This document provides answers to questions from potential offerors regarding solicitation N3220521R4190 for weld metal crack repair on USNS BURLINGTON ROH / DD. Question 34 asks for the approximate length and depth that should be allowed for when estimating repair requirements. The answer states that repairs should assume a maximum length of one inch and a maximum depth of half an inch.

View the file

Other files

File Type Posted
USNS BURLINGTON ROH DD N3220521R4190 AMENDMENT 0004.pdf PDF
Q AND A Responses 37.pdf PDF
J - 2 Category A Items BURLINGTON 21R4190 REV 2.xlsx XLSX spreadsheet
Q AND A Responses 35.pdf PDF
Q AND A Responses 36.pdf PDF
USNS BURLINGTON ROH DD N3220521R4190 AMENDMENT 0003.pdf PDF
Q AND A Responses 33.pdf PDF
Q AND A Responses 8.pdf PDF
Q AND A Responses 1 REV (10 JUNE 2021).pdf PDF
Q AND A Responses 22.pdf PDF
Q AND A Responses 10.pdf PDF
Q AND A Responses 19.pdf PDF
Q AND A Responses 27.pdf PDF
Q AND A Responses 16.pdf PDF
Q AND A Responses 28.pdf PDF
Q AND A Responses 2 REV (10 JUNE 2021).pdf PDF
Q AND A Responses 9.pdf PDF
Q AND A Responses 14.pdf PDF
Q AND A Responses 25.pdf PDF
Q AND A Responses 20.pdf PDF
Q AND A Responses 24.pdf PDF
Q AND A Responses 21.pdf PDF
Q AND A Responses 12.pdf PDF
Q AND A Responses 15.pdf PDF
Q AND A Responses 32.pdf PDF
Q AND A Responses 3 REV ( 10 JUNE 2021).pdf PDF
Q AND A Responses 13.pdf PDF
Q AND A Responses 29.pdf PDF
Q AND A Responses 18.pdf PDF
Q AND A Responses 17.pdf PDF
Q AND A Responses 11.pdf PDF
Q AND A Responses 30.pdf PDF
Q AND A Responses 26.pdf PDF
Q AND A Responses 23.pdf PDF
Q AND A Responses 31.pdf PDF
Q AND A Responses 6.pdf PDF
Q AND A Responses 3.pdf PDF
Q AND A Responses 5.pdf PDF
Q AND A Responses 7.pdf PDF
Q AND A Responses 4.pdf PDF
J - 2 Category A Items BURLINGTON 21R4190 REV 1.xlsx XLSX spreadsheet
Q AND A Responses 1.pdf PDF
Q AND A Responses RFE.pdf PDF
Q AND A Responses 2.pdf PDF
USNS BURLINGTON ROH DD N3220521R4190 AMENDEMENT 0001.pdf PDF
USNS BURLINGTON ROH DD N3220521R4190.pdf PDF
J - 13 Past Performance Questionnaire - BURLINGTON 21R4190.docx DOCX document
J-6.zip ZIP file
J - 10 Interport Differential - BURLINGTON 21R4190.doc DOC document
J - 2 Category A Items BURLINGTON 21R4190.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 61 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N3220521R4190

QUESTIONS AND ANSWERS #34

The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

SPECIFICATION ITEM NO.: 104

PARAGRAPH / SECTION NO: 7.1

TITLE: Weld Metal Crack Repair

QUESTION 34:

Is approximate length, depth, etc. that should be allowed for when estimating the requirements of the repairs?

ANSWER:

Assume length is not to exceed one (1) inch and depth is not to exceed one half (1/2) inch.