N0040618Q0354_N00406-18-Q-0354_Amendment_0001.docx
DOCX document 57 KB Posted
- Attached to
- Floating Concrete Docks
- Solicitation number
- N0040618Q0354
About this file
N0040618Q0354_N00406-18-Q-0354_Amendment_0001.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N00406-18-Q-0354.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N0040618Q0354
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
Q & A Question 1. Section II - 2. States "Concrete floats to be manufactured from a durable crack proof concrete, suitable for salt water usage. Contractor to include the concrete's durability spec.'s, expected performance in salt water environments and through the local freeze/thaw cycles, as well as the ability of the mixture and structural design to minimize crack formation and propagation. Suggest using 120 to 150-pound concrete with a 5000 PSI." We would like a clarification on the term "crack proof" as we believe this is an unattainable specification. In our experience all concrete cracks to some degree and we take every precaution during the design and construction of our floats to limit and minimize potential cracking. We suggest striking the term "crack proof" as the rest of the paragraph addresses the structural design to minimize crack formation and better represents the industry standard.
Answer 1: Crack proof specification requirement description removed. See revised PWS.
Question 2. Section II - 4 calls for type II cement, recently the regions ready mix suppliers have moved to type IL cement, which is equal to or better than type II. Currently type II is not available in the region. We request type IL be allowed with approval from the project engineer.
Answer 2: Type IL cement specifications accepted. See revised PWS.
SECTION SF 1449 - CONTINUATION SHEET
The following have been added by full text:
52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE (AUG 1996)
(a) Definition. "Supplies," as used in this clause, includes but is not limited to raw materials, components, intermediate assemblies, end products, and lots of supplies.
(b) The Contractor shall provide and maintain an inspection system acceptable to the Government covering supplies under this contract and shall tender to the Government for acceptance only supplies that have been inspected in accordance with the inspection system and have been found by the Contractor to be in conformity with contract requirements. As part of the system, the Contractor shall prepare records evidencing all inspections made under the system and the outcome. These records shall be kept complete and made available to the Government during contract performance and for as long afterwards as the contract requires. The Government may perform reviews and evaluations as reasonably necessary to ascertain compliance with this paragraph. These reviews and evaluations shall be conducted in a manner that will not unduly delay the contract work. The right of review, whether exercised or not, does not relieve the Contractor of the obligations under the contract.
(c) The Government has the right to inspect and test all supplies called for by the contract, to the extent practicable, at all places and times, including the period of manufacture, and in any event before acceptance. The Government shall perform inspections and tests in a manner that will not unduly delay the work. The Government assumes no contractual obligation to perform any inspection and test for the benefit of the Contractor unless specifically set forth elsewhere in this contract.
(d) If the Government performs inspection or test on the premises of the Contractor or a subcontractor, the Contractor shall furnish, and shall require subcontractors to furnish, at no increase in contract price, all reasonable facilities and assistance for the safe and convenient performance of these duties. Except as otherwise provided in the contract, the Government shall bear the expense of Government inspections or tests made at other than the Contractor's or subcontractor's premises; provided, that in case of rejection, the Government shall not be liable for any reduction in the value of inspection or test samples.
(e)(1) When supplies are not ready at the time specified by the Contractor for inspection or test, the Contracting Officer may charge to the Contractor the additional cost of inspection or test.
(2) The Contracting Officer may also charge the Contractor for any additional cost of inspection or test when prior rejection makes reinspection or retest necessary.
(f) The Government has the right either to reject or to require correction of nonconforming supplies. Supplies are nonconforming when they are defective in material or workmanship or are otherwise not in conformity with contract requirements. The Government may reject nonconforming supplies with or without disposition instructions.
(g) The Contractor shall remove supplies rejected or required to be corrected. However, the Contracting Officer may require or permit correction in place,promptly after notice, by and at the expense of the Contractor. The Contractor shall not tender for acceptance corrected or rejected supplies without disclosing the former rejection or requirement for correction, and, when required, shall disclose the corrective action taken.
(h) If the Contractor fails to promptly remove, replace, or correct rejected supplies that are required to be removed or to be replaced or corrected, the Government may either (1) by contract or otherwise, remove, replace, or correct the supplies and charge the cost to the Contractor or (2) terminate the contract for default. Unless the Contractor corrects or replaces the supplies within the delivery schedule, the Contracting Officer may require their delivery and make an equitable price reduction. Failure to agree to a price reduction shall be a dispute.
(i)(1) If this contract provides for the performance of Government quality assurance at source, and if requested by the Government, the Contractor shall furnish advance notification of the time (i) when Contractor inspection or tests will be performed in accordance with the terms and conditions of the contract and (ii) when the supplies will be ready for Government inspection.
(2) The Government's request shall specify the period and method of the advance notification and the Government representative to whom it shall be furnished. Requests shall not require more than 2 workdays of advance notification if the Government representative is in residence in the Contractor's plant, nor more than 7 workdays in other instances.
(j) The Government shall accept or reject supplies as promptly as practicable after delivery, unless otherwise provided in the contract. Government failure to inspect and accept or reject the supplies shall not relieve the Contractor from responsibility, nor impose liability on the Government, for nonconforming supplies.
(k) Inspections and tests by the Government do not relieve the Contractor of responsibility for defects or other failures to meet contract requirements discovered before acceptance. Acceptance shall be conclusive, except for latent defects, fraud, gross mistakes amounting to fraud, or as otherwise provided in the contract.
(l) If acceptance is not conclusive for any of the reasons in paragraph (k) hereof, the Government, in addition to any other rights and remedies provided by law, or under other provisions of this contract, shall have the right to require the Contractor (1) at no increase in contract price, to correct or replace the defective or nonconforming supplies at the original point of delivery or at the Contractor's plant at the Contracting Officer's election, and in accordance with a reasonable delivery schedule as may be agreed upon between the Contractor and the Contracting Officer; provided, that the Contracting Officer may require a reduction in contract price if the Contractor fails to meet such delivery schedule, or (2) within a reasonable time after receipt by the Contractor of notice of defects or nonconformance, to repay such portion of the contract as is equitable under the circumstances if the Contracting Officer elects not to require correction or replacement. When supplies are returned to the Contractor, the Contractor shall bear the transportation cost from the original point of delivery to the Contractor's plant and return to the original point when that point is not the Contractor's plant. If the Contractor fails to perform or act as required in (1) or (2) above and does not cure such failure within a period of 10 days (or such longer period as the Contracting Officer may authorize in writing) after receipt of notice from the Contracting Officer specifying such failure, the Government shall have the right by contract or otherwise to replace or correct such supplies and charge to the Contractor the cost occasioned the Government thereby.
(End of clause)
The following have been modified:
PWS
Performance Work Statement Floating Concrete Docks
Navy Region Northwest, Port Operations, Code N31, requests to purchase new floating concrete docks (also referred to as concrete floats). Contractor to provide new concrete monolithic type floats to replace current steel floats. These types of concrete floats are formed by the interconnection of modules consisting of polystyrene foam billets that are fully encased with concrete. Concrete floats will include, utility trenches for large shore power cables, float to float connection points, rub strips, mooring cleats and bitts, D-rubber, and piling collars. Concrete floats must have the capability to connect together to form long extended mooring configurations up to 600 foot or more in length. This requirement is for four (4) 15 ft. wide X 60 ft. long concrete floats and one (1) 30 ft. wide X 60 ft. long concrete float with the same characteristics.
I. Concrete Floats Specifications:
A. Size:
a. 15 ft. wide X 60 ft. long (QTY 4 Each)
b. 30 ft. wide X 60 ft. long (QTY 1 Each)
| B. Freeboard: 30” inches | |
| C. Able to support Sea state 4 | |
| II. | Fabrication specifications for the concrete floats: |
A. Precast Concrete Float Requirements:
1. Concrete mooring floats shall be monolithic style sections fabricated in modules corresponding to the nominal length, widths, and geometric cross sections. All forces and loads imposed on the float system shall be borne by the concrete float structure. The use of longitudinal whalers to support structural loads or to interconnect the float units will not be accepted.
2. Concrete floats to be manufactured from a durable concrete, suitable for salt water usage. Contractor to include the concrete’s durability spec.’s, expected performance in salt water environments and through the local freeze/thaw cycles, as well as the ability of the mixture and structural design to minimize crack formation and propagation. Suggest using 120 to 150-pound concrete with a 5000 PSI.
2. All corners of concrete shall be eased with chamfers or rounding. Transitions between thick and thin concrete sections or between horizontal and vertical sections shall be eased with chamfers.
3. Float sidewalls shall be full-depth concrete, leaving no portion of the sidewall floatation exposed to damage.
4. Cement shall be Normal weight Portland cement type IL or type II, in accordance with ACI 318, ACI 357R and ASTM C94, for strength, durability, serviceability, cold weather, and exposure to the marine environment.
5. Float top surfaces shall be crowned for positive drainage, struck off, and steel troweled after the initial set. Edges shall be finished with a 3/8-inch radius edger. The walking surface of the float shall be given a final course "broom" finish by texturing to the longitudinal centerline of the float. All float tops and exposed surfaces shall be treated with an approved concrete sealant after curing and drying. The walking surface of the concrete floats shall be crowned and shall be flush with the adjacent floats.
B. Concrete reinforcement:
1. Contractor shall maintain the minimum concrete steel reinforcement requirements as indicated in ACI 357R-84 Section 4.5.6.
2. Welded wire fabric shall be in accordance with ASTM A185 and shall be galvanized. Welded wire fabric or wire mesh will not be accepted for use as primary reinforcement. Wire mesh shall be new, clean, and shall be ordered in flat sheets.
3. All reinforcing steel shall be from new billet and conform to ASTM A615, Grade 60 for deformed bars and shall be galvanized in accordance with ASTM A767. Lap all reinforcing bars a minimum of 12 inches at the joints and splices.
| 4. | Reinforcement steel shall be galvanized and shall conform to the requirements of | ASTM A767 and ASTM A143. Bars shall be galvanized after fabrication. Tie all | galvanized steel bars with galvanized ties. | ||||||||||||||||||
| 5. | All reinforcing shall have a minimum concrete cover in accordance with ACI | 357R-84. | |||||||||||||||||||
| C. Structural steel | |||||||||||||||||||||
| 1. | All structural steel and structural steel fabrication, including but not limited to, | pile guides, plates, and shapes shall be in accordance with ASTM A36 or ASTM A572. | Cold formed hollow structural sections shall be in accordance with ASTM A500, Grade B. | All steel fabrications and components shall be hot-dipped galvanized after fabrication in | accordance with ASTM Al23. | ||||||||||||||||
| 2. | Steel fabrication shall be performed in accordance with AISC S335. | ||||||||||||||||||||
| 3. | Fasteners for rub strips: Bolts shall conform to ASTM A307 or A36 as applicable, | with ASTM A563 hex nuts and flat washers. Malleable iron washers are required in all | cases (except economy head bolts) where the bolt heads or nuts would otherwise bear | directly | on the rub strip. Locking nuts shall be heavy hex head and self-locking type. All | bolts, nuts, washers, etc. shall be hot-dipped galvanized in accordance with ASTM Al53. | |||||||||||||||
| 4. | Bolts for float connections and metal fabrications shall be ASTM A325 and shall | be hot dip galvanized after fabrication in accordance with ASTM A153. | |||||||||||||||||||
| 5. | All structural bolts, including utility mounting and cleat bolts shall be through- | bolted in concrete, unless noted otherwise on the Drawings, and shall be capable of | developing their full allowable strength without causing damage to the concrete float. | Provide plate washers on all nut-bearing surfaces. All bolt heads beating on exposed | concrete surfaces shall be recessed flush with the adjacent concrete. Bolts shall be | economy head type and have a neoprene or polyethylene washer between the head of | the bolt and the concrete. Epoxy grouted or cast-in inserts shall not be used for structural | connections between floats. Primary connection bolts shall be a minimum of 3/4-inch | diameter. | ||||||||||||
| D. Float Internal componets | |||||||||||||||||||||
| 1. | Request the vendor use expanded Polystyrene core foam. Float inner cores | shall be filled from side wall to side wall with closed-cell corrosion proof, expanded | rigid cellular polystyrene foam in accordance with ASTM C578. | ||||||||||||||||||
| 2. | Float Structural Section shall be either inverted channel or box based. Where | inverted channel sections are utilized, the sides and bottom of the float, shall be | sealed with a spray applied and cured, durable compound suitable for use to protect | polystyrene foam in marine environments and that provides appropriate durability and | design life. | ||||||||||||||||
| 3. | Float material surfaces not protected by concrete, shall be sealed in | accordance with applicable Federal, and State criteria. These exposed float material | surfaces shall be sealed with a spray applied and cured, durable compound suitable | for use to protect polystyrene foam in marine environments and that provides | appropriate durability and design life. Sealant shall be continued a minimum of 6 | inches up the sidewall of the float. | |||||||||||||||
| E. Float Connection points | |||||||||||||||||||||
| 1. | Steel fabrications and connections shall be designed by the Float Supplier. | Steel fabrications and associated connections to the concrete floats shall be designed | to develop the full capacity of the pertinent structural member connected. | ||||||||||||||||||
| 2. | Float connections (Connecting one float to another) shall be noiseless and non- | wearing. Float connections shall be designed to distribute loads based on the relative | flexibility of the | specified piles and supplier designed float assembly. Connection | designs shall consider joint rotation effects so that contact, abrasion or subsequent | damage between unprotected float elements does not occur due to wave and live load | effects. Floats with special loading (DL and/or LL) shall have similar freeboard as | adjacent floats with no such loading such that no residual stresses or tilting when the | floats are interconnected. Walking surfaces of the floats shall be flush with adjoining | float units. | |||||||||||
| 3. | Primary connection bolts for float unit to unit assembly shall be a minimum of 3/4- | inch diameter. All other bolts shall be a minimum of 5/8-inch diameter. | |||||||||||||||||||
| F. Cleats and Bitts | |||||||||||||||||||||
| 1. | Request 7” bitts with 18” crossbars-placed every 20 feet on the shipboard side | of the float. Bitts to be strong enough to moor vessels of the following size: | |||||||||||||||||||
| a. 109’ long, 33’ Wide, and weigh 400 Tons. | |||||||||||||||||||||
| 2. | Request cleats be placed every 6 feet on the shipboard side of the float. Cleats | shall be heavy duty, galvanized SEA-DOG, or approved equal, located every six | feet on the shipboard side of the floats. | ||||||||||||||||||
| a. Cleat connections within the concrete floats shall be designed by the | Supplier for working loads specified. The applied load shall be applied at 6 | inches above the finished deck, parallel to the deck surface and normal to the | direction of the float element. The working cleat loads are as follows: | ||||||||||||||||||
| 18-inch cleat= 13,000 pounds (cleat and thru-bolts) | |||||||||||||||||||||
| 15-inch cleat= 10,000 pound (cleat and thru-bolts) | |||||||||||||||||||||
| b. Concrete reinforcement to support cleats shall meet requirements defined | in procurement drawings, utilizing a minimum of two rebar hairpins designed | to withstand 1.5 times the cleat working loads defined above without damage | to concrete. Cleat bolts shall shear prior to concrete damage. The concrete | reinforcement load demands are as follows: | |||||||||||||||||
| 18-inch cleat= 20,000 pounds (concrete) | |||||||||||||||||||||
| 15-inch cleat= 15,000 pound (concrete) | |||||||||||||||||||||
| G. Piling collars/Moorage attachments | |||||||||||||||||||||
| 1. | Floats to include piling collars to facilitate the install of the concrete floats to the | pier. The piling collars/moorage attachments-(the way the concrete floats are attached to | the pilings) shall be manufactured to transfer working horizontal loads, acting in any | direction, between the float, the mooring and the piling itself, with due consideration to | the dynamic nature of the load and the resulting fatigue and wear on the connecting | surfaces. | |||||||||||||||
| 2. | Piling collars shall be portable, detachable, and adjustable, within the individual | concrete float. Floats will be moved frequently to various locations where the piling | configuration may be different. Piling collars shall be non-rigid with a flexible collar, and | may also be made with a two-part collar assembly that includes a chain mechanism and | a flexible collar. These may be needed so the floats can travel easily up and down the | pilings during extreme tidal changes. The piling collars should also be maintenance free. | |||||||||||||||
| H. Utility Trenches | |||||||||||||||||||||
| 1. | Floats to include Utility trenches with metal covers to facilitate electrical cables | and hoses. Suggested size to be 2’ foot wide X 1’ foot deep to accommodate large | shore power cables, and hoses. | ||||||||||||||||||
| 2. | Trenches shall have a type of non-skid cover to prevent slippage in wet or icy | weather conditions. Suggest that the trenches run port to stbd across the float. Exact | locations to be determined, after the contractor has been selected. All steel plate used | shall have a 1/4 – inch minimum thickness. | |||||||||||||||||
| I. D-rubber fendering | |||||||||||||||||||||
| 1. | Floats to have 6-inch D-rubber fendering on the ship side of the float. | ||||||||||||||||||||
| a. Size: Height 6”, Base width 6 ¾”. Color: black | |||||||||||||||||||||
| b. Compound: EPDM, Durometer: 70=/-5, | |||||||||||||||||||||
| III. | Design load criteria for the Concrete floats | ||||||||||||||||||||
| A. Provide float units, connections and pile restraints capable of withstanding | design | loading criteria indicated below: | |||||||||||||||||||
| Freeboard: 30-inches on all floats under dead loads. | |||||||||||||||||||||
| Dead Load: Dead loads shall consist of the float system, rub strips, and piling collars, and | all other attached appurtenances. Under all Dead Loads, all exposed elements of | utilities and the float connection system such as connecting hardware, cleat hardware, | and rub strips shall be greater than or equal to 6-inches above the water surface. | ||||||||||||||||||
| Concentrated Load: 400 lbs., distributed over 144-square inches, placed anywhere on | floats. | ||||||||||||||||||||
| When 400 lb. concentrated load is applied at 1-foot from the outer end of the float, the | end of the float shall lose less than 4-inches of freeboard at time of installation and less | than 6-inches after five years of operation. | |||||||||||||||||||
| When 200 lbs. is applied on one outer comer of the float, there shall be no more than 2- | inches in freeboard differential. | ||||||||||||||||||||
| Wind Load: 85 mph basic wind speed (3-second gust), 70 mph fastest mile, IBC | exposure. Apply wind load on exposed over-water vessel profiles. Consider both end | and side loading conditions and sheltering effects. | |||||||||||||||||||
| Design wave: 1.5 feet in height, with varying wave lengths corresponding to wave | periods of 2 seconds. | ||||||||||||||||||||
| Design pressure for current: 3.0 pounds per square foot | |||||||||||||||||||||
| Impact Load: Forward velocity of 1.0 knots, vessel berthing angle of 10 degrees for | largest boat normally using slip, striking at the end of a finger or end of a main float. | ||||||||||||||||||||
| Level Tolerances: The deck of the float system shall be within the following level | tolerances for the life of the system: | ||||||||||||||||||||
| Maximum transverse tilt angle for floats: 3 degree | |||||||||||||||||||||
| Maximum longitudinal slope for floats: 1-inch per 20-feet | |||||||||||||||||||||
| Maximum vertical and horizontal differential between adjacent floats at any point across | the float connection: 1-inch |
THE FOLLOWING NAVSUP LOCAL TEXT IS HEREBY MADE PART OF THE STATEMENT OF WORK/PERFORMANCE WORK STATEMENT.
NAVSUP FLCPS may utilize contractor support through the AbilityOne Program, as needed, to perform contract closeout functions for this acquisition. Information, including business sensitive/confidential or proprietary data, that the offeror provides to the Government or information already in the possession of the Government may be viewed and utilized by the AbilityOne Program support contractor personnel during the course of its contract performance. The information that may be made available to the support contractor may include, for example, pricing and technical proposals, historical contract, pricing and performance information, Commercial Asset Visibility (CAV) reporting information and similar data/information.
By submission of a proposal in response to this solicitation, the offeror and its subcontractors consent to a release of their business sensitive/confidential or proprietary data to the Government's AbilityOne Program support contractor personnel in order to perform close out services. Prior to the release of any such information to the support contractor, the support contractor will have in place with the Government a Non-Disclosure/Non-Use Agreement in accordance with the terms of the AbilityOne Program support contract.
Offerors may execute their own Non-Disclosure Agreement with the AbilityOne Program (AbilityOne contact information available from the contracting point of contact). The support contractor must provide copies of the executed agreements to the Contracting Officer and the Contracting Officer's Representative (COR) for the support contract; and the offeror/contractor for this acquisition must provide copies of the executed Agreement to the Contracting Officer for this acquisition. If the offeror/contractor seeks such a Non-Disclosure Agreement with the AbilityOne Program support contractor, the Agreement must be executed no later than the date of final delivery under the resulting NAVSUP FLCPS contract.