Definitization of Equitable Adjustments.docx

DOCX document 23 KB Posted

Attached to
Bldg. 894 - Create Bldg. Security Boundary Federal contract opportunity
Solicitation number
N0025324R5002
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This document is a summary of equitable adjustments to construction contracts. It shows the time taken to definitize change order proposals under various timeframes, with the majority taking 91 to 365 days to definitize.

The related federal contract opportunity is for a project to upgrade Building 894 at the Naval Undersea Warfare Center Division Keyport to create a secure building boundary. The scope includes security upgrades such as adding security bars, door removal and wall infill, and installing emergency eyewash stations and compressed gas bottle racks. The government intends to award a single firm-fixed-price service contract, with a planned solicitation release date of February 13, 2024 and a 30-day response time. The contract will be 100% set aside for small businesses under NAICS code 238290, with a $22 million size standard. The contracting office is the Naval Sea Systems Command.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Definitization of Equitable Adjustments.

Selected Agency:
DEPT OF THE NAVY
Time to definitize after receipt of an adequate Change Order Definitization Proposal under Construction Contracts
Number of Change Order Proposals definitized under Construction Contracts
30 days or less
2
31 to 60 days
3
61 to 90 days
3
91 to 180 days
5
181 to 365 days
5
Greater than 365 days
2

After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance