About this file

N32205-17-R-3407 Q&A 3-7

View the file

Other files

File Type Posted
N32205-17-R-3407_0004_Released.pdf PDF
N32205-17-R-3407_Amend_0003_Released.pdf PDF
N32205-17-R-3407_Amend_0002_released.pdf PDF
N32205-17-R-3407_Amend_0001_released.pdf PDF
Q_AND_A_1.docx DOCX document
N32205-17-R-3407_RFP.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question and Answer (Q&A) Sheet

Solicitation: N32205-17-R-3407 EOD Group Two The solicitation is available on www.FBO.gov at the link provided below:

https://www.fbo.gov/notices/8a76331d9334210bf6dd2706260f5d42

3) Question: Is the Eighty (80) Mbps requirement still valid?

Answer: No. See N32205-17-R-3407 Amendment 0002.

4) Question: Does the Upload/Download speed requirement of Eighty (80) Mbps apply only to pier side or does it also include underway?

Answer: See N32205-17-R-3407 Amendment 0002.

5) Question: Does the Eighty (80) Mbps upload/download speed requirement apply to all locations (pier side Little Creek, pier side other ports, and underway)?

Answer: See N32205-17-R-3407 Amendment 0002.

6) Question: Must the speed be 80 Mbps all the time (24 hours a day, 7 days a week)?

Answer: See N32205-17-R-3407 Amendment 0002.

7) Question: Are upload/download speeds of less than 80 Mbps acceptable underway?

Answer: See N32205-17-R-3407 Amendment 0002.

http://www.fbo.gov/

File details come from the government source that posted it. Updated .