4.06 N0018925Q0222-0001.pdf
PDF 137 KB Posted
- Attached to
- Access Control/Intrusion Detection System
- Solicitation number
- N0018925Q0222
About this file
This document is a Standard Form 30 (SF-30) Amendment of Solicitation/Modification of Contract for a naval access control and intrusion detection system solicitation. The amendment changes the response deadline from 16-Apr-2025 12:00 PM to 18-Apr-2025 10:00 AM and provides detailed questions and answers about the project specifications.
Key technical details include connecting new Lenel controllers to an existing Lenel Enterprise system in Building 235, with controllers placed in rooms 108 and 112. The system will have motion detectors in Rooms 100, 108, and 112, with door contacts only on specific doors listed in the Minimum Requirements. The contractor will handle initial programming and train Navy personnel for system enrollment, with District Navy personnel providing enterprise-level support. The intrusion detection system (IDS) will be tied into the access control system and monitored by base dispatch.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1.04 Brand Name Justification_Redacted.pdf | ||
| Reference 1- Floor Plan.pdf | ||
| 4.02 N0018925Q0222.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N4365A25RC007AD
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide clarif ications to questions asked during the solicitation. No further questions w ill be recieved. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Apr-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0018925Q0222
X 9B. DATED (SEE ITEM 11)
08-Apr-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Apr-2025
CODE
NAVSUP FLC NORFOLK CONTRACTING
NORFOLK OFFICE
ATTN: J CLARK
1968 GILBRT STREET STE 600
NORFOLK VA 23511-3392
N00189 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N0018925Q0222
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 16-Apr-2025 12:00 PM to 18-Apr-2025 10:00 AM.
The following have been added by full text:
QUESTIONS & ANSWERS
1. Will the new Lenel controller connect back to an existing Lenel server or will a new standalone server need to be provided as part of this quote?
A: The Lenel controllers will be tied into the existing Lenel Enterprise. The connection from building to dispatch will be an access point installed in the Building 235 server room.
2. If connecting to an existing server, are there enough licenses to accommodate the new 5 doors? Could you provide the Dongle ID for this system?
A: There are enough licenses to accommodate the new five (5) doors. Dongle ID is accounted for in the existing enterprise scheme.
3. Please clarify that you would like one Lenel controller set up in room 112 controlling doors 1,3,4, and 5 with a second control panel in room 108.
A: A controller will be in room 108. Room 112 will have 2 controllers to break out the communications room separately from Room 100, and Room 107. An additional controller will be in Room 108.
4. Will Lenel programming be provided by the contractor or site?
A: The contractor will set up the initial programming and train local Navy personnel for enrollment. District Navy personnel will also be supporting on an enterprise level.
5. Will the IDS devices tie into Lenel or will this be a separate alarm system?
A: Tied together by area and monitored by base dispatch.
6. For the IDS, are we to assume that all rooms will receive motion detectors and that all exterior doors to include roll up doors will receive door contacts?
A: No, motion detectors will be in Rooms 100, 108, and 112. Only doors listed in the Minimum Requirements will receive door contacts.
7. Are the ceilings hard lid or drop ceilings in the corridors and office areas?
A: Drop ceiling
8. How high are the ceilings in the garage area?
A: Not Applicable.
(End of Summary of Changes)