J-3_Category_B_Items_Revised.xls

XLS spreadsheet 53 KB Posted

Attached to
REGULAR OVERHAUL/DRY-DOCKING (ROH)
Solicitation number
N32205-14-R-2000
Issued by

About this file

Revised J-3 for Work Item 025

View the file

Other files

File Type Posted
Amendment_0007.pdf PDF
SF_30.docx DOCX document
Released_Amend_0006.doc DOC document
Copy_of_J_-_2_Category_A_Items_-_USNS_ARCTIC_2014(6-2-14).xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cat B Items

Contractor's price will be broken down for each item of the specification, as follows:
CATEGORY “B” ITEMS
GENERAL REQUIREMENTPrice / TankQTYUIUnit PriceTotalPRIME ContractorSUBCONTRACTOROTHER COSTS
ITEM NO.TITLE CAT B ITEMPRIME L/HLABOR PRICEMATERIAL PRICESUB L/HLABOR PRICEMATERIAL PRICETotal Labor HoursTotal MaterialTOTAL PRICE
CATEGORY "B"
000GENERAL REQUIREMENTS
25PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY- 0$ - 0$0
FP CONDITION BRAVO Establish1Each$ - 0$0
FP CONDITION CHARLIE Establish1Each$ - 0$0
FP CONDITION DELTA Establish1Each$ - 0$0
FP CONDITION BRAVO Maintain1Day$ - 0$0
FP CONDITION CHARLIE Maintain1Day$ - 0$0
FP CONDITION DELTA Maintain1Day$ - 0$0
30CONTINUATION OF SERVICES
7.1OVERHAUL MANAGEMENT TEAM SERVICES (B-ITEM)15Days- 0$ - 0$0
7.2GENERAL SERVICES FOR THE SHIP (B-ITEM)15Days- 0$ - 0$0
7.3TELEPHONE SERVICES (B-ITEM)15Days- 0$ - 0$0
7.4PROJECT PLANNING AND MONITORING (B-ITEM)15Days- 0$ - 0$0
7.5FIRE PROTECTION AND SHIPS SAFETY (B-ITEM)15Days- 0$ - 0$0
7.6DELIVERY, CARE & REDELIVERY OF VESSEL (B-ITEM)15Days- 0$ - 0$0
7.7SHIPBOARD ACCESS AND SECURITY (B-ITEM)15Days- 0$ - 0$0
7.8GAS FREE CERTIFICATES (B-ITEM)15Days- 0$ - 0$0
$0
200PROPULSION, MACHINERY
204LINE SHAFT BEARINGS REBABBIT3Each- 0$ - 0$0
500MACHINERY, AUXILIARY
503MISCELLANEOUS EQUIPMENT AND MOTOR OVERHAUL33Each
504LAGGING AND INSULATION REPAIRS485Lnr-FT
507ASSIST SHIPS FORCE720Hours
508JP-5 MOTOR AND PUMP OVERHAUL1Each
509DFM CARGO MOTOR AND PUMP OVERHAUL1Each
600OUTFIT, FURNISHING & HABITABILITY
605HELO DECK REFINISHING
900DRYDOCKING AND UNDOCKING
902DRY-DOCKING AND UNDOCKING VESSEL15Days
918ULTRASONIC TESTING1100 Shots
919REPLACE STERN TUBE SHAFT BEARING LINERS3Each
920SHELL PLATE WELDING AND REPAIR
7.2.5WELD SEAM REPAIR150Each
7.3.5CLAD WELD60Each
7.4.5BELZONA 1111 APPLICATION25Each
7.5.5BELZONA 5811 IMMERSION APPLICATION30Each
7.6.5INTERGARD 822 FILLER APPLICTION25Each
921STEEL RENEWAL
7.2.1MISC DECKS & BHDS3000LBS
7.2.2BHD/DECK STIFFENERS1000LBS
7.2.3SHELL PLATING4000LBS
7.2.4SHAPED SHELL PLATING8000LBS
7.2.5TANK BHD1000LBS
7.2.6TANK INTERNALS1000LBS
7.2.7SHELL FRAMING & STIFFENERS4000LBS
7.2.8TANK TOP IN MACH SPC3000LBS
7.2.9MACHINERY FOUNDATIONS IN ENG RM1000LBS
7.2.10FLOOR & INTERCOSTALS IN DB TKS1000LBS
7.2.11DB STIFFENERS & BHD1000LBS
7.2.12MACHINERY FOUNDATTIONNS ON DECK1000LBS
922RESERVE FEED AND CONDENSATE TANK PAINTING4TANK
TOTALSTotal CAT "B"$0.00

&L&14USNS ARCTIC (T-AOE 8) Sol. No. N32205-14-R-2000&C&14CONTRACTOR PRICE BREAKDOWN &"Arial,Bold"CATEGORY "B" ITEMS&R&14N32205-14-R-2000

&CATTACHMENT J-3

Sheet1