This document is a Request for Clarification (RFC 046) related to the USNS MERCY FY25 Mid-Term Availability federal contract opportunity, solicitation number N3220524R4026. The RFC seeks clarification on the intended start and duration of the Dock Trials for the USNS MERCY, as described across multiple work items. The key details are:
The RFC references Work Items 013, 022, and 287, which provide different information on the timing and duration of the Dock Trials. Work Item 013 states the Dock Trials shall be scheduled at least two days prior to the Sea Trials. Work Item 022 states the Dock Trials shall be conducted as scheduled per Work Item 013. Work Item 287 states the Technical Representative will attend the vessel for a total of nine days, commencing two days prior to the six-day Dock Trials and one day of Sea Trials.
The Navy's answer clarifies that the Dock Trials are intended to be a one-day event, as scheduled in Work Item 013. The contractor will be on site for a total of nine days through the Sea Trials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| USNS MERCY Amendment 0007.pdf | ||
| RFC 047 - Answered.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N3220524R4026 USNS MERCY (T-AH 19)
REQUEST FOR SPECIFICATION CLARIFICATION - 046
Work Item: 013, 022, & 287
Paragraph/Section: Various
Title: Schedule Dock Trials
Question:
0013_A_TAH-SWI-INTEGRATED PROJECT PLANNING AND PRODUCTION STATUS MONITORING REPORTS WI 0013, paragraph 7.2.9.i states Dock trial: Shall be scheduled to occur at least two (2) days prior to the sea trial milestone.
0022_A_TAH-SWI-MACHINERY SPACE TURN-OVER DOCK TRIALS AND SEA TRIALS
WI 0022, Conduct dock trials as scheduled per work item 013.
0287_A_TAH CSI AUTOMATION AND PROPULSION CONTROLS - INSPECTION & TEST (1 YR) (SCSI) WI 0287, paragraph 7.10.2 states Technical Representative will attend the vessel a total of nine days commencing two days prior to six day dock trials and one day sea trials, contract will end one day after sea trial as per WI 0013.
Please clarify the intended start and duration of Dock Trials.
Answer:
Dock Trial is a one day event as scheduled in WI 0013. The intent is to have the contractor on sight for a total of nine days through the Sea Trial
ATTACHMENT J-8