Draft RFP.pdf
PDF 915 KB Posted
- Attached to
- Light Vertical Bulkhead & Support Plate
- Solicitation number
- N0025324R0004
About this file
This document is a pre-solicitation notice for a forthcoming Request for Proposals (RFP) solicitation from the Naval Undersea Warfare Center Division (NUWC) Keyport. The solicitation, numbered N0025324R0004, will be a 100% Small Business Set-Aside for the procurement of Light Vertical Bulkheads (P/N: 7053453) and Support Plates (P/N: 7053454) in accordance with specific NAVSEA drawings. The items are required for the continued production of MK48 Fuel Tank Assemblies. The government anticipates awarding a single firm-fixed price contract. Solicitation N0025324R0004 is expected to be issued on or about September 23, 2024, with a 30-day response period. Pricing is required on a FOB Destination basis to NUWC Keyport, Washington. The applicable NAICS code is 332313 with a 750 employee size standard. Special security requirements apply, and only vendors registered with the Defense Logistics Information Services Joint Certification Program will have access to the restricted technical drawings and information.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pre-Solicitation_Synopsis.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until local time
X
A X B X C X D
EX
X
G F 47 - 57
58 - 74 X H 75 - 80
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
DO-C9 1 80
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
N00253 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 9
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
10 - 19 20 - 22
J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
23 - 26 27 - 28
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 29 - 34 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 35 - 38 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIONS AND INSTRUCTIONS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
39 - 45
PART II - CONTRACT CLAUSES
NAVAL UNDERSEA WARFARE CENTER
ATTN: REBECCA JETT
REBECCA.JETT@NAVY.MIL
610 DOWELL STREET, BLDG 206
KEYPORT WA 98345
360-315-6798
FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.5. DATE ISSUED4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
N0025324R0004
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 10 Each Light Vertical Bulkhead (FAT)
FFP
*** This is a first article/pre-production requirement. ***
Manufacture IAW NAVSEA Drawing number 7053453 Rev D, and associated drawing number PL7053453 Rev C, Hardware must be marked with 53711- 7053453 in accordance with SAE-AS478 per drawing.
FOB: Destination
PSC CD: 5342
NET AMT
0002 90 Each Light Vertical Bulkhead (PRODUCTION)
FFP
*** This is a production requirement. ***
Manufacture IAW NAVSEA Drawing number 7053453 Rev D, and associated drawing number PL7053453 Rev C, Hardware must be marked with 53711- 7053453 in accordance with SAE-AS478 per drawing.
0003 10 Each Support Plate (FAT)
FFP
*** This is a first article/pre-production requirement. ***
Manufacture IAW NAVSEA Drawing number 7053454 Rev E, and associated drawing # PL7053454 Rev C, Hardware must be marked with 53711-7053454 in accordance with SAE-AS478 per drawing.
0004 90 Each Support Plate (PRODUCTION)
FFP
*** This is a production requirement. ***
Manufacture IAW NAVSEA Drawing number 7053454 Rev E, and associated drawing # PL7053454 Rev C, Hardware must be marked with 53711-7053454 in accordance with SAE-AS478 per drawing.
0005 1 Lot Request for Variance CDRL A001
FFP
*** Not Separately Priced ***
Data in accordance with Exhibit A, Data Items A001: Contract Data Requirements Lists, DD Form 1423-1 (Not Separately Priced).
CDRLs required with every delivery of materials (FA units, and Production units).
1002 100 Each OPTION Light Vertical Bulkhead
FFP
*** This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR I. ***
Refer to CLIN 0002 Manufacture IAW NAVSEA Drawing number 7053453 Rev D, and associated drawings.
FOB: Destination
DWG NR: 7053453
1004 100 Each OPTION Support Plate
FFP
*** This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR I. ***
Refer to CLIN 0004: Manufacture IAW NAVSEA Drawing number 7053454 Rev E, and associated drawings.
FOB: Destination
DWG NR: 7053604
2002 100 Each OPTION Light Vertical Bulkhead
FFP
*** This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR I. ***
Refer to CLIN 0002 Manufacture IAW NAVSEA Drawing number 7053453 Rev D, and associated drawings.
FOB: Destination
2004 100 Each OPTION Support Plate
FFP
*** This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR I. ***
Refer to CLIN 0004: Manufacture IAW NAVSEA Drawing number 7053454 Rev E, and associated drawings.
FOB: Destination
3002 100 Each OPTION Light Vertical Bulkhead
FFP
*** This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR I. ***
Refer to CLIN 0002 Manufacture IAW NAVSEA Drawing number 7053453 Rev D, and associated drawings.
FOB: Destination
3004 100 Each OPTION Support Plate
FFP
*** This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR I. ***
Refer to CLIN 0004: Manufacture IAW NAVSEA Drawing number 7053454 Rev E, and associated drawings.
FOB: Destination
4002 100 Each OPTION Light Vertical Bulkhead
FFP
*** This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR I. ***
Refer to CLIN 0002 Manufacture IAW NAVSEA Drawing number 7053453 Rev D, and associated drawings.
FOB: Destination
4004 100 Each OPTION Support Plate
FFP
*** This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR I. ***
Refer to CLIN 0004: Manufacture IAW NAVSEA Drawing number 7053454 Rev E, and associated drawings.
FOB: Destination
Section C - Descriptions and Specifications
STATEMENT OF WORK
STATEMENT OF WORK
Light Vertical Bulkhead and Support Plate
1. SCOPE
Naval Undersea Warfare Center Division, Keyport is seeking to procure Light Vertical Bulkheads and Support Plates for the MK 48 Heavyweight Fuel Tank Assembly. This statement of work (SOW) defines the scope of work required to produce, test, and deliver MK 48 Heavyweight (HWT) Fuel Tank components. Components include Light Vertical Bulkheads (P/N: 7053453) and Support Plates (P/N: 7053454) for the continued production of MK48 Fuel Tank Assemblies in Depot repair. The contractor shall provide all necessary facilities, resources, and management required to meet the production, test, and delivery requirements of both light vertical bulkheads and support plate configurations.
2. APPLICABLE DOCUMENTS
2.1 DRAWINGS
Table 1 – Drawing No., Type, Revision and Title
DWG/DOC
NUMBER
TYPE REV TITLE
7053453 FN D VERTICAL BULKHEAD, LIGHT
7053454 FN E SUPPORT PLATE
7053487 FN A EPOXY PRIMER
7053488 FN A TOP COAT, POLYURETHANE GLOSS
PL7053453 FN C VERTICAL BULKHEAD, LIGHT Part List PL7053454 FN C SUPPORT PLATE Part List
MIL-I-24768 FN PLATE, FIBERGLASS EPOXY RESIN,
TYPE GEE (G10) M24768/2-S-19
SAE-AMS3145 FN PAINT, MARKING EPOXY
2.2 SPECIFICATIONS AND STANDARDS
- ANSI/ASQ Z1.4-2003 (R2013)
- ISO 9001-2008
- SAE AMS3145
- MIL-I24768
3. REQUIREMENTS
3.1 CLINs 0001 & 0002
The contractor shall manufacture and provide NUWC Division Keyport, with ten (10) first article testing (FAT) Units and 90 production units of Light Vertical Bulkhead, in accordance with (IAW) NAVSEA Drawing 7053453, Revision D, Baseline with Drawing Reference - Sequential, and all associated drawings, changes, and specifications. Four (4) options periods with 100 production lot units each.
First Articles can be waived if from qualified sources.
3.2 CLIN 0003 - 0004
The contractor shall manufacture and provide NUWC Division Keyport, with ten (10) first article testing (FAT) Units and 90 production units of Support Plate, in accordance with (IAW) NAVSEA Drawing 7053454 Revision E , Baseline with Drawing Reference - Sequential, and all associated drawings, changes, and specifications. Four (4) options periods with 100 production lot units each.
First Articles can be waived if from qualified sources.
3.3 CLIN 0005 – CDRL
Submit a request for variance for any deviations, change requests or vendor recommendations to reference CLINs 0001 and 0003 using Contract Data Requirements List (CDRL) A001 REQUEST FOR VARIANCE (RFV) Number: DI-SESS-80640E.
There is no substitution of material allowed without prior consent of Technical Point of Contact (TPOC) via contract modification signed by the Procuring Contracting Officer (PCO).
4. SECURITY REQUIREMENTS
4.1 General Security Requirement
4.1.1 The requirements of this contract contain Covered Defense Information (CDI). Per DFARS 253.204-7019, Notice of NIST SP 800-171 DoD Assessment Requirements, the National Institute of Standards and Technology (NIST) Special Publication (SP) 800-171 applies to this procurement. The Offeror shall have a current (not more than three (3) years old), minimum Confidence Level assessment of BASIC.
4.1.2 The requirements of this contract contain export-controlled Controlled Unclassified Information (CUI). To access and view the drawings, technical requirements, and critical item specifications the Vendor shall be registered in the Defense Logistics Agency (DLA) Joint Certification Program (JCP). Vendor shall submit a copy of the approved DD Form 2345 via email to the Contract Specialist/Purchasing Agent listed as the point of contact. Instructions for filing a DD Form 2345 can be found at the following web address, https://www.dla.mil/HQ/LogisticsOperations/JCP/SpecificDD2345Instructions.aspx . The contractor shall maintain a current Certification of eligibility from DLA, Joint Certification Office for access to export-controlled Controlled Unclassified Information (CUI).
4.1.3 Foreign Interests. Contractors with defined Foreign Interests (a Facility that is owned, controlled, or influenced by foreign interests) will ensure adherence to DoD and DON regulations, directives and policies. Full disclosure to the Contracting Officer, and Security Contracting Officer is required.
4.1.4 The Contractor shall reference the OPSEC Guide for Defense Contractors. Document can be downloaded from http://www.navsea.navy.mil/nuwc/Keyport/default.aspx; click on “OPSEC Guide for Defense Contractors” on the left-hand side. The Contractor shall issue the proper classification markings and maintain appropriate security.
5. LABEL AND PACKING
5.1 Hardware must be marked with 53711-7053453 or 7053454 in accordance with SAE-AS478 per drawing reference 3.1 & 3.2.
5.2 Mark packaging label with Manufacturer, NSN, Nomenclature, Part Number, Vendor Cage Code and Contract Number
5.3 Package material with best commercial practices to ensure no damage to parts.
6. DELIVERY, INSPECTION AND ACCEPTANCE
6.1 Delivery
6.1.1 FAT REQUIREMENTS Delivery within 60 days After Date of Contract
6.1.2 PRODUCTION REQUIREMENTS Delivery within 60 days After First Article Testing Acceptance
6.1.3 OPTIONS Delivery within 60 days After Option Exercise
6.1.4 Certificate of Conformance is required and shall accompany all deliveries.
6.1.5 Vendor to provide shipping and tracking information as it becomes available to vendor to technical POC by phone and email
6.1.6 Early and partial deliveries are encouraged and acceptable.
6.2 Inspection & Acceptance
6.2.1 The government will inspect first articles within 45 days of receipt of material on NUWC Division Keyport.
6.2.2 The government will perform periodic inspection of production units. Acceptance will occur within 60 days of receipt of material on NUWC Division Keyport.
6.2.3 Confirm material packaging is labeled with Part Number, Contract Number and Vendor Cage Code
6.2.4 The Government will perform IC inspection of the 10 FAT units, verify material complies with reference 2.1 and 2.2. The government will use a Coordinate Measuring Machine (CMM) to perform validation (or equivalent). Critical Dimensions: Includes all diameters, locations, and surface finish requirements of reference 3.1 & 3.2.
6.2.5 The Government will perform periodic IC inspection up to 10% of each production lot quantity. The government will use a Coordinate Measuring Machine (CMM) to perform validation (or equivalent). Critical Dimensions: Includes all diameters, locations, and surface finish requirements of reference 3.1 & 3.2.
6.2.6 Do not accept without Technical POC concurrence. Allow 45 days for IC – Dimensional/QA Inspection for FAT requirement & 60 Days for Production requirement respectively.
6.2.7 Acceptance will come in the form of a communication from the Contracting Officer stating the items have passed inspection or have fail inspection and what are the known causes of the failure. A Contract Modification will be issued to proceed with the production lot. No work may begin on the production lot until acceptance of the First Article is complete.
CLAUSES INCORPORATED BY FULL TEXT
C-202-H001 ADDITIONAL DEFINITIONS–BASIC (NAVSEA) (OCT 2018)
(a) Department - means the Department of the Navy.
(b) Commander, Naval Sea Systems Command - means the Commander of the Naval Sea Systems Command of the Department of the Navy or his duly appointed successor.
(c) References to The Federal Acquisition Regulation (FAR) - All references to the FAR in this contract shall be deemed to also reference the appropriate sections of the Defense FAR Supplement (DFARS), unless clearly indicated otherwise.
(d) National Stock Numbers - Whenever the term Federal Item Identification Number and its acronym FIIN or the term Federal Stock Number and its acronym FSN appear in the contract, order or their cited specifications and standards, the terms and acronyms shall be interpreted as National Item Identification Number (NIIN) and National Stock Number (NSN) respectively which shall be defined as follows:
(1) National Item Identification Number (NIIN). The number assigned to each approved Item Identification under the Federal Cataloging Program. It consists of nine numeric characters, the first two of which are the National Codification Bureau (NCB) Code. The remaining positions consist of a seven digit non-significant number.
(2) National Stock Number (NSN). The National Stock Number (NSN) for an item of supply consists of the applicable four-position Federal Supply Class (FSC) plus the applicable nine-position NIIN assigned to the item of supply.
(End of text)
C-204-H001 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL CONTRACT FILES (NAVSEA)
(OCT 2018)
(a) NAVSEA may use a file room management support contractor, hereinafter referred to as "the support contractor", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as “protected information”. File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.
(b) The cognizant Contracting Officer will ensure that any NAVSEA contract under which these file room management services are acquired will contain a requirement that:
(1) The support contractor not disclose any information;
(2) Individual employees are to be instructed by the support contractor regarding the sensitivity of the official contract files;
(3) The support contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,
(4) In addition to any other rights the contractor may have, it is a third party beneficiary who has the right of direct action against the support contractor, or any person to whom the support contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.
(c) Execution of this contract by the contractor is considered consent to NAVSEA's permitting access to any information, irrespective of restrictive markings or the nature of the information submitted, by its file room management support contractor for the limited purpose of executing its file room support contract responsibilities.
(d) NAVSEA may, without further notice, enter into contracts with other contractors for these services. Contractors should enter into separate non-disclosure agreements with the file room contractor. Contact the Procuring Contracting Officer for contractor specifics. However, any such agreement will not be considered a prerequisite before information submitted is stored in the file room or otherwise encumber the government.
C-209-H002 FIRST ARTICLE (GOVERNMENT TESTING) (NAVSEA) (APR 2024)
(a) The First Article shall conform in every respect to the requirements of this contract. The First Article shall be manufactured with tools, materials, and methods which are the same as the tools, material and methods which will be used to manufacture the production units. All items delivered under the contract shall be manufactured under the same conditions and quality established by the First Article. Any changes to tools, material, or methods after the first article approval shall be documented by the contractor and approved by the Contracting Officer before they are used. The First Article shall not be delivered for first article approval tests as provided for in the clause of this contract entitled "First Article Approval--Government Testing" (FAR 52.209-4) until after the Contractor has fully tested it, at its expense, to determine compliance with said requirements.
(b) The Contractor shall make a record of all data obtained during such tests in a form similar to the guidance provided in MIL-HDBK-831A dated 25 June 2013.
(c) Pursuant to paragraph (e) of the clause entitled "First Article Approval--Government Testing", the First Article shall not be delivered as part of the production quantity.
(End of Text)
C-209-H003 WAIVER OF FIRST ARTICLE REQUIREMENTS (NAVSEA) (OCT 2018)
If the First Article is waived by the Government, the Contractor shall deliver supplies that are identical or substantially identical to those previously accepted by the Government under the following contract(s):
(Offeror to fill in contract number(s), as applicable. See Section M)
C-211-H016 SPECIFICATIONS AND STANDARDS (NAVSEA) (OCT 2018)
(a) Definitions.
(i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments).
(ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing.
(b) Requirements. All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only unless specifically identified below.
None
C-211-H017 UPDATING SPECIFICATIONS AND STANDARDS (NAVSEA) (DEC 2018)
The contractor may request that this contract be updated to include the current version of the applicable specification or standard if the update does not affect the form, fit or function of any deliverable item or increase the cost/price of the item to the Government. The contractor should submit update requests to the Procuring Contracting Officer with copies to the Administrative Contracting Officer and cognizant program office representative for approval. The contractor shall perform the contract in accordance with the existing specifications and standards until notified of approval/disapproval of its request to update by the Procuring Contracting Officer. Any approved alternate specifications or standards will be incorporated into the contract.
C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019)
Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.
C-215-H002 CONTRACTOR PROPOSAL (NAVSEA) (OCT 2018)
(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with the detailed obligations to which the Contractor committed itself in Proposal dated in response to Solicitation No. N0025324R0004.
(b) The technical volume(s) of the Contractor's proposal is(are) hereby incorporated by reference and made subject to the "Order of Precedence" (FAR 52.215-8) clause of this contract. Under the "Order of Precedence" clause, the technical volume(s) of the Contractor's proposal referenced herein is (are) hereby designated as item (f) of the clause, following "the specifications" in the order of precedence.
C-227-H006 DATA REQUIREMENTS (NAVSEA) (OCT 2018)
The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements List, DD Form 1423, Exhibit(s) A001, attached hereto.
C-242-H001 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (OCT 2018)
(a) As part of the negotiated fixed price or total estimated amount of this contract, both the Government and the Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $1,000 or less at the time of final contract closeout. The term "residual dollar amount" shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.
(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.
C-243-H003 CONFIGURATION MANAGEMENT (NAVSEA) (APR 2024)
(a) Baseline Definition - All contractual documentation in effect at the time of contract award shall constitute the Contract Baseline, which shall be considered incorporated in the baseline documentation.
(b) General Requirement –
(1) The Contractor shall maintain a Configuration Control Program to assure that all detail level work being performed under this contract is in compliance with appropriate baseline documentation. The Contractor shall prepare a Configuration Management Plan in accordance with the requirements of the contract. If required, the Contractor’s Configuration Management Plan shall be submitted through the appropriate Contract Data Requirements List (CDRL) for approval by the Government.
(2) Whenever a situation arises wherein the Contractor cannot comply with a baseline document, or whenever intent of such documentation is significantly changed by detail level documentation, the Contractor shall submit change documents to modify the baseline to resolve the conflict or to allow non-compliance. Whenever the cost of implementing a proposed change is less than the threshold requiring certified cost or pricing data, the Contractor shall provide such detail of related costs as to allow the Government to determine an equitable adjustment for the change document submission. Whenever the contract cost changes by an amount greater than the threshold requiring certified cost or pricing data, the Contractor shall complete such cost and pricing data as the Contracting Officer shall require detailing all related costs, and attach it to the change document. Requirements for cost and pricing data shall be determined by the gross amount of the change unless otherwise directed by the Contracting Officer. Change documentation shall be submitted to the Contracting Officer in accordance with the appropriate CDRL, and as described in paragraphs (c) through (f) below.
(c) Engineering Change Proposals (ECPs) - ECPs shall be prepared in accordance with the approved configuration management plan and the requirements of the contract. DI-SESS-80639E approved 11 February 2020, EIA-649-1A dated 10 August 2020, and MIL-HDBK-61B dated 7 April 2020 apply. An ECP shall be submitted whenever the detail level physical configuration, material quality, operational or functional performance of equipment or installed systems will not be in compliance with baseline design-related documents (Specifications, Contract Drawings, etc.), and a change to the baseline document is considered an appropriate means of resolving a design-related issue. The contractor shall develop documentation in sufficient detail to enable Government review and evaluation of the merits of the proposed change, including cost and scheduling impact, ship class impact if applicable, and consequences if disapproved. List all existing drawings and technical manuals impacted by the change, including a brief narrative explanation of needed changes to incorporate the ECP if approved. Provide weight and moment data incidental to the change, if applicable. The Contractor shall also prepare applicable baseline document insert sheets, with specific word changes or proposed rewrite, to facilitate baseline documentation changes.
(d) Non-Engineering Change Proposals (NECPs) – An NECP shall be submitted whenever necessary to document administrative, procedural, scheduling, or documentation changes that do not directly impact the physical configuration of the equipment. The NECP shall explain the nature of the problem, identify the applicable baseline document (i.e., Contract Data Requirement List (CDRL), Contract Clause, etc.) and provide a detailed explanation justifying the proposed course of action desired to resolve the problem. Insert sheets for applicable documents shall also be attached to facilitate change action in the event the NECP is approved.
(e) Deviations/Waivers - In the event that a baseline design-related document requirement cannot be met, and a change to the baseline document is considered inappropriate, the Contractor shall submit a Request for Variance.
The explanation of "Need for Deviation/Waiver" in the DD1694 shall provide detailed justification and consequences of approval, to include technical details explaining the degree of noncompliance and the effect on ship equipment or system operation.
(f) Equitable Adjustments for Change Documentation Preparations - For its effort expended in preparing ECPs, NECPs, and Deviations/Waivers, the Contractor shall receive equitable adjustment under the following circumstances:
(1) In the event the Contractor, on its own initiative, and without written request from the Contracting Officer, develops a change document that is later disapproved by the Government, the Contractor shall bear the cost of this effort.
(2) To avoid such loss, and at its option, the Contractor may submit a "preliminary" document that outlines intent, but without detailed supporting documentation and request the Contracting Officer's approval for expenditure of effort to complete the detailed supporting documentation. In the event the Contracting Officer denies this request, the Contractor will bear the cost of development of the "preliminary" document, and shall make no further effort to complete detailed supporting documentation.
(3) In the event the Contracting Officer approves the Contractor's request to develop supporting documentation, the Contractor shall be equitably compensated for its effort for both the "preliminary" and "final" documentation, regardless of whether or not the change document is later approved.
(4) In the event the Contracting Officer requests in writing that the Contractor develop change documentation, the effort expended by the Contractor in developing such documentation shall be subject to equitable adjustment, regardless of whether or not the change document is later approved.
(5) In the event the Contractor, on its own initiative, and without written request from the Government, develops a change document that is later approved by the Contracting Officer, the cost of developing such documentation shall be subject to equitable adjustment.
(6) Failure to agree to such equitable adjustment in contract price shall constitute a dispute, and shall be adjudicated in accordance with the requirements of the clause entitled "Disputes" (FAR 52.233-1).
(g) Any cost reduction proposal submitted pursuant to the clause entitled "Value Engineering" (FAR 52.248-1) shall be submitted as a Value Engineering Change Proposal (VECP). The Contractor shall follow the VECP preparation requirements of FAR 52.248-1(c) and any additional guidance provided by the Contracting Officer.
C-245-H005 INFORMATION AND DATA FURNISHED BY THE GOVERNMENT--ALTERNATE I
(NAVSEA) (MAY 2019)
(a) Contract Specifications, Drawings and Data. The Government will furnish, if not included as an attachment to the contract, any unique contract specifications or other design or alteration data cited or referenced in Section C.
(b) Government Furnished Information (GFI). GFI is defined as that information essential for the installation, test, operation, and interface support of all Government Furnished Material identified in an attachment in Section J. The Government shall furnish only the GFI identified in an attachment in Section J. The GFI furnished to the contractor need not be in any particular format. Further, the Government reserves the right to revise the listing of GFI as follows:
(1) The Contracting Officer may at any time by written order:
(i) delete, supersede, or revise, in whole or in part, data identified in an attachment in Section J; or
(ii) add items of data or information to the attachment identified in Section J; or
(iii) establish or revise due dates for items of data or information in the attachment identified in Section J.
(2) If any action taken by the Contracting Officer pursuant to subparagraph (1) immediately above causes an increase or decrease in the costs of, or the time required for, performance of any part of the work under this contract, the contractor may be entitled to an equitable adjustment in the contract amount and delivery schedule in accordance with the procedures provided for in the "CHANGES" clause of this contract.
(c) Except for the Government information and data specified by paragraphs (a) and (b) above, the Government will not be obligated to furnish the Contractor any specification, standard, drawing, technical documentation, or other publication, notwithstanding anything to the contrary in the contract specifications, the GFI identified in an attachment in Section J, the clause of this contract entitled "Government Property" (FAR 52.245-1) or "Government Property Installation Operation Services" (FAR 52.245-2), as applicable, or any other term or condition of this contract. Such referenced documentation may be obtained:
(1) From the ASSIST database via the internet at https://assist.dla.mil/online/start/; or
(2) By submitting a request to the
Department of Defense Single Stock Point (DoDSSP) Building 4, Section D
700 Robbins Avenue Philadelphia, Pennsylvania 19111-5094 Telephone (215) 697-6396 Facsimile (215) 697-9398.
Commercial specifications and standards, which may be referenced in the contract specification or any sub-tier specification or standard, are not available from Government sources and should be obtained from the publishers.
C-246-H002 GOVERNMENT USE OF CONTRACTOR’S INSPECTION EQUIPMENT (NAVSEA) (OCT 2018)
The contractor's gages, measuring, and testing devices shall be made available to the Government when required to determine contractor conformance with contract requirements. If conditions warrant, the contractor’s personnel shall be made available for operation of such devices and for verification of their accuracy and condition.
C-247-H001 PERMITS AND RESPONSIBILITIES (NAVSEA) (DEC 2018)
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits for complying with any applicable Federal, State, and Municipal laws, codes, and regulations for shipping and transportation including, but not limited to, any movement over public highways of overweight/over dimensional materials.
Section D - Packaging and Marking
D-211-H001 PACKAGING OF DATA (NAVSEA) (FEB 2022)
Data to be delivered by Integrated Digital Environment (IDE) or other electronic media shall be as specified in the contract.
All unclassified data to be shipped shall be prepared for shipment in accordance with best commercial practice.
Classified reports, data, and documentation shall be prepared for shipment in accordance with National Industrial Security Program Operating Manual (NISPOM), 32 CFR Part 117.
D-211-H005 IDENTIFICATION MARKING OF PARTS – ALTERNATE I (NAVSEA) (OCT 2018)
(a) For all parts not subject to the marking requirements in DFARS 252.211-7003 – Item Unique Identification and Valuation, marking shall be accomplished in accordance with the following:
(1) Parts not manufactured to Government specifications shall be marked in accordance with generally accepted commercial practice.
(2) Parts manufactured to Government specifications shall be marked as follows:
(i) Electrical Parts - that is, all parts in electrical equipment and electrical parts when used in equipment which are not electrical in nature (e.g., electric controls and motors in a hydraulic system) - shall be identified and marked in accordance with MIL-STD-1285D(2) dated 22 June 2018, or, where MIL-STD-1285D(2) does not cover such a part, in accordance with MIL-STD-130N(1) dated 16 November 2012. Requirements of MIL-STD-1686C dated 25 October 1995 for Electrostatic Discharge Control shall be addressed.
(ii) Electronic Parts - that is, all parts in electronic equipment and electronic parts when used in equipment which are not electronic in nature (e.g., electronic fuel controls in some engines) - shall be identified and marked in accordance with Requirement 67 of MIL-HDBK-454B dated 15 April 2007 with Notice 1 dated 12 December 2012. Requirements of MIL-STD-1686C for Electrostatic Discharge Control shall be addressed.
(iii) Parts other than electrical or electronic parts (as described above) shall be identified and marked in accordance with MIL-STD-130N(1).
(b) In cases where parts are so small as not to permit identification marking as provided above, such parts shall be appropriately coded so as to permit ready identification.
D-246-H003 WARRANTY NOTIFICATION FOR ITEM(S)—ALTERNATE I (NAVSEA) (APR 2024)
The Contractor shall apply a permanent warranty notification stamping or marking on each warranted deliverable end item and its container in accordance with MIL-STD-129R with Change 3 dated 25 February 2023 and MIL- STD-130N(1) dated 16 November 2012. The notification shall be placed in close proximity to other required stamping or markings so as to be easily readable by personnel. The warranty notification shall read:
THIS ITEM WARRANTED UNDER CONTRACT ________ TO CONFORM TO DESIGN,
MANUFACTURING, AND PERFORMANCE REQUIREMENTS AND BE FREE FROM DEFECTS IN
MATERIAL AND WORKMANSHIP FOR ________________ FROM DATE OF ACCEPTANCE. IF
ITEM IS DEFECTIVE NOTIFY _______________________ AND PCO.
D-247-H004 MARKING AND PACKING LIST(S) – BASIC (NAVSEA) (FEB 2022)
(a) Marking. Shipments, shipping containers and palletized unit loads shall be marked in accordance with ASTM- D-3951-18 approved 1 May 2018, Standard Practice for Commercial Packing.
(b) Packing List(s). A packing list (DD Form 250 Material Inspection and Receiving Report may be used) identifying the contents of each shipment, shipping container or palletized unit load shall be provided by the Contractor with each shipment. When a contract line item identified under a single stock number includes an assortment of related items such as kit or set components, detached parts or accessories, installation hardware or material, the packing list(s) shall identify the assorted items. Where assortment of related items is included in the shipping container, a packing list identifying the contents shall be furnished.
(c) Master Packing List. In addition to the requirements in paragraph (b) above, a master packing list shall be prepared where more than one shipment, shipping container or palletized unit load comprise the contract line item being shipped. The master packing list shall be attached to the number one container and so identified.
(d) Part Identification. All items within the kit, set, installation hardware or material shall be suitably segregated and identified within the unit pack(s) or shipping container by part number and/or national stock number.
D-247-H005 MARKING AND PACKING LIST(S) – ALTERNATE I (NAVSEA) (OCT 2018)
(a) Marking. Shipments, shipping containers and palletized unit loads shall be marked in accordance with MIL- STD-129R with Change 1 dated 24 May 2018.
(b) Packing List(s). A packing list (DD Form 250 Material Inspection and Receiving Report may be used) identifying the contents of each shipment, shipping container or palletized unit load shall be provided by the Contractor with each shipment in accordance with the above cited MIL-STD. When a contract line item identified under a single stock number includes an assortment of related items such as kit or set components, detached parts or accessories, installation hardware or material, the packing list(s) shall identify the assorted items.
Where DD Form 1348-1 or DD Form 1348-1A is applicable and an assortment of related items is included in the shipping container, a packing list identifying the contents shall be furnished.
(c) Master Packing List. In addition to the requirements in paragraph (b) above, a master packing list shall be prepared where more than one shipment, shipping container or palletized unit load comprise the contract line item being shipped. The master packing list shall be attached to the number one container and so identified.
(d) Part Identification. All items within the kit, set, installation hardware or material shall be suitably segregated and identified within the unit pack(s) or shipping container by part number and/or national stock number. Refer to the above cited MIL-STD for marking of assorted (related-unrelated) items.
D-247-W001 PROHIBITED PACKING MATERIALS (NAVSEA) (OCT 2018)
The use of asbestos, excelsior, newspaper or shredded paper (all types including waxed paper, computer paper and similar hygroscopic or non-neutral material) is prohibited. In addition, the use of yellow wrapping or packaging material is prohibited except where used for the containment of radioactive material. Loose fill polystyrene is prohibited for shipboard use.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government 1002 Destination Government Destination Government 1004 Destination Government Destination Government 2002 Destination Government Destination Government 2004 Destination Government Destination Government 3002 Destination Government Destination Government 3004 Destination Government Destination Government 4002 Destination Government Destination Government 4004 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-2 Inspection Of Supplies--Fixed Price AUG 1996 52.246-16 Responsibility For Supplies APR 1984
52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)
(a) The Contractor shall comply with the higher-level quality standard(s) listed below.
ISO 9001-2008
ANSI/ASQ Z1.4-2003
(b) The Contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph
(a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in--
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require--
(i) Control of such things as design, work operations, in-process control, testing, and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
(End of clause)
52.246-15 CERTIFICATE OF CONFORMANCE (APR 1984)
(a) When authorized in writing by the cognizant Contract Administration Office (CAO), the Contractor shall ship with a Certificate of Conformance any supplies for which the contract would otherwise require inspection at source.
In no case shall the Government's right to inspect supplies under the inspection provisions of this contract be prejudiced. Shipments of such supplies will not be made under this contract until use of the Certificate of Conformance has been authorized in writing by the CAO, or inspection and acceptance have occurred.
(b) The Contractor's signed certificate shall be attached to or included on the top copy of the inspection or receiving report distributed to the payment office or attached to the CAO copy when contract administration (Block 10 of the DD Form 250) is performed by the Defense Contract Administration Services. In addition, a copy of the signed certificate shall also be attached to or entered on copies of the inspection or receiving report accompanying the shipment.
(c) The Government has the right to reject defective supplies or services within a reasonable time after delivery by written notification to the Contractor. The Contractor shall in such event promptly replace, correct, or repair the rejected supplies or services at the Contractor's expense.
(d) The certificate shall read as follows:
"I certify that on ______ [insert date], the ____ [insert Contractor's name] furnished the supplies or services called for by Contract No._____ via ____ [Carrier] on ________[identify the bill of lading or shipping document] in accordance with all applicable requirements. I further certify that the supplies or services are of the quality specified and conform in all respects with the contract requirements, including specifications, drawings, preservation, packaging, packing, marking requirements, and physical item identification (part number), and are in the quantity shown on this or on the attached acceptance document."
Date of Execution: _______________________________
Signature: ______________________________________
Title: __________________________________________
E-246-H013 INSPECTION AND ACCEPTANCE OF DATA (NAVSEA) (OCT 2018)
Inspection and acceptance of all data shall be as specified on the attached Contract Data Requirements List(s), DD Form 1423.
E-246-H020 QUALITY MANAGEMENT SYSTEM REQUIREMENTS (NAVSEA) (OCT 2018)
The Contractor shall provide and maintain a quality management system that, as a minimum, adheres to the requirements of ASQ/ANSI/ISO 9001:2015 “Quality Management Systems – Requirements” and supplemental requirements imposed by this contract. The quality management system procedures, planning, and all other documentation and data that comprise the quality management system shall be made available to the Government for review. Existing quality documents that meet the requirements of this contract may continue to be used. The Government may perform any necessary inspections, verifications, and evaluations to ascertain conformance to requirements and the adequacy of the implementing procedures. The Contractor shall flow down such standards, as applicable, to lower-tier subcontractors under instances covered in FAR 52.246-11(b) or at the direction of the Contracting Officer. The Government reserves the right to disapprove the quality management system or portions thereof when it fails to meet the contractual requirements.
E-246-H022 INSPECTION AND TEST RECORDS (NAVSEA) (JAN 2019)
Inspection and test records shall, as a minimum, indicate the nature of the observations, number of observations made, and the number and type of deficiencies found. Data included in inspection and test records shall be complete and accurate, and shall be used for trend analysis and to assess corrective action and effectiveness. The data shall, on request, be identified and made available for on-site review by the Contracting Officer or designated Government representative.
E-246-W002 CERTIFICATE OF COMPLIANCE (NAVSEA) (OCT 2018)
(a) A certification of material shall be provided by the Contractor, one (1) copy to accompany the shipment (in the packing list envelope) and (l) copy mailed to arrive at time of receipt of the shipment. Mark all certificates to the attention of Code 00Q.
(b) The certificate shall state compliance of material with drawing specification and contract/order requirements. The certificate shall as a minimum state the company name, contract/order number, drawing or specification number, and date. The certificate shall state, above the signature of a legally authorized representative of the company, the following:
This certification concerns a matter within the jurisdiction of an agency of the United States and the making of a false, fictitious, or fraudulent certification may render the maker subject to prosecution under Title 18, United States Code, Section 1001.
(c) Failure to provide certification at the time of shipment may result in material being rejected and returned at the contractor's expense.
(d) The certificate shall read as follows:
I certify that on ______ [insert date], the ____ [insert Contractor’s name] furnished the supplies called for by the Order/Contract No._____ via ____ [Carrier] on ________ [identify the bill of lading or shipping document] in accordance with all applicable requirements. I further certify that the supplies or services are of the quality specified and conform in all respects with the contract requirements, including specifications, drawings, preservation, packaging, packing, marking requirements, and physical item identification (part number), and are in the quantity shown on this document.
Date of Execution: ________________________________ Signature: _______________________________________ Typed Name: ____________________________________ Title: ___________________________________________
E-246-W003 INSPECTION STANDARDS (NAVSEA) (OCT 2018)
Acceptance inspection of lots or batches will be in accordance with American National Standard ANSI/ASQ Z1.4-2003. Unless otherwise specified, attributes, which if defective would prohibit or reduce the usability of the product for its intended purpose, will be inspected at an acceptable quality level (AQL) of 1.0. Attributes which do not materially reduce the usability of the product will be inspected at an AQL of 2.5.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .