This is a Statement of Work for USS MAKIN ISLAND (LHD-8) requiring inspection, repair or replacement, and installation of an AFT Winch Inverter #860-02024 on the Port Davit. The contractor must assess the material condition of the inverter, determine whether refurbishment or new replacement is necessary, and provide this assessment to the ship's force. If refurbishment is required, the contractor shall refurbish and reinstall the inverter on the Port Boat Davit boat deck, conduct operational testing (OPTEST) and quality assurance (QA) checks following installation, and troubleshoot as necessary until satisfactory OPTEST is accomplished.

The work location is USS MAKIN ISLAND LHD-8 at Naval Base San Diego, Pier 8, with a required delivery date of August 3, 2026. Materials must be shipped to BLDG 3581 MPC DLA DISTRIBUTION SAN DIEGO, CUMMINGS ROAD, SAN DIEGO CA 92136. The contractor shall be subject to monitoring and inspection while on the military installation but shall not be deemed a government employee or agent. The contractor is liable for failure to return the inverter. Work acceptance occurs once the ship's force confirms that OPTEST and QA points are satisfactory. Section 6.0 contains invoicing and payment policy information that is redacted in the provided document.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

USS MAKIN ISLAND (LHD-8)

Inspect & Repair or Replace AFT Winch Inverter #860-02024

Reference: AFT Winch Inverter #860-02024

Introduction: USS Makin Island (LHD-8) is requesting services to inspect, repair or replace and install Inverter on the Port Davit.

Background: USS MAKIN ISLAND requires a Port Boat Davit Inverter to be installed upon receipt with FTA. It will allow us to turn on the control panel and load center breaker that powers the davit. The box helps to launch our small boat onboard.

1.0 General Requirements for Inspection, repair and install:

1.1 Assess material condition of inverter that requires refurbishment and troubleshoot and assess inverter.

1.2 Contractor to provide information if refurbishment will be required or new replacement.

1.3 If refurbishment required, move on to 1.4

1.4 Contractor refurbish and reinstall inverter on Port Boat Davit boat deck for operational checks.

1.5 Contractor conduct OPTEST and QA following installation.

1.6 Contractor troubleshoot as necessary until SAT OPTEST of the inverter is accomplished.

2.0 Salvage Parts: Refurbish or provide new inverter if needed upon contractor assessment of turned in item.

3.0 PACKING/PICK-UP/Delivery:

Company will send the material to:

USS MAKIN ISLAND LHD8

BLDG 3581 MPC DLA DISTRIBUTION SAN DIEGO

CUMMINGS ROAD

SAN DIEGO CA. 92136

4.0 Inspection and Acceptance: Inverter will be assessed by contractor upon arrival and initial inspection. Ship’s force will accept work complete once OPTEST and QA points are SAT.