N0018919Q0314_SOW_N0018919Q0314_Amend_01.docx
DOCX document 17 KB Posted
- Attached to
- Habitability, USS Whidbey Island, Desks
- Solicitation number
- N0018919Q0314
About this file
N0018919Q0314_SOW_N0018919Q0314_Amend_01.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N0018919Q0314_PRICING_WORKSHEET_N0018919Q0314_Amend_01.xlsx | XLSX spreadsheet | |
| PRICING_WORKSHEET_N0018919Q0314.xlsx | XLSX spreadsheet | |
| N0018919Q0314_Combined_Synopsis_Solicitation.docx | DOCX document | |
| SOW_N0018919Q0314.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
HABITABILITY UPGRADES ABOARD
USS WHIDBEY ISLAND
N0018919Q0314 Amendment 01
The Medical and Dental offices aboard the USS Whidbey Island require habitability upgrades as outlined in the Statement of Work. This requirement is to be practical and workable, and to enhance the spaces used by the ship’s personnel. Workmanship will support fundamental elements of standard quality and design and will not be guided by personal opinion or taste, but rather practical and reasonable standards.
1.0 General Description of Work: Provide repair and rehabilitation of the ship’s spaces as identified below. The contractor is responsible for the removal, installation, and disposition of residual removed materials, except as identified below in the SOW.
1.1 All furnishings must comply with:
MIL-STD-1623E, Fire Performance Requirements and Approved Specifications for Interior Finish Materials and Furnishings, Naval Shipboard Use MIL-PRF-32038A, Shipboard Furniture, fixtures, Fittings, and Accessories NAVSEA STANDARD ITEM 009-26 Ch. 3.General Criteria; Accomplish
2.0 Contractor shall affirm, in writing, that the work performed and items supplied comply with MIL-STD-1623E, MIL-PRF-32038A, and NAVSEA STANDARD ITEM 009-26 Ch. 3.
3.0 Contractor shall provide an installation schedule, by space, to Contracting Officer and ship’s Technical Point of Contact (TPOC).
3.1 Contractor shall plan and present a written project schedule to ship’s TPOC and the Contracting Officer within 3 days of contract award. Contractor shall include the name and cell phone number of the Contractor’s on-site project lead.
3.2 Contractor shall report any Government-induced delays to the TPOC and the Contracting Officer immediately.
3.3 Contractor shall report any Contractor-induced delays to the TPOC and the Contracting Officer immediately.
3.4 Contractor is responsible for accurate measurement for all items. Government will not reimburse Contractor for misfit items.
3.5 Contractor shall supply and install furnishings in ship’s spaces as identified in paragraph 4 and associated subparagraphs below.
3.6 Contractor shall clean up work–in-progress spaces at completion of day’s work. Leave in-progress spaces in general safe and orderly condition before departing work space.
3.7 Contractor shall provide ship’s TPOC with a space-specific punch list, and resolution per space upon completion installation of each space.
4.0 Requirements by Specific Spaces:
4.1 Location 02-53-4-Q:
4.1.1 Remove existing desks 1 3 ea.
4.1.2 Provide and install
a) 1 ea. Desk, Flat Top, Single Pedestal L. H. (39 3/4x30x30)
SFC NO: B-5A-2 (OR EQUAL)
HULL TYPE DRAW NO: 805-2224391
4.2 Location 02-52-2-L:
4.2.1 Remove existing desk 1 ea.
4.2.2 Provide and install
a) 1 ea. Desk, Flat Top, Single Pedestal, L. H. (39 3/4x30x30)
SFC NO: B-5A-2 (OR EQUAL)
HULL TYPE DRAW NO: 805-2224391
4.2.3 Remove stainless steel cabinet. Stage for disposition by ship’s force.
4.2.4 Remove stainless steel bookcase. Stage for disposition by ship’s force.
4.3 ISSUE ROOM 02-43-2-L
| 4.3.1 Remove existing desks 3 1 ea. | |
| 4.3.2 | Provide and install |
a) 3 ea. Desk, Flat Top, Single Pedestal, R. H. (39 3/4x30x30)
SFC NO: B-5A-2 (OR EQUAL)
HULL TYPE DRAW NO: 805-2224391
5.0 Place of Performance:
Naval Station Norfolk Pier 11 Norfolk VA 23511
6.0 Scheduling and Coordination: Contractor shall comply with a work plan and schedule (as determined and agreed to by the contractor and the ship’s Supply Officer, suppo@lsd41.navy.mil, 619-829-8087. Working hours are 0700-1800 M-F.
7.0 Period of Performance: 1 Ju1 - 30 Aug 2019 Contract award date through 16 August 2019
8.0 Cardholder’s Information:
NAME: LS2 Nicole Nagtalon, EMAIL: Nicole.nagtalon@lsd41.navy.mil
PHONE: (510) 239-6776
9.0 No tag-out or plumbing disconnection is required by contractor.