RFI Questions CLB_MMH.pdf
PDF 282 KB Posted
- Attached to
- Columbia Multi-Material Hardware Manufacturing
- Solicitation number
- N00167-22-RFPREQ-CD-81-0008
About this file
This document is a Request for Information from the Naval Surface Warfare Center, Carderock Division regarding Columbia Multi-Material Hardware Manufacturing. The RFI seeks to conduct market research and solicit industry comments and feedback to determine potential small and large businesses capable of providing multi-material hardware manufacturing support services for the CLB Class propulsor effort. Responses are requested to include organization details, capabilities to meet the draft Statement of Work, ability to comply with security requirements, production bottlenecks, recommended clarifications to material and process specifications, estimated qualification and first article testing timelines, and contract vehicle recommendations assuming a 33% rework rate. The anticipated award date for a follow-on C-type contract is August 2023.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FINAL RFI Questions CLB_MMH.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information: COLUMBIA MULTI-MATERIAL HARDWARE MANUFACTURING
This is not a Request for Proposal and award of a contract will not be made as a result of this Request for Information
(RFI). The Advanced Propulsor Management Office (Code 808) in the Naval Architecture and Engineering
Department (Department 80) of the Naval Surface Warfare Center, Carderock Division (NSWCCD) requests assistance from industry for conducting market research to produce multi-material hardware for the CLB Class propulsor manufacturing effort. The multi-material hardware produced shall interface appropriately with the parent components of the CLB propulsor. The detailed capabilities are classified at the CONFIDENTIAL LEVEL. Both the
Geometric Dimension &Tolerance (GD&T) and performance specifications are defined in NAVSEA drawings. The contractor shall meet both specifications in order for the propulsor system to meet its performance requirements.
The purpose of this RFI is to conduct market research by soliciting industry comments and feedback. Market research will determine potential socio-economic small and large businesses interested in, and capable of, providing the support services identified herein. This posting is issued in accordance with the requirements of Federal
Acquisition Regulation (FAR) Part 10.
NSWCCD intends to fulfill this requirement via completion type under C-type contract with an anticipated award date of August 2023.
Responses should include the following:
1. Cover letter, not to exceed one (1) page that includes:
(a) Organization name, CAGE Code, and address
(b) Point of contact name and contact information
(c) Size and type of organization, including if applicable U.S. small business or other status
(d) Brief statement of interest that indicates the organization’s interest in applying as a prime or subcontractor.
2. Interested parties shall provide a response (not to exceed 25 pages) to the following questions:
(a) Describe capabilities to meeting all aspects of the draft Statement of Work including any necessary equipment.
(b) Addresses any barriers to satisfying the draft SOW and provide recommendations such as modifications that would be required to be able to satisfy meeting the draft SOW.
(c) Confirm understanding of the security requirement and the DX rating, and state willingness to comply upon award.
(d) Identify bottlenecks in production (e.g. personnel or equipment) that would impact your ability to manufacture 2 or 3 shipsets simultaneously List any recommended clarifications needed to the “material formulation specification” and the “manufacturing and material process specification”, refer to SOW references.
(e) State whether your firm is able to meet or is unable to meet the requirements in the “material formulation specification” and the “manufacturing and material process specification”, refer to SOW references.
(f) Estimate total time required to qualify to produce each type of hardware listed and pass first article testing as defined in the SOW references.
(g) Provide recommendations on the contract vehicle, contract type or/and CLIN structure assuming a rework rate of 33% for all hardware.
(h) Provide an estimate of time required for the qualification process.