STATEMENT OF WORK

View the file

Other files

File Type Posted
SF181.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREVENTIVE MAINTENANCE & TRAINING/ SYSTEM REPAIR

STATEMENT OF WORK

1.0 BACKGROUND

The Naval Surface Warfare Center, Dahlgren Division (NSWDDD), has a requirement to procure repair and preventive maintenance (Health Checks) and training on in-house of TEAM manufactured Subsidiary Shock Test System (SSTS) equipment located on base. It is critical that the system be maintained, and personnel educated on proper operation/sustainment to prevent program stoppage.

2.0 APPLICABLE DOCUMENTS

Original Equipment Manufacturer (OEM) Specifications & Maintenance Guide/Manual

3.0 REQUIREMENTS

3.1 The contractor shall provide preventive maintenance and training on the following systems, manufactured by TEAM Corporation:

NAME
MODEL (if known)
SERIAL NUM. (if known)
Tandem 1
2205A Servo
Job# 7960
Tandem 2
2205A Servo
Job# 7960

5DOF system

Job# 10348

V-SSTS

Job# 11023

H-SSTS

Job# 12247

HPS-265
HPS-265
SN 589
HPS-265
HPS-265
SN 750

3.2 The contractor shall provide preventive maintenance to include on-site inspection, and adjustment of each system identified in section 3.1, located at NSWCDD along with all parts required for maintenance.

3.2.1 The contractor shall schedule the inspections in advance with NSWCDD personnel not later than five (5) calendar days after receipt of the order (ARO) as identified below.

3.2.1.1 The inspections shall be accomplished in accordance with the manufacturer’s recommended preventative maintenance schedules and procedures.

3.2.2 The contractor shall perform the following and provide the following hardware/repair parts at the time of service:

3.2.2.1 Perform vision inspection of cables, hoses, manifolds

3.2.2.2 Inspect Slip Table Assemblies

3.2.2.3 Inspect Couplings

3.2.2.4 Collect oil samples for analysis

3.2.2.5 Check accumulator pressure and recharge as necessary to proper levels

3.2.2.6 Check airbag pressures and recharge as necessary to proper levels

3.2.2.7 Verify function of valve drivers

3.2.2.8 Verify function of 1510-D HPS Remote Controller

3.2.2.9 Perform health checks on actuators and verify status

3.3 The contractor shall provide training for up to twenty (20) NSWCDD personnel on site based on vendor’s standard maintenance procedures.

3.3.1 The training shall include verbal instruction on proper maintenance, repair, troubleshooting, QC analyzer operation, and general standard operating procedures.

NOTE: It is estimated that twenty (20) hours of training will occur during the contractor’s visit.

3.4 The contractor shall provide repair/installation of new valve drivers for the SSTS on-site at NSWC Dahlgren.

3.4.1 The contractor shall schedule the repair in advance with NSWCDD personnel not later than 15 calendar days ARO with the technical point of contact as identified in Section 4.0 below.

3.4.2 The contractor shall setup, tune new valve drivers and run health checks on SSTS system.

4.0 TRAVEL

The contractor will be required to travel in performance of this contract. The number of trips and types of personnel traveling shall be limited to the minimum required to accomplish work requirements and shall be coordinated with the technical point of contact. All travel shall be conducted in accordance with the Federal Travel Regulations (FTR). The following travel is anticipated: Two (2) personnel for seven (7) days to Dahlgren, VA during the period of performance and a second trip with two (2) personnel for five (5) days.