N0016425PLXXX SOW BEAVER AEROSPACE 07JUL2026.pdf
PDF 147 KB Posted
- Attached to
- ENGINEERING SERVICES
- Solicitation number
- N0016426Q0175
About this file
This is a Statement of Work (SOW) for engineering analysis and evaluation services supporting the Turret Deployment Drive System (TDDS) modifications to accommodate new Navy Tactical Airborne Sensor (TAS) loads. The contract is identified as N0016426PLXXX and was prepared by Naval Surface Warfare Center, Crane Division on May 21, 2026.
The primary objective is to conduct ongoing engineering analysis evaluating the current P-8A TDDS against new estimated Navy TAS loads and assess the feasibility of utilizing existing P-8 and MQ-25 actuator/ball screw systems as potential solutions. The contractor, Beaver Aerospace & Defense, Inc., must identify necessary design modifications, performance considerations, and define the scope and materials required for follow-on testing. Key tasks include data acquisition and review of dynamic operating loads, life requirements, stroke length, speed, power, environmental requirements, positioning accuracy, interface requirements, materials, and weight specifications. The contractor must perform plug-and-play feasibility evaluation of existing systems, analyze fatigue life impacts, assess required modifications, and evaluate electrical performance risks and brushless motor transition feasibility while maintaining compatibility with existing electrical interfaces. Additional tasks include identifying performance limitations, documenting major design modifications with deviations from current designs, and defining components and test equipment for future physical testing phases.
The estimated performance period is nine months from the signed agreement date, targeting August 1, 2026 through April 30, 2027, with monthly invoicing. Primary deliverables include monthly PowerPoint status updates at Technical Interchange Meetings, a CDRL A001 Technical Report documenting analyses and findings, participation in Navy/MTech design reviews (notionally PDR November 21, 2025 and CDR July 9, 2026), and a single government review comment clarification meeting. The SOW explicitly excludes detailed design work, specification updates, physical testing or prototyping, hardware procurement, detailed design calculations, extensive finite element analysis, and comprehensive modeling. Government rights in technical data developed under this contract are governed by DFAR 252.227-7013.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - N0016426Q0175.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N0016426PLXXX
STATEMENT OF WORK (SOW)
for
Engineering Analysis and Evaluation Services in support of
Turret Deployment Drive System (TDDS)
Changes to Accommodate New Navy Tactical Airborne Sensor (TAS) Loads
21 May 2026
Revision -
Prepared by:
Naval Surface Warfare Center, Crane Division Emerging Airborne EO Sensors Branch
300 Highway 361 Crane, IN 47522-5001
DISTRIBUTION STATEMENT D. “Distribution authorized to DoD and U.S. DoD Contractors only (Critical Technology) as 22 November 2022. Other requests for this document shall be referred to:
COMMANDER , BLDG 3291 CODE JXQL, NAVAL SURFACE WARFARE CENTER, 300 HIGHWAY
361, CRANE, IN 47522-5001
1. Objective:
• To build upon efforts previously conducted under order N00164PL001 and N0016425FW526 between Naval Surface Warfare Center, Crane Division , hereafter NSWC Crane, and Beaver Aerospace & Defense, Inc, hereafter Beaver Aero, that allowed each company to gain an understanding of the goals, data requirements and limitations.
• To conduct an on-going engineering analysis to evaluate the current P-8A Turret Deployment Drive System (TDDS) against the new estimated Navy Tactical Airborne Sensor (TAS) loads, as outlined in the Naval Surface Warfare Center, Crane Division Statement of Work and referencing documents Heavy Turret Deployment Unit (TDU)
• System Design Specification (SDS) (TAS-PLN-SPEC-0013) and SD-EN-004 Equipment Specification (Rev I), and to assess the feasibility of utilizing existing P-8 and MQ- 25 actuator/ball screw systems as potential solutions or starting points for the TDDS needed to support the heavier TAS turrets.
• To identify the necessary design modifications and performance considerations based on the available data and the anticipated operational TAS loads, and to define the scope and material required for a follow-on testing contract.
• To work with the US Navy and their current Turret Deployment Unit (TDU) system contractor, Magee Technologies LLC, hereafter MTech, to support overall system design.
2. Tasks:
Engineering Evaluation:
• Data Acquisition and Review:
o Data Provision: NSWC Crane will provide all available data, clearly indicating any preliminary estimates. Beaver Aerospace & Defense, Inc. will then analyze this data and provide results based on the data provided. Any limitations to the data will be noted in the results. Data may be revised and re-evaluated as needed during this effort.
o Obtain and review the following critical data from NSWC Crane/MTech:
Dynamic operating loads/Load profiles (time-based curves).
System Load Profile: Time-based curve of overall TAS system load.
Ball Screw Loads: Operating load for each ball screw (BS1, BS2, BS3), accounting for unequal aerodynamic loads.
Life requirements (hours, cycles).
Stroke length.
Speed requirements.
Power requirements.
Environmental requirements.
Positioning accuracy and repeatability.
Interface Requirements.
Material and Finish requirements.
Weight requirements.
Identification of specific performance requirements and sections within SCD 8090200490 and details within SD-EN-004 that are critical for evaluation against the new TAS loads and anticipated changes.
o Analyze the provided data to understand the operational demands of the TDDS (TAS) system.
Plug-and-Play Feasibility Evaluation:
o Based on the acquired operational data, evaluate the feasibility of using the existing P-8 and MQ-25 ball screw assemblies, motors, PCBs, and gearing for the TDDS
(TAS).
o Analyze the impact of operational loads on component fatigue life and performance.
o Assess the required modifications to existing systems for integration into the TDDS (TAS) application.
o Evaluate the electrical performance risks based on the MQ-25 electrical concessions.
o Evaluate the specific feasibility and design impacts of transitioning to a brushless motor and controller, with the critical constraint that the new solution must maintain compatibility with existing electrical interfaces and connector pin requirements.
Performance and Design Considerations:
o Identify potential performance limitations and risks associated with using existing systems for the TDDS (TAS).
o Document the necessary major design modifications, highlighting any deviations from the current P-8A TDDS design as documented in SCD 8090200490 and SD-EN-004.
Note: This analysis will identify expected major design changes, but due to the limited scope, it will not identify all design changes, SCD 8090200490 updates, or SD-EN-004 updates that would be necessary for a full design cycle.
o Document all assumptions that were made, including assumptions regarding the specific SCD requirements or SD-EN-004 details being evaluated.
Procurement Planning and Test Definition:
o Based on this analysis, Beaver Aero shall define the components, materials, Other Direct Costs (ODCs), and test equipment required for the subsequent physical testing phase. This includes defining the materials and developing a scope for future contract modifications or separate contract vehicle to fund these activities.
Reporting and Communication:
o Participate in monthly "Technical Interchange Meetings (TIMs)" to provide current status, updates and address questions. Beaver Aero shall provide current status via PowerPoint slides or other similar media.
o Support Navy/MTech TAS TDU Design Reviews as necessary to provide TDDS specific information and answer questions. Notional scheduled TAS TDU Design Reviews are: PDR (11/21/2025), CDR (7/9/2026), but are subject to change.
o Prepare a written TDDS Analyses Technical Report (CDRL A001). The report shall document previous order N0016425FW526 and this efforts analyses, methodology, findings, feasibility assessment, risks/mitigations, design considerations and recommendations related to meeting the new estimated TAS loads, with reference to the evaluated SCD 8090200490 requirements or SD- EN-004 details.
o Government Review Comment Clarification Meeting: Following the Government's review of the Draft Technical Report, Beaver Aerospace & Defense, Inc. will participate in a single (1) joint meeting with the Navy to discuss and clarify any comments received. This meeting will ensure mutual understanding of the required revisions prior to final edits and final report submission.
3. Timeline:
• The estimated overall timeline for completing this scope of work is nine (9) months from the date of the signed agreement, with the target period of performance being August 1, 2026, through April 30, 2027. Beaver Aero shall provide on-going support and shall invoice the Government for each month’s support as delineated in the contract.
4. Deliverables:
• Participation and informal status updates of design analyses in PowerPoint presentations at each monthly TIM (MS Teams meetings).
• CDRL A001 Technical Report – TDDS Analyses Technical Report in accordance with this SOW and CDRL A001.
• Participation in a single joint Navy/MTech/Beaver Aero Review and Comment
Clarification Meeting.
• Revisions to the CDRL A001 Technical Report based on Government review, as clarified and agreed upon during the Government Review Comment Clarification Meeting, will be limited to corrections of factual errors, clarifications of existing content based on the scope of work, and completion of any work identified as incomplete within this defined scope. Any requests for analysis or content outside this defined scope will be considered a change in scope and subject to separate agreement and potential modification to the contract.
5. Exclusions:
This scope of work is contingent upon the timely receipt of the requested operational data and clarification on the specific requirements within SCD 8090200490 or details within SD-EN-004 to be evaluated.
• This scope does not include detailed design work for a new TDDS (TAS) system.
• This scope does not include an update to SCD 8090200490 or SD-EN-004.
• This scope does not include any physical testing or prototyping.
• This scope does not include the procurement of any hardware, materials, or Other Direct
Costs (ODCs). All material and ODC costs must be negotiated and funded separately via a contract modification or new contract vehicle.
• This scope does not include creating any new specifications beyond the initial assessment.
• This scope does not include detailed design calculations, extensive finite element analysis (FEA), or comprehensive modeling of the TDDS (TAS) system.
6. Assumptions:
• Beaver Aero will receive sufficient requested data in a timely and accurate manner to facilitate their analyses and development.
• NSWC Crane will provide clear identification of the specific performance requirements and sections within SCD 8090200490 (Rev E) and SD-EN-004 (Rev I) that are most relevant to the on-going analysis and the anticipated changes for the TAS integration.
• Mutual agreement on the level of detail, requirements, assumptions, and expected output will be reached between Beaver Aerospace & Defense, Inc. and Naval Surface Warfare Center, Crane Division during the Kickoff Meeting allowing for a clear path forward upon commencement of the effort.
• Level of Detail: This initial feasibility assessment and the resulting Technical Report will provide a high-level overview of the potential for utilizing existing P-8 and MQ-25 systems for the TDDS (TAS) application based on the provided TAS load data and referenced specifications. Supporting calculations will be included to justify the findings and identify potential areas of concern. This scope does not include detailed design calculations, extensive finite element analysis (FEA), or comprehensive modeling of the TDDS (TAS) system.
• Resource Allocation: The FP-LOE is based on a defined and finite scope of work that corresponds to the internal labor hour ceiling. Beaver Aero reserves the right to prioritize and manage resource allocation to ensure the total contract NTE is not exceeded prior to the contract end date.
• Report Acceptance: The Technical Report Initial Load Analysis deliverable will be considered acceptable upon Naval Surface Warfare Center, Crane Division's confirmation that the report addresses the tasks and provides the information as defined within this Scope of Work.
7. Government Rights:
Prior Government Rights: Technical data that will be delivered, furnished, or otherwise provided to the Government under this contract, in which the Government has previously obtained rights shall be delivered, furnished, or provided with the preexisting rights.