Item

Contract Section/ Page #
Title/Topic
Question
Government Answer
1.
Section B, Page 3
Travel
Are travel days included in the “trips?” As an example, Item No 0001 identifies ‘nine trips for four days each’. Do these four days include time for travel? Or are the four days actual work days at NSWCCD and the offeror needs to bid additional time for travel?
The intent was for supporting a full work- week (5 days/4 nights) with travel on Monday and Friday. Additional travel time may be necessary based on point of origin.
2.
Section B, Page 5
Weekend Work
Is weekend work expected? As an example, Item No 0006 identifies “one trip for twelve days;” is the 12-day trip to include 2 days of overtime for working through the weekend?
No, weekend work was not expected. Twelve days assumes two (2) five-day work- weeks with one weekend in place.
3.
Section B,

Pages 3 - 8

Days Onsite
Item Nos 0001 through 0011. For estimating purposes, are days onsite to be considered 8-hour days billed at a straight-time rate?
For estimating purposes 8-hour workdays (M-F) should be assumed: 0800-1630 (includes ½ hour for lunch).
4.
Section C, Statement of Work
Component Drawings
Upon award, will specific component drawing be provided to contractor to establish NDT qualification data?
Yes, drawings will be provided to the contractor at the time of award.
5.
Section C, Statement of Work
Components
Upon award, will specific components made from the same material, heat treatment, and surface finish/coatings be provided to contractor to establish NDT qualification data?
Yes, components made from the same material and heat treatment will be available to the contractor at the time of award. The mock-up component with surface finish/coatings will be provided at a later date and will be GFE.
6.
Page 24, Factor 2
Past Performance
Is there specific Past Performance information the Government is expecting for evaluation, or will an evaluation of CPARs be performed by the Government?
The Government is particularly interested in past work experiences that are similar in scope and complexity to the work required. The Government may also use CPARs as part of the evaluation process.