41. QUESTIONS AND ANSWERS 10.06.2022.pdf
PDF 232 KB Posted
- Attached to
- Air Conditioning / Dehumidifier Rentals Federal contract opportunity
- Solicitation number
- N3225322Q0091
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 41. N3225322Q0091.2 RFQ.pdf | ||
| 41. QUESTIONS AND ANSWERS 10.03.2022.pdf | ||
| 41. QUESTIONS AND ANSWERS 09.23.2022.pdf | ||
| 41. N3225322Q0091.1 RFQ.pdf | ||
| 41.A4. OPSEC Contract Requirements 03.21.2022.pdf | ||
| 41.A2. ENV FOR KTRS - FACILITY PROJECTS 10.16.2019.pdf | ||
| 41.A3. KTR CIA, CNIA & NWA SECREQS 06.2021.pdf | ||
| 41.A1. SAFETY & HEALTH 07.08.2021.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Air Conditioning / Dehumidifier Rentals N32253-22-Q-0091 Questions and Answers as of 10/06/2022
Question Answer
1. Please advise as to how we are to achieve the requirement to provide 100 tons of cooling capacity. There are numerous ways we can achieve this requirement. (1 QTY – 100 Ton Temp Chiller, 100 QTY – 1-Ton spot coolers, etc.)
Multiple units stationed around the project, only to be moved for maintenance and when job is complete.
2. What is the quantities and cooling capacity of each unit being required. If a specific response cannot be provided, if you could let us know your intentions for this 100-tons of temporary cooling. This will help us in quoting and providing the proper units needed.
(8) DH/AC 5000HP, 5,000 CFM Cooling and Dehumidifier
3. “8 month rental period” but period of performance is from 10/31/2022 to 10/30/2023. Please clarify if an 8 month period is suffice or if it should be for one year.
8 months is sufficient
4. Will the units be turned over to PHNSY once the 8 month rental period has expired?
No
5. Will the units be set up at one location and left there or will it move from one building to another during the period of performance 10/31/2022 to 10/30/2023?
One location
6. How many BTUs do you need? Included in the PWS
7. What the size of the unit Generally several 10 Ton to 20 Ton Cooling units are adequate (vice 1ea 100Ton Unit)
8. What voltage should the unit be? 440 Volt 3-phase AC Power
9. Are there any specific temperatures No, just cooling capacity requirements to support comfort cooling shipboard
10. Any additional specs on the unit? Should be transportable by crane and forklift
11. Where are the rentals installed? It’s outdoors, alongside the Dry Dock pier or on platforms in the Dry Docks