This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a high-voltage diode procurement. The solicitation (N0016425Q06400) is issued by the Naval Surface Warfare Center Crane Division and has extended the response due date to 28 August 2025. The procurement will use a Low Price Technically Acceptable (LPTA) evaluation method with four technical acceptance factors: technical approach, delivery, past performance, and constructive acceptance.

Key requirements include providing diodes with a repetitive reverse voltage of 3000 VDC, experience in encapsulating/potting high-voltage diodes for airborne applications at 50,000 feet, and ability to integrate diodes in small footprint assemblies (2 cubic inches or smaller). Vendors must be small businesses with current SAM.gov accounts, and will be evaluated based on their Supplier Performance Risk System (SPRS) ratings. The contract will be a firm fixed-price award using Simplified Acquisition Procedures, with pricing evaluated including all option quantities. Responsive quotes must include a signed SF18, delivery schedule, complete pricing for all Contract Line Item Numbers (CLINs), and a completed Technical Evaluation Matrix.

View the file

Other files

File Type Posted
25Q0640_SOL.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section A - Solicitation/Contract Form

The following changes have been made:

INFORMATION FROM TO

Response Due Date 30 May 2025 28 Aug 2025

N0016425Q06400001

1.

1.

Section M - Evaluation Factors for Award

Miscellaneous text in this section has been modified to:

THE FOLLOWING BEST VALUE DETERMINATION IAW FAR 13.106 WILL BE USED TO EVALUATE THE QUOTES

USING LOW PRICE TECHNICALLY ACCEPTABLE EVALUATION CRITERIA:

QUOTERS - PLEASE SEE THE FOLLOWING FOR EVALUATION CRITERIA

The following Best Value listed will be used to the Quotes using Evaluation Factors evaluate Low Price Technically Acceptable Criteria - GO - NO GO Criteria:

TECHNICAL APPROACH

DELIVERY

PAST PERFORMANCE

CONSTRUCTIVE ACCEPTANCE

Technical Acceptance Factor #1: Technical Approach

Quoters will need to provide product literature or a capabilities document which outlines how the vendor will provide the diode IAW the Drawing and SOW. The product literature or capabilities document will be evaluated by the Requiring Technical Authority (RTA) to ensure technical acceptance.

Provide examples or details on your experience with successfully encapsulating/potting high voltage (repetitive reverse voltage of 3000 VDC or greater) diodes for use in airborne applications of 50,000 feet minimum

Provide examples or details on your experience successfully integrating high voltage (repetitive reverse voltage of 3000 VDC or greater) diodes in small footprint assemblies (2 cubic inch or smaller)

Note - The assembly volume is based on the maximum dimensions provided in the specification drawing of this solicitation.

Technical Acceptance Factor #2: Delivery

Quoters will need to fill out the clause 52.211-8 for evaluation by the Government. All vendors who can meet the Governments required delivery date will be deemed technically acceptable. The Government will not review individual quotes for delivery only clause 52.211-8.

Technical Acceptance Factor #3: Past Performance

Past performance will be evaluated based on the Supplier Performance Risk System (SPRS).

In accordance with (IAW) provision 252.204-7024(e) the Government will review the Quoter's Summary Report" for Product Service Code (PSC) information. IAW provision 252.204-7024(c)(3), the Government will also utilize the "Suppliers Risk

Report" will be utilized to assess the risk of unsuccessful performance and supply chain risk. Below is a snapshot of the supplier color legend listed in the report in each report. In addition, IAW provision 252.204-7024(c)(1) and (2) the Government will review the Quoter's "Item/Risk Report" to determine whether the procurement represents high performance risk to the Government as well as to ensure the quoted pricing is consistent with historical prices paid for the products or otherwise creates a risk for the Government.

SUPPLIER COLOR LEGEND

Blue Top 5%

Purple Next 10%

Green Next 70%

Yellow Next 10%

Red Lowest 5%

Summary Report:

The Government will review the summary report score for the PSC(s) associated with this effort only.

Supplier Risk Report:

The Government will review the supplier risk score as well as the suspected counterfeit area.

Item/Price Risk Report:

The Government will review the item/price risk score utilizing the various search functions.

Past performance will be based on GO / NO GO basis. An unacceptable (NO GO) equals a yellow or red listing in the SPRS system for the PSC(s) in the summary report as well as the supplier risk score/suspected counterfeit area and the item/price risk report. A quoter with no past performance (scores in either summary or supplier risk report) will be evaluated as neutral.

Technical Acceptance Factor #4: Constructive Acceptance

Acceptance period is three (3) months from once the diodes (FAT and Production) are delivered as noted in clause G-232.

W0001.

SEE TECHNICAL ACCEPTANCE EVALUATION MATRIX BELOW:

Quoter's by checking a "GO" column you are certifying that your company meets technical acceptance evaluation factors. Matrix must be filled out for consideration of award.

TECHNICAL ACCEPTANCE EVALUATION FACTOR

G O

NO

GO

CONFORMANCE TO DRAWING AND SOW

By checking GO in this box you are certifying you can provide diode required that meets all aspects outlined in the drawing and SOW.

CONFORMANCE TO DELIVERY

By checking GO in this box you are certifying that your company meets the Governments required delivery schedule outline in 52.211-8.

CONFORMANCE TO PAST PERFORMANCE

By checking GO in this box you are certifying that your company will not be either yellow or red in the SPRS Summary or Supplier Risk Report.

CONFORMANCE TO CONSTRUCTIVE ACCPETANCE

By checking GO in this box you are certifying that your company agrees to the constructive acceptance of 3 months for FAT and Production.

A RESPONSIVE QUOTE CONSISTS OF THE FOLLOWING

- Signed SF18 (ALL PAGES RETURNED, 1 to 49)

- 52.211-8 Time of Delivery schedule filled out with Quoters delivery dates - You will only be considered responsive to this section if you fill in the clause 52.211-8 and return with the solicitation pages noted above.

- All pricing must be entered on each CLIN of the SF18 - You will only be considered responsive to this section if you fill in the CLINs and return with the solicitation pages noted above. Note, for CLINs 0004 and 0005 ALL OPTION QTY breaks need to be filled out.

- Technical Evaluation Matrix completely filled out

- Must be a small business.

- Must have a current SAM.gov account and not currently excluded.

The Government will review in three (3) phases:

- Responsiveness, see A below

- Technical Acceptance, see B below

- Pricing, see C below

A. RESPONSIVENESS

If anything is not provided or in the manner addressed above (under a responsive quote consists of the following) you will not be considered responsive and your quote be evaluated for technical acceptance. Quoters are able to provide will not quotes on their own format and other documents they wish however, be in conjunction with the documents listed it must above (under a responsive quote consists of the following) and in the manner the Government has made clear or it will be considered non responsive. In order to move phase B responsiveness to the solicitation must be adhered to.

B. TECHNICAL ACCEPTANCE

To be considered technically acceptable all quoters must meet the above criteria, see technical acceptance factors one (1) to four (4). Once quoters have been deemed technically acceptable, .then and only then will price be evaluated

C. PRICING

Upon certifying responsiveness and technical acceptance, award will be made to the lowest priced vendor. Pricing will be evaluated for aggregate total for CLINs to include options. For pricing evaluation purposes the Government will include the highest possible QTY's listed in option CLINs 0002 and 0003 as well as include every option QTY break for CLINs 0004 and 0005 in the total. This is only for evaluation only.

Quotes that are non-compliant with any material requirement of this solicitation may be rejected without further consideration for award. This will be a firm fixed price contract and will be awarded utilizing Simplified Acquisition Procedures.

(End of provision)

IDCode: J
Page: 1
Pages: 7
AmendNo: 0001
EffDate: 18 Aug 2025
ReqNo: See Continuation Sheet
ProjNo:
IssCode: N00164
AdmCode:
IssuedBy: NSWC CRANE

WARFARE CENTER, 300 HIGHWAY 361

CRANE, IN 47522-5001

UNITED STATES

TRACY FIELDS, Email: tracy.k.fields.civ@us.navy.mil Telephone: 812-381-7235 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: N0016425Q0640
SolDate: 15 May 2025
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: This solicitation is being amended to add further specificity for technical acceptance factor one (technical approach) as the Government was unable to discern technical acceptability based on the quotes received. In addition, this extend the closing date 8/28/25.
ContNameTitle:
CoNameTitle: Andrew Ficklin
ContDate:
CODate: 18 Aug 2025