About this file

This is a Standard Form 30 Amendment of Solicitation/Modification of Contract for the Naval Surface Warfare Center, Carderock Division. The amendment revises the Performance Work Statement (PWS) for the procurement of 46 custom concrete jersey barriers to be delivered to the Acoustic Research Detachment in Bayview, Idaho. The barriers are 12.5 feet long, 36 inches high, and will have custom galvanized steel pipes attached to increase their height to 42 inches. The contractor must attach the pipes using galvanized steel standard pipe brackets, ensuring firm attachment and compliance with OSHA standards.

The project requires delivery to the Remote Storage Facility within 12 weeks of award, with work to be completed during normal working hours (6:00 AM to 6:00 PM, Monday through Friday). The government will offload the barriers from the flatbed trailer using a forklift and store them on-site. Strict security requirements are in place, including the need for contractor personnel to obtain base access passes, display identification badges, and adhere to specific site access and conduct guidelines. The solicitation amendment is dated 18 Sep 2025 and is associated with solicitation number N0016725Q1214.

View the file

Other files for this federal contract opportunity

Other files attached to Jersey Barriers, newest first.
File Type Posted
Attachment 0001.pdf PDF
Attachment 0002 - Jersey Barrier Base Dimensions.pdf PDF
N0016725Q1214 CSS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

Created On:

18 Sep 2025, 18:25 PM Greenwich Mean Time

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Continuation of Description

Miscellaneous text in this section has been modified to:

Performance Work Statement (PWS)

Bayview Seawall Jersey Barriers

1.0 DESCRIPTION OF SERVICES/INTRODUCTION: Acoustic Research Detachment, Carderock Div. requires delivery of 46, 12.5 foot long, custom jersey barriers to delineate between parking areas and the seawall.

2.0 BACKGROUND: The NSWCCD Acoustic Research Detachment (ARD) is located on Lake Pend Oreille, which is Idaho's largest, deepest (1,150 feet), and quietest body of water providing an ideal environment for acoustic testing without the attendant problems and costs of open ocean operations. Along the border of the base and Lake Pend Oreille, there are various parking spots that require a protective barrier to prevent motorists from driving over the seawall and into the lake. These parking spots span from the west edge of Warf 48 following the contour of the seawall until it hits the property line (Attachment 0001).

3.0 OBJECTIVE:

3.1 The contractor shall deliver forty-six (46), twelve and a half feet (12.5') long, 36-inch-high concrete jersey barriers with custom twelve and a half foot (12.5') long galvanized steel pipe attached to the top of all 46 barriers.

3.2 The contractor shall attach the galvanized pipe to the top of the jersey barrier using a galvanized steel standard pipe bracket.

3.2.1 Piping and bracket should increase the height of the barriers to forty-two inches (42") tall.

3.2.2 Attached pipe and bracket should be firmly attached with no movement of any kind.

3.2.3 The mounted piping and bracket will meet OSHA 1910.29 (b)(1) & (2).

3.3 The contractor shall deliver the complete (3.3.1) jersey barriers to the Remote Storage Facility (RSF) or "Bone Yard".

3.3.1 Bayview Address: 33964 N Main Bayview, ID 83803

3.3.2 The RSF entrance is approximated 1/2 mile south of the main base entrance on the right-hand side of the road if you are traveling north.

3.3.3 Delivery will be scheduled and coordinated with onsite POC: TBD

3.3.3.1 TBD

3.3.4 Completed barriers shall have little to no chipping, flaking, or cracking. All attachments will be firmly fixed to the concrete with no movement of any kind. Barrier and piping should resemble Attachment 0003.

3.3.5 The Government shall offload the materials off the flatbed trailer with a forklift and store the materials in a storage area on-site. The Contractor shall not offload or install these materials.

4.0 Work Schedule: All work will be completed during regular working hours, and delivery will take place no later than 12 weeks from award, if weather permits. If local weather conditions restrict the delivery and installation of the barriers, contact the Procuring Contracting Officer (PCO) and the Technical Point of Contact (TPOC).

4.1 All work planned for normal working hours shall be performed between 6:00 AM and 6:00PM, Monday through Friday, except

(a) federal holidays, or (b) other days so designated by the Commanding Officer. Any work other than these hours or weekend work will be permitted only when advanced written approval has been issued by the Government.

5.0 SPECIAL QUALIFICATIONS:

5.1 N/A

6.0 APPLICABLE DOCUMENTS

6.1 [List all documents reference under section 3.0 in chart below]

N0016725Q12140001

Document Type No./Version Title Date

Base Map (Parking)

N/A Attachment 0001 07/18/2025

Jersey Barrier N/A Attachment 0002 07/18/2025

7.0 GOVERNMENT FURNISHED EQUIPMENT/PROPERTY/INFORMATION: N/A

8.0 DELIVERABLES: N/A

9.0 SECURITY REQUIREMENTS: The site access is controlled by the onsite Naval Surface Warfare Center Security Requirements. Contractor personnel working at NSWC must be fully identified and approved. Contractors will complete Department of the Navy Local Population ID Card /Base Access Pass Registration Form SECNAV 5512/1 for all employees, staff, sub-Contractor's personnel, etc., who will require access. Forms must be approved by the local Department of Defense Security Office prior to access.

Contract personnel are expected to perform work during normal NSWC duty hours. If work must be performed otherwise, permission must be obtained from the Security Office through the TPOC. Contractor personnel must confine themselves to the work sites specified in their contract.

Visiting other areas is prohibited. Alcoholic beverages, weapons, cameras, sound recorders, proscribed drugs and explosives are prohibited on NSWC property. Use of Government property without prior written approval of the Contracting Officer is prohibited.

NSWC personnel will arrange for special contractor parking if required. Contractor personnel shall not park in numbered spaces, areas reserved for carpools, or other prohibited areas. Posted speed limits and traffic restrictions must be observed at all times. Accidents or problems of a security /safety nature must be reported to the onsite personnel immediately.

Contractor personnel working on site for less than five days may be required to log in and out at the Visitor's Center each day and will not be issued an Extended Entry Contractors Badge.

Pursuant to federal regulations, all personnel and vehicles on NSWC property are subject to search by authorized personnel at any time. All contractor's personnel are required to display the NSWC issued identification badge on their person at all times while present at the laboratory. Access to NSWC property will not be allowed without this identification badge. The badge is to be displayed on the person's outer clothing, above the waist and in full view. Identification badges and vehicle passes issued to contractor personnel remain the property of the U.S. Government and must be surrendered upon completion of the contractor at the termination of individual employment, and when requested by the Government.

A list of all personnel working under this contract should be turned in immediately after award in order to allow sufficient time to process security information

N0016725Q12140001

IDCode: J
Page: 1
Pages: 3
AmendNo: 0001
EffDate: 18 Sep 2025
ReqNo: See Continuation Sheet
ProjNo:
IssCode: N00167
AdmCode:
IssuedBy: NSWC CARDEROCK

CARDEROCK DIVISION, 9500 MACARTHUR BOULEVARD

BETHESDA, MD 20817-5700

UNITED STATES

ARNEL NGO, Email: arnel.a.ngo.civ@us.navy.mil Telephone: 7574782013 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: N0016725Q1214
SolDate: 17 Sep 2025
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: See Continuation
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: Amendment is issued to revise the Performance Work Statement (PWS). the following is added to the PWS:

3.3.5The Government shall offload the materials off the flatbed trailer with a forklift and store the materials in a storage area on-site. The Contractor shall not offload or install these materials.

ContNameTitle:
CoNameTitle:
ContDate:
CODate:

File details come from the government source that posted it. Updated .