Questions_and_Answers.pdf

PDF 91 KB Posted

Attached to
InTop/EMC Testbed Maintenance and Configuration Federal contract opportunity
Solicitation number
N00173-18-R-GF02
Issued by
Department of the Navy Secretary of the Navy Office of Naval Research

About this file

Please review Attachment 9, Questions and Answers which is incorporated as part of Amendment 1

View the file

Other files for this federal contract opportunity

Other files attached to InTop/EMC Testbed Maintenance and Configuration, newest first.
File Type Posted
New_Award_Report.doc DOC document
N00173-18-R-GF02_U00002.pdf PDF
N00173-18-R-GF02_U00001.pdf PDF
N00173-18-R-GF02.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 9

Questions and Answers

N00173‐18‐R‐GF02

1) Question: Option 2‐ Year 3 should read as 01/01/2020 to 12/31/2020?

Answer: Yes. Please see the attached amendment which corrects the typo.

2) Question: Can section H‐6 ONR 5252.216‐9706‐ Level of Effort (Dec 88) be deleted?

Answer: Yes. Please see the attached amendment.

3) Question: H‐3 (d) the following are identified as key personnel: Will be listed at time of award.

What resumes should be included?

Answer: Key Personnel have been added. Please see the attached amendment.

4) Question: In the proposal should the Configuration/Data Manager, Fabricator, Foreman, Machinist, Department Manager and Program/Project Manager provide their resumes along with the key personnel who will be fulfilling the requirements?

Answer: Please see the attached amendment.

5) FAR Clause 52.204‐10 – Reporting Executive Compensation and First‐Tier Subcontract Awards

(Oct 2015) ‐ Question: should the FAR Clause be (Oct 2016)?

Answer: Yes. This has been corrected in the attached amendment.

6) Question: L‐16, Volume III, (3) states Cost Proposal shall be submitted in Microsoft Excel format using Attachment L‐3, Cost Summary Format. In Section J‐ List of Attachments, Attachment 3 is Small Business Participation Plan Template. Where is the Microsoft Excel format using Attachment L‐3, Cost Summary Format located?

Answer: Please see the attached amendment.

7) Question: L‐16, Volume III, (d) states Offeror shall complete and include as part of its proposal the pricing table found in Attachment 6 to reflect the Offeror ’s ceiling rates for each year of the contract. In Section J‐ List of Attachments, Attachment 6 is DD Form 254, Contract Security Classification Specification. Where is Attachment 6 (ceiling rates) located?

Answer: Please see the attached amendment

8) Question: Will mileage reimbursement for key personnel coming from the Hanover, Maryland office to the site be reimbursed?

Answer: Please refer to Section 2.6 of the Statement of Work.