Q:
What is the anticipated start date of this project?
Also, Regarding replacing the absorber material, do you have existing absorber material on site or will the contractor be responsible for purchasing and replacing the new absorber material?
A:
The work will have to be scheduled around our project work for the chambers. Once a vendor is selected we will work with them to work out a schedule for each chamber.
We do have extra absorber and would provide that first.