This performance work statement outlines preventative maintenance and repair services required for a Kuraki CNC horizontal boring mill located at Pearl Harbor Naval Shipyard and Intermediate Maintenance Facility. The contractor shall supply a manufacturer-trained technician to perform annual preventative maintenance, including inspection, calibration, and remedial repairs if needed. Preventative maintenance is required within the one-year period of performance, with additional technical support available by phone. The contractor must submit inspection reports within five business days and repair reports for any remedial work. The services are to be performed at Pearl Harbor Naval Shipyard during normal business hours excluding federal holidays. The contractor shall comply with all safety, security, and environmental regulations at the facility.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 4. KURAKI PWS - 1 (1).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS) Pearl Harbor Naval Shipyard and Intermediate Maintenance Facility
Kuraki CNC Horizontal Boring Mill Preventive Maintenance Inspection and Remedial Services
1. Background:
1.1. Pearl Harbor Naval Shipyard & Intermediate Maintenance Facility (PHNSY & IMF) is a
US Navy regional industrial center that maintains, overhauls, and repairs various vessels of the US Navy. Its industrial operations provide the US naval forces with a wide range of services and resources located on the island of Oahu, Hawaii, with direct and indirect support to SSN 688 and 774 class submarines, surface vessels and shore based activities in the Pacific
2. Objective and Scope:
2.1. The Contractor shall supply a Manufacturer Trained Certified Technician to perform annual preventive maintenance services on 1EA. Kuraki KBT-11ZP CNC Horizontal Boring Mill (HBM). The Contractor shall perform on-site, preventive maintenance, repair, calibration, re-leveling, and remedial services (repairs required outside scope of annual preventive maintenance), to include an inspection report on 1EA. Kuraki CNC
HBM.
Manufacturer Model Serial no Location
KURAKI KBT-11ZP C2296 Bldg. 67
3. Performance Requirements:
3.1. Preventive Maintenance. The contractor shall provide all management, parts, labor, materials, supplies, transportation and tools required for preventive maintenance of all equipment in paragraph 2.1 in accordance with the applicable manufacturer’s manual to ensure proper operation of equipment. Contractor shall provide a contact phone number and alternate phone number for use during the contract duration. The contractor shall notify the Technical Point of Contact (TPOC) if any machine covered under this contract cannot be restored to operational status within the contract period. The Contractor shall create complete system backups, prior to and after any configuration changes to hardware or software to ensure no loss of data. All software upgrades, if required, shall be provided. The Contractor shall ensure that upgrades include all applicable software licensing agreements.
3.1.1. Preventive Maintenance Service. The Contractor shall provide one, (1) on-site preventive maintenance service within the period of performance. The PM visit shall be scheduled with Shop 31 Supervisor to avoid disruption to shop operations kylie.keller Draft schedule. Preventive Maintenance Service shall be in accordance with applicable Manufacturer’s Requirements.
3.1.2. Technical Support: The Contractor shall provide technical support via telephone for any authorized adjustments, modifications, maintenance, repair, and application development of equipment operating software (listed in section 2.1). Contractor shall respond to technical support requests within 24 business hours.
3.1.3. Preventive Maintenance Parts. Parts that are replaced as part of the preventive maintenance service are included at no additional cost to the Government. Materials supplied shall be new and not refurbished or reconditioned materials.
3.2. Software Upgrades. All software upgrades, if required, shall be provided. The
Contractor shall ensure that upgrades include all applicable software licensing agreements. The Contractor shall create complete system backups, prior to and after any configuration changes to hardware or software to ensure no loss of data.
3.3. Preventive Maintenance Reports. The contractor shall submit a preventive maintenance inspection report within five (5) business days after the completion of each Preventive Maintenance and Inspection. The report shall contain at a minimum, the identification and location of equipment, the type of maintenance performed, materials or parts replaced, date of preventive maintenance, service technicians name and an assessment of the overall condition of the equipment serviced. The report shall be delivered to the Contracting Officer or designated representative.
3.4. Remedial Repairs. Remedial service repair identified during preventive maintenance shall be accomplished if completion of the repair is possible during the on-site PM visit or within the period of performance.
3.4.1 Remedial Repair Parts. Parts that are replaced as part of remedial repair is to be issued on a separate purchase order to be approved by the TPOC. Materials supplied shall be new and not refurbished or reconditioned materials. If parts are needed, it shall be installed during next on-site preventive maintenance visit.
3.4.2 Remedial Repair Reports. The Contractor shall provide a repair report to the TPOC within five (5) business days after completion of the repair. The report shall include the date and time of the remedial repairs, the identification and location of the equipment, the repairs performed, material or parts replaced, and the name of the technician performing the repairs. If a repair cannot be completed during the on-site visit, the Contractor shall provide a report which includes equipment identification, description of the needed repair, estimated time and cost to accomplish the work.
3.5. Contractor must comply with environmental guidelines specified in Appendix II of paragraph 8.0
3.6. Removal and disposal of replacement parts and materials. Contractor shall transfer replacement parts and materials, to PHNSY & IMF for proper disposal.
3.7. Hazardous Waste and Scrap Metal shall be turned over to PHNSY & IMF. For specific guidance, guidelines, and procedures governing the use and disposal of hazardous material or hazardous waste at PHNSY & IMF, direct all questions to the
TPOC.
3.8. Place of Performance. Pearl Harbor Naval Shipyard, Controlled Industrial Area (CIA), Shop 31 Bldg.67, Pearl Harbor, Hawaii.
3.9. Period of Performance. All work to be completed within twelve months after award of contract on an annual basis, for the base and four option years.
3.10 Hours of Performance. Normal Hours. All work shall be performed during normal business working hours of 0630 to 1500 hours, daily, Monday through Friday, excluding Federal Holidays.
3.11 Federal Holidays. If the Federal Holiday falls on a Saturday, the holiday is observed on the following Monday. Facilities may close due to local or national emergencies, administrative closings, or other Government directed facility closings. PHNSY & IMF typically observes an annual curtailment closure between Christmas and New Year’s, consult with TPOC for details. Contractor access to Government facilities during closures is not permitted.
3.12 Workmanship. The Contractor shall ensure that all work performed is done by a factory trained and authorized service technician and shall provide a 1-year warranty on the work performed. The warranty shall begin when all work is completed and accepted by the Government.
3.13 Service Delivery Summary Table A:
Performance Requirement
PWS
Paragraph
Notes Performance Threshold
1. Perform Preventive Maintenance Paragraphs 3.1
3.1.1 and 3.1.2, 3.1.3.
100% delivery and compliance.
2. Provide software upgrades if required.
Paragraph 3.2 100% delivery and compliance.
3. Provide a PM Inspection Report within five (5) business days after completion of PM service.
Paragraphs 3.3 100% delivery and compliance.
4. Perform Remedial Service and Repair
Paragraphs 3.4 100% delivery and compliance.
5. Remedial Repairs Parts Paragraphs 3.4.1
100% delivery and compliance.
6. Provide written Remedial Repair Report within five (5) business days after completion of PM service.
Paragraph 3.4.2 100% delivery and compliance.
8. Removal and disposal of replacement parts and materials.
Paragraph 3.5 100% delivery and compliance.
9. Hazardous waste and scrap metal to be turned in to PHNSY & IMF.
Paragraph 3.6 100% delivery and compliance.
4. Quality Assurance.
4.1. The Contractor is responsible for implementing and maintaining a Quality Control Plan
(QCP) that identifies and results in the correction of potential and actual problems. The QCP shall be implemented on the first day of contract performance and a copy of QCP shall be provided to the Contracting Officer’s Representative (COR) prior to contract performance.
4.2. The QCP shall outline the Contractor’s plan to ensure the quality of deliverables as outlined in this PWS. The QCP shall address what will be reviewed and shall outline actions to be taken by the Contractor, should the review(s) identify areas requiring remedial action.
4.3. The Contractor shall keep records of any inspections and corrective actions taken, as outlined in the QCP and shall make such records available to the COR upon request within five (5) business days.
5. Government Furnished Property and Services.
5.1. GENERAL: The Government will provide the following:
5.1.1. All reasonably required amounts of electricity for Contractor supplied tooling or test equipment.
5.1.2. Removal and disposal of Hazardous Waste, used lubricants, coolants, and cleaning solutions generated from servicing
5.1.3. No other property, utilities or services will be provided by the Government.
6. Contractor Qualifications:
6.1. The Contractor shall provide a manufacturer trained and authorized certified technician and the necessary management and administrative support associated with personnel, to perform annual preventive maintenance services.
6.2. Contractor personnel shall have a valid driver's license and a vehicle pass for base access. The Government will submit the base access request to JBPHH Security. In accordance with the Security Requirement - Appendix III (paragraph 8.0), the Government will provide escorts as required while in the CIA.
6.3. The Contractor must be able to attain and maintain a CIA badge.
6.4. Contractor employees shall clearly identify themselves as a Contractor (i.e. company shirt, badge, company identification) in a visible location on the front of exterior clothing, above the waist, (except when safety or health reasons prevent such placement). Identification badges shall be worn at all times when performing work.
6.5. The Contractor performing services shall be required to comply with all PHNSY&IMF rules, regulations and training that are applicable to conduct, safety, security, and procedures governing site entry and exit. Contractor personnel will be escorted when working in sensitive areas, as required. The TPOC will make arrangements to provide escort service if required.
7. Security Requirements:
The contractor shall pass a background check to gain access PHNSY & IMF. The contractor’s employees must be a U.S. Citizen and registered with the Defense Biometric Identification System (DBIDS). The contractor shall coordinate with the COR to obtain a gate pass at Building 3455 Pass Office. Only those individuals with favorable investigations shall be utilized on this contract. Contractor will coordinate with building 3455 Pass Office in the completion of current form SECNAV 5512/1.
Contractor personnel must meet the requirements for a “green” unescorted badge for access to areas requiring services related to this contract. Contractor will coordinate with PHNSY Security Office at building 207 in the completion of Visit Request for Pearl Harbor Naval Shipyard current form PH-SYD 5512/28.
Security Requirements: This contract does not require a security clearance level and clearance granted by the Defense Security Service (DSS). Contractor shall comply with Security requirements specified in Appendix III (paragraph 8.0).
8. Attachments:
APPENDIX I – SAFETY AND HEALTH WORK PRACTICES FOR CONTRACTORS
WORKING WITH PEARL HARBOR NAVAL SHIPYARD AND INTERMEDIATE
MAINTENANCE FACILITY (PHNSY & IMF) (AUG 2022)
APPENDIX II –ENVIRONMENTAL PROTECTION GUIDELINES for CONTRACTORS on FACILITES PROJECTS (REV 16 Oct 2019)
APPENDIX III – CONTRACTOR SECURITY REQUIREMENTS FOR PHNSY & IMF’S
CONTROLLED INDUSTRIAL AREA, CONTROLLED NUCLEAR INFORMATION
AREAS, AND/OR OTHER SENSITIVE AREAS (REV JUN 2021)
File details come from the government source that posted it. Updated .