Definitization_of_Equitable_Adjustments.docx

DOCX document 26 KB Posted

Attached to
Bldg 514 Re-insulate process water piping
Solicitation number
N0025324Q0079
Issued by

About this file

This document is a report on the definitization of equitable adjustments under construction contracts. It provides data on the time taken to definitize change order proposals, with the majority being definitized within 180 days. Related to this, the document includes details on a pre-solicitation for a contract to re-insulate process water pipes in Building 514 at the Naval Undersea Warfare Center Division (NUWC) Keyport. The solicitation will be issued under FAR Part 13 and 36, with a firm-fixed price contract type and a small business set-aside. The solicitation is expected to be issued around September 10, 2024, with a 30-day response time, and the government estimate is less than $25,000. An organized site visit is anticipated to be included.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Definitization of Equitable Adjustments.

Selected Agency:
DEPT OF THE NAVY
Time to definitize after receipt of an adequate Change Order Definitization Proposal under Construction Contracts
Number of Change Order Proposals definitized under Construction Contracts
30 days or less
2
31 to 60 days
3
61 to 90 days
3
91 to 180 days
5
181 to 365 days
5
Greater than 365 days
2

After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance