This document contains a draft Statement of Work (SOW) and Sources Sought/Request for Information notice for the acquisition and installation of a C-40A Load Master Trainer (LMT) unit. The Department of the Navy Naval Supply Systems Command Fleet Logistics Center Norfolk is seeking information from contractors to procure and install a C-40A LMT device at the Air Logistics Training Center in Fort Worth, Texas to replace an obsolete C-9B LMT. Responses to the Sources Sought notice are due by December 11, 2019 and should include business information, an estimated installation schedule, availability on contract vehicles, capability statement, confirmation of power supply compatibility, and any suggestions to improve the draft SOW. The SOW requires the C-40A LMT unit to replicate specific components and dimensions of the C-40A aircraft, support cargo loading training, and integrate with the existing facility power supply.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F I N A L – 26 NOV 2019 V1

Statement of Work (SOW) for

Procurement of a C-40A Loadmaster Trainer (LMT)

1.0 INTRODUCTION: Commander, Naval Air Force Reserve (CNAFR) has a requirement to procure a C-40A LMT to be located at Air Logistics Training Center (ALTC), Fort Worth, TX in support of Commander, Fleet Logistics Support Wing (CFLSW). This action is for the acquisition of a C-40A LMT which should be secured in place by the contractor at the ALTC in Fort Worth, TX.

The contractor is also responsible for any additional equipment needed to secure the C-40 LMT in-place and to identify any facility or parking apron modifications required for installation of the C-

40A LMT.

2.0 BACKGROUND: This device is required to replace the C-9B LMT with a fleet-representative C-40A LMT to effectively train and equip C-40A Loadmasters. The Navy Reserve divested the last C-9B aircraft from its inventory on 30 June 2014 and the Marine Corps Reserve divested the last two C-9Bs on 1 June 2017, thus rendering the C-9B LMT obsolete. The training of Navy Reserve Loadmasters is essential to ensure safe and efficient cargo loading operations in support of global Navy fleet logistics missions. C-40A Loadmasters are responsible for safe on- and off-loading of all palletized cargo on the C-40A aircraft as well as direction of loading vehicles (e.g.

K-Loaders and forklifts) in close proximity to the aircraft fuselage. The addition of a properly configured C-40A LMT device will allow C-40A Loadmasters to practice cargo loading evolutions (in a controlled training environment) on a fleet-representative C-40A LMT prior to executing actual missions.

3.0 SCOPE: The scope of this CNAFR effort is to acquire and have installed, a C-40A LMT device, to include the following (at a minimum): the portion of the fuselage from the aft most wing section to the forward galley (including forward entry door), complete Combi configuration cargo compartment and main cargo door that replicates the USN C-40A (Boeing 737-700C) aircraft, to include overhead storage bins, and port wing section to include port engine nacelle. The existing facility will accommodate a C-40A LMT device with dimensions of approximately 60 feet in length by 47 feet in width by 29 feet in height. Contractors should plan to participate in a site visit in order to take exact measurements of a C-40A aircraft, survey the facility in which it will be installed and identify any additional equipment and/or modifications needed for the installation of the C-40 LMT device at ALTC. The exact date, time and place of the site visit will be discuss in Section 6.0 below.

3.1 NAICS Code SIC Code Federal Product/Service Code Object Class Code

333318 3728 6930 26.0

4.0 APPLICABLE DIRECTIVES: The directives listed below are applied and reviewed as part of the support for this requirement.

Document Type Number/Version Title Date

NATOPS NAVAIR A1-

C40AAA-

NFM000

C-40A NATOPS

CFLSWINST 3500.7 series Enlisted Aircrew Phase Training and Qualification

03 Mar 15

DOD MANUAL DOD 4160.21M Defense Material Disposal Manual Aug 1997

4.1 ACRONYMS AND ABBREVIATIONS:

ALTC Air Logistics Training Center CFLSW Commander, Fleet Logistics Support Wing CNAFR Commander, Naval Air Force Reserve CNRF Commander, Navy Reserve Force IT Information Technology JRB Joint Reserve Base JPAS Joint Personnel Adjudication System LM Loadmaster LMT Loadmaster Trainer TBD To Be Determined TRS Technical Requirements Statement

5.0 PERFORMANCE REQUIREMENTS/TASKINGS: This SOW shall be used to acquire a C-40A LMT device and to identify any additional equipment, facility or parking apron modifications required for installation of the C-40A LMT. The C-40A LMT shall replicate the confined space of the C-40A in a Combi configuration, providing the capability to instruct Navy C-40A Loadmasters on proper load planning, cargo loading, and cargo pallet securing techniques.

5.1 The C-40A LMT: The C-40A LMT shall include the following:

5.1.1 The contractor shall provide and install a C-40A LMT Device, to include the following (at a minimum): the portion of the fuselage from the aft most wing section to the forward galley (including forward entry door), complete Combi configuration cargo compartment and main cargo door replicating the USN C-40A (Boeing 737-700C) aircraft to include overhead storage bins, and port wing section to include port engine nacelle. The device shall include the forward passenger entry door, a secondary exit, and a fully-operational cargo door that replicates the main cargo door operation of the C-40A including operating positions (CLOSED, CANOPY, FULL OPEN). Design shall include the following C-40A features: forward and aft cargo bulkheads with doors; flooring/ball-decking; all latches, restraints and other fixed equipment used for attaching and restraining cargo/pallets; cargo safety net/rigging; and all panels/switches/placards/lights/indicators required for main cargo door operation as found in the C-40A aircraft.

5.1.1.1 The C-40A LMT shall replicate the interior dimensions of the C-40A Combi configuration cargo compartment, including operable stowage bins.

5.1.1.2 Interior Layout:

5.1.1.3 The contractor shall mount the C-40A LMT on a steel base frame structure (which the contractor would provide) or landing gear that will support the fuselage section at actual aircraft height during loading and unloading cargo evolutions.

5.1.1.4 The C-40A LMT shall include lighting which enables safe loading and unloading evolutions. Lighting is not necessarily required to match aircraft configuration, but must provide sufficient lighting to carry out training. Control of these lights will be via non-aircraft control switches located near the exit(s).

5.1.1.5 The C-40A LMT shall include interior and exterior fuselage station markings of (at a minimum) medium level of fidelity in size and color.

5.1.1.6 The C-40A LMT shall have forward and in-cabin smoke/fire barriers that replicate the C-40A in Combi configuration. A representative light-weight durable barrier and simplified mounting system is acceptable.

5.1.1.7 The C-40A LMT shall have the forward passenger entry door and service door of similar design to C-40A (Boeing 737-700C) aircraft. Identical C-40A airstairs are not required; however, some form of stair system shall be incorporated to allow entrance to the device without impeding cargo evolutions. The stairs shall fall within the dimensions called out in Section 3.0. Some form of safety barrier/netting/restraint at the forward passenger entry door opening is required and shall be of design to not interfere with cargo loading/unloading evolutions.

5.1.1.8 The C-40A LMT shall have a primary and secondary means of entering/exiting the training device. At a minimum, there shall be a means of entering/exiting forward of the Combi cargo section and another aft of the Combi cargo section. This can either be via forward passenger and service entry doors with fixed or operable airstairs, or some other system (i.e. overwing or aft entry/service door, either option should include stairs), but stairs shall be of design to not impede cargo loading/unloading evolutions. With exception of the main cargo door, any door openings which include retractable/removable stairs shall have some form of restraint system incorporated for personnel fall prevention. All stairs shall have safety handrails.

5.1.1.9 The LMT units shall be compatible with a 240V/200Amp/60Hz power supply. The lighting, cargo door controls and operation, stairs and any other electronics or electronically controlled components of the LMT shall be compatible with the current power supply (240V/200Amp/60Hz) available in the ALTC hanger.

5.2 Cargo Handling: The C-40A LMT shall have a fully-operational main cargo door of identical specifications to the USN C-40A (Boeing 737-700C) aircraft. Switch location and latching mechanism shall replicate the design and operation of the C-40A (Boeing 737-700C) aircraft. The main cargo door shall replicate main cargo door operation of the C-40A including operating positions (CLOSED, CANOPY, FULL OPEN). Door shall be designed to operate via electrical power located in the fuselage cargo area.

5.2.1 The C-40A LMT interior floor structure and interior cargo hold area and interior cargo handling system shall replicate the interior cargo compartment of the C-40A (Boeing 737- 700C) aircraft and able to accept and support three (3) standard U.S. Air Force 463L pallets with dimensions of 2.25 inches high, 88 inches long and 108 inches wide (empty pallet weight 290 pounds). The LMT device shall be capable of supporting a total of 15,000 lbs. of cargo.

5.2.2 The C-40A LMT shall incorporate all systems associated with cargo loading and unloading, to include a full complement of interior cargo floor elements, latches, anchor points and restraints and an actual C-40A Combi main deck cargo net. Nonskid material, cargo locks, ball decking and rollers shall be installed on the floor identical to the C-40A aircraft in Combi configuration.

5.3 The following additional information is provided/requested:

5.3.1 The government is not anticipating any modifications to the facility or parking apron for the installation of the C-40 LMT unit, however, if the contractor discovers that a modification to the facility or parking apron is needed (during the site visit), the contractor should include the list of modifications to the facility or parking apron in their proposal. Hangar power is currently available as detailed in Section 5.1.1.4. Air-conditioning is not currently available and not required.

5.3.2 The contractor is responsible for the safe storage and oversight of any material or equipment that may be needed during the installation process at the ALTC.

6.0 Site Visit:

6.1 A site visit will take place from TBD. The site visit will allow perspective contractors to take measurements inside a C-40A aircraft so the exact measurements can be replicated on the C-40A LMT unit. Site visits should be scheduled at least 2 week prior to the start of the site visit window mentioned above by contacting TBD for direction/instructions about base admittance and safety protocol.

7.0 PERIOD OF PERFORMANCE:

TBD

8.0 PLACE OF PERFORMANCE:

8.1 Commander, Fleet Logistics Support Wing (CFLSW), Air Logistics Training Center (ALTC), NAS JRB Fort Worth Fort Worth, TX 76127-1251

9.0 POINTS OF CONTACT:

9.1 CDR Heath Leggett

CNAFR VR Jet Program Manager Comm: 757-322-2675

DSN: 262-2675

Email heath.leggett@navy.mil

9.2 CDR Chad Martin

ALTC Officer-In-Charge Comm: 817-782-5229

DSN: 739-5229

Email: chad.c.martin@navy.mil

9.3 Jacob Segal

Contract Specialist – NAVSUP FLCN Comm: 215-697-9813 Email: Jacob.Segal@navy.mil

File details come from the government source that posted it. Updated .