SOR 27_004_BALLAST WATER MANAGEMENT ABS SUPPORT_PWS.docx
DOCX document 37 KB Posted
- Attached to
- USNS RF KENNEDY - BWTS ABS Support
- Solicitation number
- N3220527Q7042
About this file
This is a Performance Work Statement (PWS) for OEM support of a ballast water treatment system aboard the USNS Robert F. Kennedy (TAO 208). The work is to be performed at NAVSTA Norfolk, Pier 8, Virginia, from December 14-18, 2026. The contractor must provide manufacturer's representative services to clear an American Bureau of Shipping (ABS) Condition of Class and conduct crew familiarization and training on the GLOEN-P3000 Ballast Water Treatment System located in the Cargo Pump Motor Controller Room. The specific scope includes demonstrating operation in four modes (ballast, de-ballast, bypass, and eductor/stripping modes), submitting a Coordinated Fleet Response (CFR) of recommended spare parts, and conducting an operational test of the system to the satisfaction of ABS and the Chief Engineer.
The PWS requires that all contractor and subcontractor personnel comply with General Technical Requirements (GTRs 1-7, 22-24, 28-29) and applicable OEM procedures. U.S. citizen technical representatives must submit the latest SECNAV FORM 5512 and possess a REAL ID for base access sponsorship, while foreign nationals must provide the same form plus U.S. Customs & Immigration work authorization visa documentation. Any costs associated with denied base access are the contractor's responsibility. The solicitation is managed by the Department of the Navy Military Sealift Command under solicitation number N3220527Q7042.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Use of Other than Full and Open WTS ABS Support_Redacted.pdf | ||
| Solicitation - N3220527Q7042.pdf | ||
| 15-4341.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT
The purpose of this work item is to provide OEM support of the vessel’s ballast water treatment system and demonstrate to ABS.
Place of Performance: NAVSTA NORFOLK, Pier 8, VA Period of Performance: 14 DEC – 18 DEC 2026
REFERENCES/ENCLOSURES
References
T9529-AK-MMC-010 BALLAST WATER TREATMENT SYSTEM; VOLUME 1 INSTRUCTION MANUAL
T9529-AK-MMC-020 BALLAST WATER TREATMENT SYSTEM; VOLUME 2 INSTRUCTION MANUAL
Enclosure: NONE
ITEM LOCATION/DESCRIPTION/QUANTITY
Location
CARGO PUMP MOTOR CONTROLLER RM, (3-99-0)
Description/Quantity Ballast Water Treatment System Model: GLOEN-P3000 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICE: None
NOTES
The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor, and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs including but not limited to GTRs 1 through 7, 22, 23, 24, 28, and 29.
QUALITY ASSURANCE REQUIREMENTS: None additional
STATEMENT OF WORK REQUIRED
Provide and operate equipment and supply all services and assistance to clear ABS Condition of Class and provide crew familiarization/training for the ballast water treatment system identified in section 3.0 using References 2.1.1 through 2.1.2 as guidance.
Provide support to execute ABS requirements and conduct crew familiarization and training. Training is to be accomplished in accordance with all OEM procedures.
Demonstrate to ship’s force how to operate ballast water treatment plant in all four modes (ballast mode, de-ballast mode, bypass mode, & eductor {stripping} mode).
Submit a CFR of recommended spare parts.
Upon completion of all work, conduct an operational test of the ballast water treatment system to the satisfaction of ABS and Chief Engineer.
Manufacturer’s Representative provide the services of the OEM or an OEM authorized representative to execute the work.
GENERAL REQUIREMENTS:
8.1 Base Access Requirements
8.1.1 Tech reps that are US citizens must fill out and submit to PPE latest revision of SECNAV FORM 5512 for sponsorship on base. Reps must meet MSCrep at base pass office for sponsorship on base. A REAL ID is required otherwise they will not be granted access to NAVSTA Norfolk.
0. Any tech reps that are foreign nationals must fill out and submit to PPE latest revision of SECNAV FORM 5512 AND provide their U.S. Customs & Immigration Work Authorization VISA at the NAVSTA Norfolk Pass & ID Office otherwise they will not be granted access to NAVSTA Norfolk.
0. Any costs incurred for a tech rep that is denied access to the base will be borne by the contractor.
USNS Robert F. Kennedy
( TAO 208 )
| AUXILIARY MACHINERY |
| Performance Work Statement |
| SOR 27-004 |
| CATEGORY "A" |
| 2026-10-05 |
| BALLAST WATER MANAGENMENT ABS SUPPORT |
| Cipolla, Michael, P |
0599 - 3
File details come from the government source that posted it. Updated .