited from connecting to any shipyard computer or network computer.
4.2 The Government will ensure access to the training room is provided before the start of the training and after it concludes to facilitate preparatory activities and removal of training equipment. The contractor shall coordinate the access arrangements with the Government TPOC.
5.0 CONTRACTOR QUALIFICATIONS:
5.1 The contractor/instructor shall have thorough knowledge and understanding and a subject matter expert of the PAUT/TOFD training and the use of Evident/Olympus Phased Array Flaw Detector and Software. The contractor/instructor shall be certified to BINDT/PCN standards.
5.1.1 Contractor/instructor to provide certifications upon request.
5.2 The contractor/instructor shall pass a background check to gain access onto the base. The contractor will coordinate with PHNSY & IMF to obtain a gate pass at building 3455 Pass Office.
It is not unusual for the pass process to take an hour or more. Contractor/instructor must pass a security background check. Only those individuals with favorable investigations shall be utilized on this contract. Prior to the start of work, the Contractor shall provide the COR (on company letterhead) a request for access and include the following information – full name of all personnel working on this contract; Social Security number; date of birth, place of birth, and citizenship.
The contractor shall state that information has been verified and shall have supporting records on file, if required for examination.
5.3 Contractor personnel must meet the requirements for a white badge (escort required), to PHNSY&IMF areas. Escorted access to CNIAs and NWAs must be coordinated with the cognizant Department Security Coordinator to ensure that the area is sanitized and the escort is properly briefed/knowledgeable of the area. The Contractor must follow the applicable requirements listed below in APPENDIX III paragraph 7.3 and brief their personnel to ensure compliance. Non-compliance with applicable items in Attachments is a material violation of the contract. Should Contractor personnel receive or suspect they have learned unauthorized sensitive information, they must identify and immediately report suspicions to the COR.
5.4 The Contractor shall conduct background investigations on personnel that are used in connection with this contract.
5.5 This contract does not require a security clearance level and clearance granted by the Defense Security Service (DSS). However Contractor personnel shall recognize that PHNSY & IMF deals with sensitive information and other proprietary information, which are valuable, special, and unique assets. Contractor personnel shall not divulge, disclose, or communicate in any manner, any information to any third party without prior written consent. Contractor personnel shall protect information and treat it as strictly confidential and will abide by the security requirements of SECNAVINST 5510.36. A violation of this paragraph shall be a material violation of this agreement. Should Contractor personnel receive or suspect they have learned of classified information beyond their level of clearance, the Contractor shall identify and report suspicions to the COR.
5.6 When performing work associated with this PWS, the Contractor shall make clear to all individuals they deal with that they are contract employees and not DOD employees.
5.7 Contractor employees shall clearly identify themselves as a Contractor (i.e. company shirt, pin, visible company identification) in a visible location on the front of exterior clothing and above the waist, (except when safety or health reasons prevent such placement) as to who their employer is.
5.8 The Contractor performing services shall be required to comply with all Pearl Harbor Naval Shipyard & IMF rules, regulations, and training that is applicable to conduct, safety, security, and procedures governing site entry and exit.
5.9 Contractor shall comply with PHNSY & IMF Operations Security (OPSEC) Contract Requirements, Appendix IV.
6.0 HOURS OF OPERATION:
6.1 TRAINING HOURS: PAUT training to be held Monday thru Friday and Saturday if necessary, from the hours of 0630 to 1700. TOFD training to be held Monday thru Friday and Saturday if necessary, from the hours of 0630 to 1500. The Technical Point of Contact (TPOC) shall be notified 1 week in advance to any changes in the training schedule.
7.0 APPENDICES
7.1 APPENDIX I – SAFETY AND HEALTH WORK PRACTICES FOR CONTRACTORS
WORKING WITH PEARL HARBOR NAVAL SHIPYARD AND INTERMEDIATE
MAINTENANCE FACILITY (PHNSY & IMF) REVISED JULY 2024
7.2 APPENDIX II – Environmental Protection Guidelines for Contractors on Facilities Projects at Pearl Harbor Naval Shipyard & Intermediate Maintenance Facility Revised October 16, 2019
7.3 APPENDIX III – CONTRACTOR SECURITY REQUIREMENTS FOR PHNSY&IMF’S
CONTROLLED INDUSTRIAL AREA, SECURITY ISLANDS, CONTROLLED NUCLEAR
INFORMATION AREAS, NUCLEAR WORK AREAS AND/OR OTHER SENSTIVE AREAS.
(Revised May 2024)
7.4 APPENDIX IV - Pearl Harbor Naval Shipyard and Intermediate Maintenance Facility Operations Security (OPSEC) Contract Requirements (02-25)
| PERFORMANCE WORK STATEMENT (PWS) |
| PAUT and TOFD Training for PEARL HARBOR NAVAL SHIPYARD (PHNSY & IMF) |
File details come from the government source that posted it. Updated .