Amendment 0002 USNS MCLEAN MTA N3220520R4077.docx
DOCX document 33 KB Posted
- Attached to
- USNS WILLIAM MCLEAN FY20 MID-TERM AVAILABILITY Federal contract opportunity
- Solicitation number
- N3220520R4077
About this file
This document contains an amendment and request for specification clarification for a sources sought notice regarding non-skid deck coating renewal and hazardous material container replacement work items for the USNS William Mclean mid-term availability. The amendment increases the square footage estimates for work items 102 through 105, which involve renewal of various levels of non-skid coating on decks and clarifies the approved application of Amercoat 385 non-slip coating. It also provides ship interference and deck marking details for work items 102 through 105. For work item 101 involving hazardous material container replacements, it specifies that ramps will need to be raised 3 inches and that empty containers will be removed by ship's force.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0012 USNS MCLEAN MTA N3220520R4077.docx | DOCX document | |
| Amendment 0011 USNS MCLEAN MTA N3220520R4077.docx | DOCX document | |
| Amendment 0010 USNS MCLEAN MTA N3220520R4077.docx | DOCX document | |
| Amendment 0009 USNS MCLEAN MTA N3220520R4077.docx | DOCX document | |
| Amendment 0008 MCLEAN MTA N3220520R4077.docx | DOCX document | |
| Amendment 0007 MCLEAN N3220520R4077.docx | DOCX document | |
| Amendment 0006 USNS MCLEAN N3220520R4077.docx | DOCX document | |
| Amendment 0005 MCLEAN MTA N3220520R4077.docx | DOCX document | |
| Amendment 0004 MCLEAN MTA N3220520R4077.docx | DOCX document | |
| Amendment 0003 MCLEAN MTA N3220520R4077.docx | DOCX document | |
| Amendment 0001 MCLEAN MTA N3220520R4077.docx | DOCX document | |
| Solicitation N3220520R4077 USNS MCLEAN MTA14 Apr 20.docx | DOCX document | |
| SYNOPSIS N3220520R4077 USNS WILLIAM MCLEAN.docx | DOCX document | |
| SOURCES SOUGHT FOR USNS MCLEAN MTA 2020.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N3220520R4077
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION B - SUPPLIES OR SERVICES AND PRICES
The following have been added by full text:
AMENDMENT 2 RFCS
REQUEST FOR SPECIFICATION CLARIFICATION
SPECIFICATION ITEM NO.: 102 - 105
PARAGRAPH / SECTION NO: N/A
TITLE: Various
QUESTION 4:
We are pricing Items 102 thru 105 separately, but assume they would be released and worked as a group to achieve the best possible pricing for MSC. Please advise if this assumption is correct.
ANSWER:
Work items 102 through 105 can be worked simultaneously, however the offeror should know the crew will remain onboard during the availability.
SPECIFICATION ITEM NO.: 102
PARAGRAPH / SECTION NO: Various
TITLE: Renew 06 Level Non-Skid
QUESTION 5:
1. Can we assume the 800 square feet noted in 3.1.2 is a continuous, unbroken area and not scattered spot work?
2. What “structure inside this perimeter” should be allowed for i.e. clover leafs, D rings, foundations, etc (7.2) or is the work area the flat deck?
3. Can we assume that the approval for UHP water blasting (7.4.7 and 7.4.7.i) will be allowed or should we provide pricing for each option i.e. girt and water?
4. Can the coating be applied via brush and roll or must these coating be applied via airless spray?
5. The finish coat of non-slip (not non-skid) is 385 ASA (4.2.4, 7.5.6.d, 7.5.7). In past experiences with this product it’s normally applied at 4 to 6 mils DFT. The application procedure defined in 7.5.7 a – g is for Amercoat 138G (which is not listed as a GFM in 4.2.4). Is the finish coat non-slip (385ASA) or non-skid (138G)?
6. Can the owner advise what deck markings (7.6.1) are involved with this item?
ANSWER:
The square footage has been increased and Work Item updated to reflect the increase based on conversations with the Ship as well as application of ASA385. Contracting will provide an updated work item.
The Offeror shall note not all areas are continuous and are expected to be broken up totaling the square footage estimated.
The Offeror should expect bulkheads, cable penetrations, fishplates and other areas that require containment.
Correction on application of ASA application, revised Work Item will reflect application.
The Offeror has the approval to use UHP water blasting vice grit blast as long as it meets the local area of environmental standards.
Work items explicitly states Non-Slip brush/Spray applications are not permitted.
All deck markings shall be identified upon starting.
SPECIFICATION ITEM NO.: 103
TITLE: Renew 05 Level Non-Skid
QUESTION 6:
1. Can we assume the 800 square feet noted in 3.1.2 is a continuous, unbroken area and not scattered spot work?
2. What “structure inside this perimeter” should be allowed for i.e. clover leafs, D rings, foundations, etc (7.2) or is the work area the flat deck?
3. Can we assume that the approval for UHP water blasting (7.4.7 and 7.4.7.i) will be allowed or should we provide pricing for each option i.e. girt and water?
4. Can the coating be applied via brush and roll or must these coating be applied via airless spray?
5. The finish coat of non-slip (not non-skid) is 385 ASA (4.2.4, 7.5.6.d, 7.5.7). In past experiences with this product it’s normally applied at 4 to 6 mils DFT. The application procedure defined in 7.5.7 a – g is for Amercoat 138G (which is not listed as a GFM in 4.2.4). Is the finish coat non-slip (385ASA) or non-skid (138G)?
6. Can the owner advise what deck markings (7.6.1) are involved with this item?
ANSWER:
The square footage has been increased and Work Item updated to reflect the increase based on conversations with the Ship as well as application of ASA385. Contracting will provide an updated work item.
The Offeror shall note not all areas are continuous and are expected to be broken up totaling the square footage estimated.
The Offeror should expect bulkheads, cable penetrations, fishplates and other areas that require containment.
Correction on application of ASA application, revised Work Item will reflect application.
The Offeror has the approval to use UHP water blasting vice grit blast as long as it meets the local area of environmental standards.
SPECIFICATION ITEM NO.: 104
TITLE: Renew 04 Level Non-Skid
QUESTION 7:
1. Can we assume the 800 square feet noted in 3.1.2 is a continuous, unbroken area and not scattered spot work?
2. What “structure inside this perimeter” should be allowed for i.e. clover leafs, D rings, foundations, etc (7.2) or is the work area the flat deck?
3. Can we assume that the approval for UHP water blasting (7.4.7 and 7.4.7.i) will be allowed or should we provide pricing for each option i.e. girt and water?
4. Can the coating be applied via brush and roll or must these coating be applied via airless spray?
5. The finish coat of non-slip (not non-skid) is 385 ASA (4.2.4, 7.5.6.d, 7.5.7). In past experiences with this product it’s normally applied at 4 to 6 mils DFT. The application procedure defined in 7.5.7 a – g is for Amercoat 138G (which is not listed as a GFM in 4.2.4). Is the finish coat non-slip (385ASA) or non-skid (138G)?
6. Can the owner advise what deck markings (7.6.1) are involved with this item?
ANSWER:
The square footage has been increased and Work Item updated to reflect the increase based on conversations with the Ship as well as application of ASA385. Contracting will provide an updated work item.
The Offeror shall note not all areas are continuous and are expected to be broken up totaling the square footage estimated.
The Offeror should expect bulkheads, cable penetrations, fishplates and other areas that require containment.
Correction on application of ASA application, revised Work Item will reflect application.
The Offeror has the approval to use UHP water blasting vice grit blast as long as it meets the local area of environmental standards.
SPECIFICATION ITEM NO.: 105
TITLE: Renew 02 Level Non-Skid STA#8 Winch Deck
QUESTION 8:
1. Paragraph 3.1.1 notes 1,400 square feet of area while 3.1.3 notes 1,100 square feet, which is correct?
2. Can we assume the area noted (whichever is correct) is a continuous, unbroken area and not scattered spot work?
3. What “structure inside this perimeter” should be allowed for i.e. clover leafs, D rings, foundations, etc (7.1) or is the work area the flat deck?
4. Can we assume that the approval for UHP water blasting (7.3.6 and 7.3.6.a) will be allowed or should we provide pricing for each option i.e. girt and water?
5. Can the coating (with the exception of the 138G) be applied via brush and roll or must these coating be applied via airless spray?
6. Can the owner advise what deck markings (7.5.1) are involved with this item?
The WI was revised to reflect the correct square footage. The correct square footage approximation is 1500 sqft. A newly revised WI shall be provided by Contracting noting the change.
Station 8 Non-skid area is a continuous area (not partial).
Structures that are of a concern are the following, but not limited to, all UNREP equipment, bedplate, cable ways, cable deck penetrations, ladder or crane foundations etc.
Approval of UHP water blasting is approved.
Work item explicitly states Non-Slip brush/Spray applications are not permitted.
SPECIFICATION ITEM NO.: 101
PARAGRAPH / SECTION NO: 7.5
TITLE: HAZMAT CONTAINER REPLACEMENTS
QUESTION 9:
Please provide more details on the amount of ramp modification.
The Contractor shall assume all ramps shall be raised 3” to meet newly installed HAZMAT Containers inside surface height.
SPECIFICATION ITEM NO.: _101
PARAGRAPH / SECTION NO: 7.8
TITLE: HAZMAT CONTAINER REPLACEMENTS
QUESTION 10:
Will the containers need to be cleaned of hazardous materials before disposal?
If yes, please provide known materials.
The Work items says “Ships force will remove all material from each container and containers will be empty.”
SPECIFICATION ITEM NO.: 102
PARAGRAPH / SECTION NO: 7.3.7
TITLE: RENEW 06 LEVEL NON-SKID
QUESTION 11:
Please provide a list of interferences.
Interferences that shall exist will be (but not limited to) deck ladders, cable way/penetrations, deck drains, etc.
SPECIFICATION ITEM NO.: 103
TITLE: RENEW 05 LEVEL NON-SKID
QUESTION 12:
Interferences that shall exist will be (but not limited to) deck ladders, cable way/penetrations, deck drains, etc.
SPECIFICATION ITEM NO.: 104
TITLE: RENEW 04 LEVEL NON-SKID
QUESTION 13:
Interferences that shall exist will be (but not limited to) deck ladders, cable way/penetrations, deck drains, Fenders, etc.
SPECIFICATION ITEM NO.: 105
PARAGRAPH / SECTION NO: 7.2.5
TITLE: RENEW 02 LEVEL NON-SKID STA#8 WINCH DECK
QUESTION 14:
Interferences that shall exist will be (but not limited to) deck ladders, cable way/penetrations, deck drains, UNREP equipment, etc.
(End of Summary of Changes) image1.wmf