This is a Class Justification and Approval (J&A) document for a non-competitive contract action with the Department of the Navy, Military Sealift Command (MSC) Norfolk.
The document authorizes award modifications under contract N3220526C1230 to Vigor Marine, LLC for the Mid-Term Availability of the USNS GUADALUPE (T-AO 200). The original contract, competitively awarded on March 3, 2026, consisted of 111 work items with a performance period of October 7, 2026 through December 20, 2026, and was valued at $17,967,446.72. The modifications incorporate work items needed to comply with regulatory requirements of the U.S. Navy, U.S. Coast Guard, and American Bureau of Shipping, to be funded with fiscal year 2027 Operations and Maintenance, Navy (O&M,N) funds. The authority to act under this Class J&A expires one year from approval by the Competition Advocate.
The justification for using other than full and open competition is based on unusual and compelling urgency under 10 U.S.C. 3204(a)(2). Following inspections conducted September 1-15, 2026, multiple critical deficiencies were identified in SSDG number 3, including persistent engine balance problems with poor combustion in cylinders B2 and B7, documented through fuel analysis samples from March 2026 through September 2026. The vessel is also approaching the 80,000-hour engine overhaul window and faces risk of catastrophic engine failure if maintenance is not completed before deployment to the 5th Fleet. The Contracting Officer determined competitive solicitation is not feasible, as the procurement action lead time of 381 days plus repair time would delay mission readiness, with daily losses to the Government estimated at $210,167.00 per day. The presolicitation notice was posted on sam.gov on October 27, 2025, and the award notice on March 4, 2026. The Contracting Officer has determined the anticipated cost will be fair and reasonable in accordance with FAR 15.404-1(b). The Government intends to develop a technical data package or performance specification to support competition for future similar acquisitions.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
J&A No. N10426C1230P00005
CLASS JUSTIFICATION AND APPROVAL (J&A)
FOR USE OF OTHER THAN FULL AND OPEN COMPETITION
1. Contracting Activity: Department of the Navy, Military Sealift Command (MSC) Norfolk
2. Description of the Action Being Approved: Award modifications under contract N3220526C1230, for the
Mid-Term Availability of the USNS GUADALUPE (T-AO 200), to Vigor Marine, LLC., incorporating work items needed to comply with regulatory requirements. The contract was awarded for $17,967,446.72 on the basis of one offer/sole source offeror.
3. Description of Supply Services: To accomplish the work items detailed in the enclosure, which are needed to comply with regulatory requirements of the U.S. Navy, U.S. Coast Guard, and American Bureau of
Shipping. The total estimated dollar value for all such work items is which will be funded utilizing fiscal year 2027 Operations and Maintenance, Navy (O&M,N) funds. The authority to act under this Class J&A expires one year after the date on which it is approved by the Competition Advocate.
4. Statutory Authority Permitting Other Than Full and Open Competition: 10 U.S.C 3204(a)(2) Unusual and compelling urgency.
5. Rationale Justifying Use of Cited Authority
a. The contracting activity competitively awarded the contract consisting of 111 work items on March 03, 2026 with a period of performance of October 07, 2026 through December 20, 2026.
b. Inspectors from the U.S. Coast Guard and/or American Bureau of Shipping along with the vessel’s crew and ashore personnel conducted inspections from Sunday September 1, 2026 through Tuesday September
15, 2026 and identified deficiencies requiring repair prior to the vessel’s departure from the shipyard to comply with Safety Management System objectives, attain Operational Availability, and maintain vessel configuration.
c. Vessel is currently experiencing multiple discrepancies with SSDG number 3 and is approaching violation of MSC N0700-106.00-T-AO187 Revision 5.0 Redlines, SOLAS Chapter II-1 Part D Regulation 43 and
ABS Marine Vessel Rules (MVR) Part 4 Chapter 8 if maintenance is not completed. MSC N0700-106.00-T-
AO187 Revision 5.0 Redlines states minimum requirements for Generators are 2 of 2 SSDG’s Operational.
Also, due to increased mission requirements in 3rd and 5th Fleet in FY25 and FY26 vessel has approached the 80,000-hour engine overhaul faster than anticipated and engines if not overhaul now will have a severe risk of catastrophic failure based on prior history and risk analysis. With vessel currently in the 80,000-hour engine overhaul window and expected deployment to 5th fleet upon departure the engine will exceed to required life cycle maintenance and will be at extreme risk of catastrophic failure while conducting mission in 5th fleet. The crew has acted on these items as we take data, but it still hasn't improved above poor balance after each attempt. Remote support to correct discrepancies has been exhausted and at this point the crew is not capable to correct the issue without OEM Bergen industrial involvement.
SSDG number 3 engine hours currently are 75577 hours and are experiencing the follow issues:
• Sample Date: 24 Mar 2026 o Analysis: CBI = 0.080 Poor Balance. Engine is in poor balance due to Cylinders B2 and B7 are notable low PFP outliers from the engine average. Data indicates late injection and poor combustion.
• Sample Date: 12 May 2025 o Analysis: CBI= 0.080 Poor Balance. Engine is in poor balance due to Cylinders B2 and B7 are notable low PFP outliers from the engine average. Data indicates late injection and poor combustion. || Priority:
#IMPORTANT || Recommendation: Investigate the cause of late ignition issues and poor combustion for
Cylinders B2 and B7 starting with the fuel injection system.
• Sample Date: 6 July 2026 o Analysis: CBI = 0.074 Poor Balance. Engine is in poor balance due to Cylinders B1, B2 and B7 are notable low PFP outliers from the engine average. Data indicates late injection and poor combustion.
• Sample Date: 18 July 2026 o Analysis: CBI = 0.074 Poor Balance. Compared to last shot taken on 6 July 2026 and with further
J&A No. N10426C1230P00005 analysis, engine is poor balance due to a bank balance. A-Bank cylinders are firing approximately 80 PSI higher than B-Bank cylinders. Also, looking at the banks independently the A-Bank side of the engine is in a
Fair Balance whereas the B-Bank side is in Poor Balance. Cylinder B7 being a notable low PFP outlier (180
PSI lower than the engine average) with data indicating poor combustion after ignition as well.
• Sample Date: 10 Sep 2026 o Analysis: CBI = 0.072 Poor Balance. Compared to last shot taken on 18JUL2026 engine remains in poor balance due to Cylinder B7 still being a notable low PFP outlier (140 PSI lower than the engine average) with data indicating poor combustion after ignition as well. Also, Cylinder A2 shows late ignition
(approximately 4 degrees later than engine average).
d. Competitively soliciting for these work items is not feasible as it would delay returning to a mission-ready posture since award of a procurement package of this magnitude will require a procurement action lead time of 381 days plus the time to accomplish repairs. The vessel’s per diem rate is $210,167.00 per day, which is the estimated losses to the Government for each day of delay.
6. Description of Efforts Made to Solicit Offers from as Many Offerors as Practicable: The presolicitation notice was posted on the Government Point of Entry website (sam.gov) on October 27, 2025.
and the award notice was posted on March 4, 2026. For reasons set forth in Paragraph 5, this particular requirement is not presently a candidate for full and open competition.
7. Determination of Fair and Reasonable Cost: The Contracting Officer has determined the anticipated cost to the Government of the supplies/services covered by this J&A will be fair and reasonable IAW FAR
15.404-1(b).
8. Actions to Removed Barriers to Future Competition: The Government expects to obtain a technical data package or develop a performance specification that will support competition for future acquisitions of the same or similar items.
CERTIFICATION AND APPROVALS
Technical/Requirements Cognizance:
I certify that the facts and representations under my cognizance, which are included in this Justification and its supporting acquisition planning documents, except as noted herein, are complete and accurate to the best of my knowledge and belief.
Contracting Officer Certification:
I certify that this justification is accurate and complete to the best of my knowledge and belief.
WHITE.THOMAS.
Digitally signed by
WHITE.THOMAS.L.III.1595615352
L.III.1595615352 Date: 2026.11.05 10:27:13 -08
'00'
Signature/Date Name (Printed) Phone No.
| CLASS JUSTIFICATION AND APPROVAL (J&A) |
| 5. Rationale Justifying Use of Cited Authority |