23RGP78_SOL.pdf

PDF 950 KB Posted

Attached to
AN/SQS-53C STAVE FRAMES
Solicitation number
N0016423RGP78
Issued by

About this file

This solicitation requests proposals for the fabrication, assembly, inspection, testing and delivery of AN/SQS-53C Stave Frames for the Department of the Navy Naval Sea Systems Command. Key requirements include the delivery of first article sets, ship sets consisting of seventy-two stave frames, and associated technical data. Offerors must demonstrate the ability to fabricate stave frames in accordance with engineering drawings from materials including plastic compounds and epoxy coatings. The solicitation establishes contract line items for the first article, ship sets for both U.S. and foreign military sales customers, and data deliverables. Pricing terms include fixed-price contract line items established on a yearly basis. Delivery of the first articles is required within 120 days of award with subsequent ship sets due 120 days thereafter.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 04:00 PM local time 30 Oct 2023

X

A X B X C X D

EX

X

G F 50 - 62

63 - 73 H 74 - 79 benjamin.k.harrison2.civ@us.navy.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

DO-A3 1 79

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N00164 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 1 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and

See Section L conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

BENJAMIN K HARRISON 812-854-6691

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 5

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

6 - 17 18 - 20

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

21 - 22 23 - 24

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 25 - 33 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

34 - 48

PART II - CONTRACT CLAUSES

NAVAL SURFACE WARFARE CENTER CRANE DIV

B. HARRISON (812-854-6691)

BLDG 3373

300 HWY 361

CRANE IN 47522-5001

812-854-6691

812-854-6691FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

25 Sep 2023

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N0016423RGP78

Section B - Supplies or Services and Prices

IDC CONSTRAINTS

CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE

The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

AMOUNT

N/A $200,000.00 N/A *

*Maximum Amount to be completed at award

ITEM NO SUPPLIES/SERVICES MAX QTY U/I UNIT PRICE MAX AMOUNT

0001 First Article - AN/SQS-53C Stave

Frame

12 Each

First Article consists of six (6) each of 03538-7321115G1 Stave Frames and 03538-7324381G1 Stave Frames, in accordance with (IAW) the Statement of Work (SOW) and applicable drawings. First Articles will not become part of the production quantity.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

PSC: 1905

FOB: Destination

FFP

0002 AN/SQS-53C Stave Frame Ship

Set - U.S.

UNDEFINED Ship Set

United States (U.S) - AN/SQS-53C Stave Frame Ship Set consists of seventy-two (72) Stave Frames, consisting of fourty-four (44) 03538-7321115G1 Stave Frames and twenty-eight (28) 03538-7324381G1 Stave Frames, in accordance with (IAW) the Statement of Work (SOW) and applicable drawings.

Minimum and Maximum are a combination of CLINs 0002 and 0003.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification

0003 AN/SQS-53C Stave Frame Ship

Set - FMS

UNDEFINED Ship Set

Foreign Military Sales (FMS) - AN/SQS-53C Stave Frame Ship Set consists of seventy-two (72) Stave Frames, consisting of fourty-four (44) 03538-7321115G1 Stave Frames and twenty-eight (28) 03538-7324381G1 Stave Frames, in accordance with (IAW) the Statement of Work (SOW) and applicable drawings.

Minimum and Maximum are a combination of CLINs 0002 and 0003.

NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification

ITEM

NO SUPPLIES/SERVICES QTY U/I UNIT PRICE AMOUNT

0004 Data

Technical Data Requirements for CLINs 0001-0003 in accordance with (IAW) Contract Data Requirements List (CDRLs) CDRLs A001-A004, applicable Data Item Descriptions (DIDs), and the Statement of Work (SOW).

Not Seperately Priced.

Lot

0005 Contract Ceiling

1 Each

This CLIN is only utilized to populate the contract ceiling amount. No Delivery Orders (DOs) will be placed against this CLIN.

CLIN 0002/0003 PRICING MATRIX

CLIN 0002/0003 Year 1 Year 2 Year 3 Year 4 Year 5

To be completed by Offeror

Year 1 Time Period: Date of Award to 12 Months After Award* Year 2 Time Period: 12 Months After Award to 24 Months After Award* Year 3 Time Period: 24 Months After Award to 36 Months After Award* Year 4 Time Period: 36 Months After Award to 48 Months After Award*

Year 5 Time Period: 48 Months After Award to 60 Months After Award* *Actual dates will included in the award document.

Section C - Descriptions and Specifications

STATEMENT OF WORK (SOW)

Statement of Work (SOW) for the

Fabrication, Assembly, Inspection, Test and Delivery of AN/SQS-53C Stave Frames

22 May 2023

1.0 SCOPE

This Statement of Work (SOW) covers the requirements and effort involved for the fabrication, inspection, test and delivery of AN/SQS-53C Stave Frames. This includes First Article Set and AN/SQS-53C Stave Frame Shipsets and Hardware. A First Article set of stave frames shall consist of six (6) each 03538-7321115G1 and 03538-7324381G1 stave frames. A shipset consists of a total of seventy-two (72) stave frames consisting of forty-four (44) 03538- 7321115G1 stave frames and twenty-eight (28) 03538-7324381G1 stave frames.

1.1 Background

The Sonar Set AN/SQS-53C is a computer-controlled surface-ship sonar that has both active and passive operating capabilities providing precise information for Anti-Submarine Warfare (ASW) weapons control and guidance. The AN/SQS-53C is designed to perform direct path ASW search, detection, localization, and tracking from a hull mounted transducer array. Stave Frames are mounted in a cylindrical array in the Sonar Dome located in the Bow of Arleigh Burke Class Destroyer Ships and are populated with eight TR-343 Sonar Transducers per Stave Frame.

2.0 APPLICABLE DOCUMENTS

The following documents of the latest issue as of the date of contract award, form a part of the SOW, to the extent specified within. In the event of conflict between the documents referenced and the contents of the SOW, the referenced documents shall be considered a superseding requirement.

Drawings and Specifications Title 03538-7321115G1 Stave 03538-7324381G1 Stave 53711-7102804 Plastic, Compound 03538-7099277 Anti-seize, Compound 53711-7103202 Coating, Epoxy 53711-7521292 Coating, Epoxy, Application Specification 53711-7521293 Coating, Epoxy, Test Specification 03538-7230954 Bolt, Machine 53711-7090449 Nut, Plain, Hexagon, Jam 03538-7819524 Shim PL 73211GG1 Stave Parts List PL 7844799G2 Stave Material Parts List PL 7324381G1 Stave Parts List MIL-STD-2219 Fusion Welding for Aerospace Application

ASTM-D2794

Deformation, Rapid, Resistance of Organic Coatings to the Effects of (impact)

MS21045 Nut, Self-Locking Hexagon

3.0 REQUIREMENTS

3.1 General Requirements

The Contractor shall provide the necessary equipment, facilities, resources, management, and labor to fabricate, assemble, inspect, test, and deliver AN/SQS-53C Stave Frames and Hardware in accordance with (IAW) the documents listed in Paragraph 2.0 herein.

3.2 Fabrication

The Contractor shall fabricate, assemble, and inspect the AN/SQS-53C Stave Frames in accordance to the associated engineering drawings and any approved changes thereto. Hardware shall be provided in accordance to the associated drawings.

3.3 Testing

The Contractor shall inspect stave frames in accordance with (IAW) the applicable documents listed in Paragraph

2.0 herein. The Government may monitor any and all inspections including first article testing performed by the Contractor.

3.3.1 First Article Testing

The Contractor shall perform first article testing as specified herein. In lieu of performing first article testing, the Contractor may submit proof of previous successful first article testing and/or qualification letter confirming successful first article testing of item(s) and the following conditions are accurate:

a. Twenty-Four (24) months or less since the manufacturer has produced the items

b. The manufacturing line used to produce the item has not been significantly altered and/or relocated

c. The manufacturer will be using the same material suppliers

d. There has been no significant changes to assembly procedures

e. There has been no significant changes to key personnel

Determination will be made by the Naval Surface Warfare Center, Crane Division (NSWC-CR) as the AN-SQS-53C

ISEA.

3.3.1.1 First Article Test Plan

The Contractor shall submit a First Article Qualification Test Plan and Procedures to the Government for review and approval. No changes will be made to any of the testing and evaluation processes, procedures or plans without the approval of the Government. (CDRL A001)

3.3.1.2 First Article Mechanical Inspection

Inspection of all dimensions shall be performed by the Contractor. Prior to coating, weld inspection shall be performed per MIL-STD-2219 for a Class C weld.

3.3.1.3 First Article Coating Inspection

Inspection of the coating shall be performed on all first article items per test requirements as specified in 53711- 7521293. Adhesion, Cure and Holiday tests shall be performed on all twelve (12) first article units. Impact and Salt Spray tests shall be performed on twelve (12) test panels per ASTM-D2794, which are required to be coated identically and concurrently with the stave frames.

3.3.1.4 First Article Inspection Report

Upon completion of First Article testing, the Contractor shall submit a First Article Test/Inspection Report. (CDRL A002)

3.3.2 Production Inspection/Testing

Stave frames shall be shall be inspected for defects, manufacturing flaws, and compliance with applicable drawings and specifications, including dimensions. Hardware shall be inspected to verify compliance with applicable drawings and specifications. An inspection report documenting specific inspections and results is required. The Contractor shall submit an acceptance test report documenting specific tests and results (CDRL A003).

3.3.2.1 Final Inspection

The Contractor shall conduct final inspection to verify compliance to applicable drawings and specifications. Final inspection shall be witnessed by DCMA. Final inspection data shall be recorded and submitted to the Government on the Certification Data Report (CDRL A004).

3.4 Packaging

Completed stave frames shall be packaged six (6) frames per crate in accordance with (IAW) industry standards and shall be adequately protected from damage during shipment and storage. Hardware shall be bagged and boxed with part numbers identified on the box.

4.0 TECHNICAL DATA DELIVERABLES

Data Deliverables shall be submitted to the government in accordance with (IAW) Contract Data Requirements List

(CDRL).

CDRL: A001

DID Number: DI-NDTI-81307A DID Title: First Article Qualification Test Plan and Procedures – Test Plan Applicable SOW Paragraph: 3.3.1.1

CDRL: A002

DID Number: DI-NDTI-80809B NOT 2 DID Title: Test/Inspection Report – First Article Test Report Applicable SOW Paragraph: 3.3.1.4

CDRL: A003

DID Number: DI-QCIC-81891 NOT 2 DID Title: Acceptance Test Report (ATR) – Production Acceptance Test and Inspection Report Applicable SOW Paragraph: 3.3.2

CDRL: A004

DID Number: DI-MISC-82386 DID Title: Certification Data Report – Certificate of Conformance Applicable SOW Paragraph: 3.3.2.1

5.0 SPECIAL CONDITIONS/REQUIREMENTS

5.1 Security Classification

Tasking under this SOW is unclassified.

5.2 Information Non-Disclosure

The Contractor shall not disclose any information provided or developed under this contract outside the Government without prior approval from the Government.

5.3 Release of Information

All technical data provided to the Contractor as GFI shall be protected from the public. All other information relating to the items to be delivered and services to be performed under this contract may not be disclosed by any means without prior approval of the Government. Dissemination or public disclosure includes permitting access to such information by foreign nations, by any other person or entity, or publication of technical or scientific papers, or advertising, or any other proposed public release. The Contractor shall provide adequate physical protection to such information so as to preclude access by any person or entity not authorized such access.

CLAUSES INCORPORATED BY FULL TEXT

C-202-H001 ADDITIONAL DEFINITIONS–BASIC (NAVSEA) (OCT 2018)

(a) Department - means the Department of the Navy.

(b) Commander, Naval Sea Systems Command - means the Commander of the Naval Sea Systems Command of the Department of the Navy or his duly appointed successor.

(c) References to The Federal Acquisition Regulation (FAR) - All references to the FAR in this contract shall be deemed to also reference the appropriate sections of the Defense FAR Supplement (DFARS), unless clearly indicated otherwise.

(d) National Stock Numbers - Whenever the term Federal Item Identification Number and its acronym FIIN or the term Federal Stock Number and its acronym FSN appear in the contract, order or their cited specifications and standards, the terms and acronyms shall be interpreted as National Item Identification Number (NIIN) and National Stock Number (NSN) respectively which shall be defined as follows:

(1) National Item Identification Number (NIIN). The number assigned to each approved Item Identification under the Federal Cataloging Program. It consists of nine numeric characters, the first two of which are the National Codification Bureau (NCB) Code. The remaining positions consist of a seven digit non-significant number.

(2) National Stock Number (NSN). The National Stock Number (NSN) for an item of supply consists of the applicable four-position Federal Supply Class (FSC) plus the applicable nine-position NIIN assigned to the item of supply.

(End of text)

C-204-H001 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL CONTRACT FILES (NAVSEA)

(OCT 2018)

(a) NAVSEA may use a file room management support contractor, hereinafter referred to as "the support contractor", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as “protected information”. File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.

(b) The cognizant Contracting Officer will ensure that any NAVSEA contract under which these file room management services are acquired will contain a requirement that:

(1) The support contractor not disclose any information;

(2) Individual employees are to be instructed by the support contractor regarding the sensitivity of the official contract files;

(3) The support contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,

(4) In addition to any other rights the contractor may have, it is a third party beneficiary who has the right of direct action against the support contractor, or any person to whom the support contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.

(c) Execution of this contract by the contractor is considered consent to NAVSEA's permitting access to any information, irrespective of restrictive markings or the nature of the information submitted, by its file room management support contractor for the limited purpose of executing its file room support contract responsibilities.

(d) NAVSEA may, without further notice, enter into contracts with other contractors for these services. Contractors should enter into separate non-disclosure agreements with the file room contractor. Contact the Procuring Contracting Officer for contractor specifics. However, any such agreement will not be considered a prerequisite before information submitted is stored in the file room or otherwise encumber the government.

C-209-H001 FIRST ARTICLE (CONTRACTOR TESTING) (NAVSEA) (OCT 2018)

(a) The First Article shall conform in every respect to the requirements of this contract. The First Article shall be manufactured with tools, materials, and methods which are the same as the tools, material and methods which will be used to manufacture the production units. All items delivered under the contract shall be manufactured under the same conditions and quality established by the First Article. Any changes to tools, material, or methods after the first article approval shall be documented by the contractor and approved by the Contracting Officer before they are used.

(b) The Contractor shall make a record of all data obtained during such tests in a form similar to the guidance provided in MIL-HDBK-831A.

(c) Pursuant to paragraph (e) of the clause entitled "First Article Approval--Contractor Testing" (FAR 52.209-3), the First Article shall not be delivered as part of the production quantity.

C-209-H003 WAIVER OF FIRST ARTICLE REQUIREMENTS (NAVSEA) (OCT 2018)

If the First Article is waived by the Government, the Contractor shall deliver supplies that are identical or substantially identical to those previously accepted by the Government under the following contract(s):

(Offeror to fill in contract number(s), as applicable. See SOW Paragraph 3.3.1 and See Section M)

(End of Text)

C-211-H016 SPECIFICATIONS AND STANDARDS (NAVSEA) (OCT 2018)

(a) Definitions.

(i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments).

(ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing.

(b) Requirements. All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only unless specifically identified below.

None

C-211-H017 UPDATING SPECIFICATIONS AND STANDARDS (NAVSEA) (DEC 2018)

The contractor may request that this contract be updated to include the current version of the applicable specification or standard if the update does not affect the form, fit or function of any deliverable item or increase the cost/price of the item to the Government. The contractor should submit update requests to the Procuring Contracting Officer with copies to the Administrative Contracting Officer and cognizant program office representative for approval. The contractor shall perform the contract in accordance with the existing specifications and standards until notified of approval/disapproval of its request to update by the Procuring Contracting Officer. Any approved alternate specifications or standards will be incorporated into the contract.

C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019)

Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.

C-215-H002 CONTRACTOR PROPOSAL (NAVSEA) (OCT 2018)

(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with the detailed obligations to which the Contractor committed itself in Proposal dated in response to Solicitation No.

N0016423RGP78.

(b) The technical volume(s) of the Contractor's proposal is(are) hereby incorporated by reference and made subject to the "Order of Precedence" (FAR 52.215-8) clause of this contract. Under the "Order of Precedence" clause, the technical volume(s) of the Contractor's proposal referenced herein is (are) hereby designated as item (f) of the clause, following "the specifications" in the order of precedence.

*Offeror shall fill-in proposal number and date above

C-223-H003 EXCLUSION OF MERCURY (NAVSEA) (MAR 2019)

(a) Definitions. As used in this text:

Article means a manufactured item other than a fluid or particle: (i) which is formed to a specific shape or design during manufacture; (ii) which has end use function(s) dependent in whole or in part upon its shape or design during end use; and (iii) which under normal conditions of use does not release more than very small quantities, e.g., minute or trace amounts of a hazardous chemical, and does not pose a physical hazard or health risk to employees.

Boundary of containment means a continuous tight seal (barrier) to prevent the release of functional mercury during normal operation and maintenance. Examples include the exterior of a fluorescent lamp, glass capsule of a mercury switch, and container for mercury reagents. A double boundary of containment consists of two independent seals.

Functional mercury means mercury or mercury compound(s) contained in equipment that is required for the equipment to operate properly, such as that found in mercury switches, fluorescent lamps, flat-panel monitors, thermostats, thermostat probes, small coin type batteries, barometers, and dental amalgams.

Hardware means any article, container, piece of material, individual part, subassembly, assembly, component, or system to which mercury control requirements apply.

Mercury-free means hardware that does not contain functional mercury and is not contaminated by mercury or mercury compounds.

Portable means items that are frequently transported during normal operation. Desk lamps, shop lights, and hand-held instruments are considered portable, while bulbs in stationary light fixtures are not. In general, items that require transport only during maintenance, installation, and removal of the items are not considered portable.

(b) The Contractor, and all subcontractors and vendors, shall ensure that mercury or mercury containing compounds are not intentionally added to, or come in direct contact with, hardware or supplies furnished under this contract.

(1) The Contractor shall ensure that mercury and mercury compounds are not taken onboard naval vessels by Contractor, subcontractor, or vendor personnel except for functional mercury used in batteries, dental amalgams, fluorescent lamps, flat-panel monitors, required instruments, sensors or controls, weapon systems, and chemical analysis reagents specified by the Naval Sea Systems Command (NAVSEA).

(2) Portable fluorescent lamps and portable instruments containing elemental mercury must be shock-proof in accordance with MIL-DTL-901E entitled Requirements for Shock Tests, H.I. (High Impact) Shipboard Machinery, Equipment, and Systems and have mercury enclosed by a double boundary of containment. Some devices with liquid crystal display (LCD) screens utilize a fluorescent bulb backlight to illuminate the LCD screen.

No additional restrictions or controls apply to devices with LCD screens; however, the Contractor shall remove the LCD screen and seal it in plastic following any evidence that the backlight failed.

(3) For Submarines, any use of mercury containing items must be approved as required by the Nuclear Powered Submarine Atmosphere Control Manual (S9510-AB-ATM-010/U) Volume 1.

(4) The Contractor shall ensure that mercury and mercury compounds do not contact hardware surfaces in systems covered by NAVSEA Manual NAVSEA 0989-064-3000 entitled Cleanliness Requirements for Nuclear Propulsion Plant Maintenance and Construction, submarine air systems, level I systems per NAVSEA Publication 0948-LP-045-7010, NAVSEA Material Control Standard, or the submarine safety program (SUBSAFE) surfaces during maintenance or repair. Such hardware is designated as mercury-free. The Contractor shall ensure that all other hardware that could be structurally degraded by contamination with elemental mercury or reactive mercury compounds is separated from it by sufficient distance, or boundaries of containment that effectively prevents contact in all but the most extreme circumstances.

(5) The Contractor shall check any hardware surfaces in the above systems which are known or suspected to have come in contact with mercury or mercury compounds for evidence of structural degradation and external mercury contamination. The existence of external mercury contamination can be determined following MIL-STD- 2041D entitled Control of Detrimental Materials.

(6) The presence of mercury in a product may be determined by checking product labeling on material safety data sheets or safety data sheets. Chemical analysis is not required.

(7) The Contractor shall dispose of any mercury and mercury compounds in accordance with OPNAV Manual (OPNAV M-5090.1) entitled Environmental Readiness Program Manual of 10 January 2014.

(8) If the use of mercury or mercury compounds cannot be avoided, a risk assessment and waiver request, if required, must be performed and submitted per the NAVSEA Hazardous Material Avoidance Process (T9070-AL- DPC-020/077-2). For systems covered by the NAVSEA Manual NAVSEA 0989-064-3000 entitled Cleanliness Requirements for Nuclear Propulsion Plant Maintenance and Construction, submit the risk assessment and waiver request, if required to Nuclear Propulsion (NAVSEA 08).

(c) In all cases where mercury or a mercury compound has contacted hardware surfaces required to be mercury-free the Contractor shall immediately provide a report to the NAVSEA Dry Environmental Systems and Hazardous Materials (NAVSEA 05P5) via the cognizant contract administration safety office. Reports concerning systems covered by NAVSEA Manual 0989-064-3000 must include NAVSEA Nuclear Propulsion Directorate (SEA 08) in the distribution. Reports must be in letter form and include the date and details of the contact, the surfaces contacted, the recovery actions taken, and the status of the affected surfaces.

C-227-H006 DATA REQUIREMENTS (NAVSEA) (OCT 2018)

The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements List, DD Form 1423, Exhibit A, attached hereto.

C-233-H001 DOCUMENTATION OF REQUESTS FOR EQUITABLE ADJUSTMENT--BASIC (NAVSEA) (OCT 2018)

(a) For the purposes of this special contract requirement, the term "change" includes not only a change that is made pursuant to a written order designated as a "change order" but also (1) an engineering change proposed by the Government or by the Contractor and (2) any act or omission to act on the part of the Government in respect of which a request is made for equitable adjustment.

(b) Whenever the Contractor requests or proposes an equitable adjustment of $100,000 or more per vessel in respect to a change made pursuant to a written order designated as a "change order" or in respect to a proposed engineering change and whenever the Contractor requests an equitable adjustment in any amount in respect to any other act or omission to act on the part of the Government, the proposal supporting such request shall contain the following information for each individual item or element of the request:

(1) A description (i) of the work required by the contract before the change, which has been deleted by the change, and (ii) of the work deleted by the change which already has been completed. The description is to include a list of components, equipment, and other identifiable property involved. Also, the status of manufacture, procurement, or installation of such property is to be indicated. Separate description is to be furnished for design and production work.

Items of raw material, purchased parts, components and other identifiable hardware, which are made excess by the change and which are not to be retained by the Contractor, are to be listed for later disposition;

(2) Description of work necessary to undo work already completed which has been deleted by the change;

(3) Description of work not required by the terms hereof before the change, which is substituted or added by the change. A list of components and equipment (not bulk materials or items) involved should be included. Separate descriptions are to be furnished for design work and production work;

(4) Description of interference and inefficiencies in performing the change;

(5) Description of each element of disruption and exactly how work has been, or will be disrupted:

(i) The calendar period of time during which disruption occurred, or will occur;

(ii) Area(s) aboard the vessel where disruption occurred, or will occur;

(iii) Trade(s) disrupted, with a breakdown of manhours for each trade;

(iv) Scheduling of trades before, during, and after period of disruption;

(v) Description of measures taken to lessen the disruptive effect of the change;

(6) Delay in delivery attributable solely to the change;

(7) Other work attributable to the change;

(8) Supplementing the foregoing, a narrative statement of the direct "causal" relationship between any alleged Government act or omission and the claimed consequences therefor, cross-referenced to the detailed information provided as required above; and

(9) A statement setting forth a comparative enumeration of the amounts "budgeted" for the cost elements, including the material costs, labor hours and pertinent indirect costs, estimated by the Contractor in preparing its initial and ultimate proposal(s) for this contract, and the amounts claimed to have been incurred and/or projected to be incurred corresponding to each such "budgeted cost" elements.

(c) Each proposal in excess of $100,000 submitted in support of a claim for equitable adjustment under any requirement of this contract shall, in addition to the information required by paragraph (b) hereof, contain such information as the Contracting Officer may require with respect to each individual claim item.

(d) It is recognized that individual claims for equitable adjustment may not include all of the factors listed in paragraph

(b) above. Accordingly, the Contractor is required to set forth in its proposal information only with respect to those factors which are comprehended in the individual claim for equitable adjustment. In any event, the information furnished hereunder shall be in sufficient detail to permit the Contracting Officer to cross-reference the claimed increased costs, or delay in delivery, or both, as appropriate, submitted pursuant to paragraph (c) of this requirement, with the information submitted pursuant to paragraph (b) hereof.

C-242-H001 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (OCT 2018)

(a) As part of the negotiated fixed price or total estimated amount of this contract, both the Government and the Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $1,000 or less at the time of final contract closeout. The term "residual dollar amount" shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.

(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.

C-245-H005 INFORMATION AND DATA FURNISHED BY THE GOVERNMENT--ALTERNATE I

(NAVSEA) (MAY 2019)

(a) Contract Specifications, Drawings and Data. The Government will furnish, if not included as an attachment to the contract, any unique contract specifications or other design or alteration data cited or referenced in Section C.

(b) Government Furnished Information (GFI). GFI is defined as that information essential for the installation, test, operation, and interface support of all Government Furnished Material identified in an attachment in Section J. The Government shall furnish only the GFI identified in an attachment in Section J. The GFI furnished to the contractor need not be in any particular format. Further, the Government reserves the right to revise the listing of GFI as follows:

(1) The Contracting Officer may at any time by written order:

(i) delete, supersede, or revise, in whole or in part, data identified in an attachment in Section J; or

(ii) add items of data or information to the attachment identified in Section J; or

(iii) establish or revise due dates for items of data or information in the attachment identified in Section J.

(2) If any action taken by the Contracting Officer pursuant to subparagraph (1) immediately above causes an increase or decrease in the costs of, or the time required for, performance of any part of the work under this contract, the contractor may be entitled to an equitable adjustment in the contract amount and delivery schedule in accordance with the procedures provided for in the "CHANGES" clause of this contract.

(c) Except for the Government information and data specified by paragraphs (a) and (b) above, the Government will not be obligated to furnish the Contractor any specification, standard, drawing, technical documentation, or other publication, notwithstanding anything to the contrary in the contract specifications, the GFI identified in an attachment in Section J, the clause of this contract entitled "Government Property" (FAR 52.245-1) or "Government Property Installation Operation Services" (FAR 52.245-2), as applicable, or any other term or condition of this contract. Such referenced documentation may be obtained:

(1) From the ASSIST database via the internet at https://assist.dla.mil/online/start/; or

(2) By submitting a request to the

Department of Defense Single Stock Point (DoDSSP) Building 4, Section D

700 Robbins Avenue Philadelphia, Pennsylvania 19111-5094 Telephone (215) 697-6396 Facsimile (215) 697-9398.

Commercial specifications and standards, which may be referenced in the contract specification or any sub-tier specification or standard, are not available from Government sources and should be obtained from the publishers.

C-246-H003 LIMITATION OF LIABILITY--HIGH VALUE ITEMS (NAVSEA) (OCT 2018)

The following items are subject to the clause of this contract entitled "Limitation of Liability--High Value Items" (FAR 52.246-24 Alternate I):

CLIN

0002 and 0003

C-247-H001 PERMITS AND RESPONSIBILITIES (NAVSEA) (DEC 2018)

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits for complying with any applicable Federal, State, and Municipal laws, codes, and regulations for shipping and transportation including, but not limited to, any movement over public highways of overweight/over dimensional materials.

Section D - Packaging and Marking

D-211-H001 PACKAGING OF DATA (NAVSEA) (FEB 2022)

Data to be delivered by Integrated Digital Environment (IDE) or other electronic media shall be as specified in the contract.

All unclassified data to be shipped shall be prepared for shipment in accordance with best commercial practice.

Classified reports, data, and documentation shall be prepared for shipment in accordance with National Industrial Security Program Operating Manual (NISPOM), 32 CFR Part 117.

D-211-H002 MARKING OF REPORTS (NAVSEA) (OCT 2018)

All reports delivered by the Contractor to the Government under this contract shall prominently show on the cover of the report:

(1) name and business address of the Contractor

(2) contract number

(3) sponsor:

NSWC-CR, Code GXP (Name of Individual Sponsor)

Mr. Curt Sullivan (Name of Requiring Activity)

Crane, IN (City and State)

D-211-H004 IDENTIFICATION MARKING OF PARTS--BASIC (NAVSEA) (OCT 2018)

For all parts not subject to the marking requirements in DFARS 252.211-7003 – Item Unique Identification and Valuation, marking shall be accomplished in accordance with the following:

(1) Parts shall be marked in accordance with generally accepted commercial practice.

(2) In cases where parts are so small as not to permit identification marking as provided above, such parts shall be appropriately coded so as to permit ready identification.

D-246-H002 WARRANTY NOTIFICATION FOR ITEM(S) 0001-0003—BASIC (NAVSEA) (OCT 2018)

The Contractor shall apply a permanent warranty notification stamping or marking on each warranted deliverable end item and its container. The notification shall be placed in close proximity to other required stamping or markings so as to be easily readable by personnel. The warranty notification shall read:

THIS ITEM WARRANTED UNDER CONTRACT ________ TO CONFORM TO DESIGN,

MANUFACTURING, AND PERFORMANCE REQUIREMENTS AND BE FREE FROM DEFECTS IN

MATERIAL AND WORKMANSHIP FOR ________________ FROM DATE OF ACCEPTANCE. IF

ITEM IS DEFECTIVE NOTIFY _______________________ AND PCO.

*The Offeror’s standard warranty is acceptable to the Government at no additional cost.

D-247-H001 ADDITIONAL MARKING REQUIREMENTS FOR FMS ITEMS (NAVSEA) (OCT 2018)

(a) The following identifying marks shall appear on the outside of each box, parcel and/or crate and all shipping papers included in each shipment:

NAVY

FMS CASE See Individual Delivery Orders REQUISITION NO. See Individual Delivery Orders ITEM DESCRIPTION See Individual Delivery Orders

If a consolidated shipment of several items in one container is forwarded, add to the above information

"CONSOLIDATED SHIPMENT, CONTAINS ____ ITEMS".

(b) The inscription "UNITED STATES OF AMERICA" shall be affixed in a suitable size indelible stencil, label or printed form on all external shipping containers or the exterior surface of uncrated items.

(c) All invoices, correspondence, reports and other documents shall be identified with the appropriate FMS case designator, requisition number(s), and item description(s).

D-247-H002 PACKAGING OF SUPPLIES—BASIC (NAVSEA) (DEC 2020)

Item(s) 0001-0003 The supplies furnished hereunder shall be packaged in accordance with ASTM-D-3951-18, Standard Practice for Commercial Packing.

D-247-H004 MARKING AND PACKING LIST(S) – BASIC (NAVSEA) (FEB 2022)

(a) Marking. Shipments, shipping containers and palletized unit loads shall be marked in accordance with ASTM- D-3951-18 approved 1 May 2018, Standard Practice for Commercial Packing.

(b) Packing List(s). A packing list (DD Form 250 Material Inspection and Receiving Report may be used) identifying the contents of each shipment, shipping container or palletized unit load shall be provided by the Contractor with each shipment. When a contract line item identified under a single stock number includes an assortment of related items such as kit or set components, detached parts or accessories, installation hardware or material, the packing list(s) shall identify the assorted items. Where assortment of related items is included in the shipping container, a packing list identifying the contents shall be furnished.

(c) Master Packing List. In addition to the requirements in paragraph (b) above, a master packing list shall be prepared where more than one shipment, shipping container or palletized unit load comprise the contract line item being shipped. The master packing list shall be attached to the number one container and so identified.

(d) Part Identification. All items within the kit, set, installation hardware or material shall be suitably segregated and identified within the unit pack(s) or shipping container by part number and/or national stock number.

D-247-W001 PROHIBITED PACKING MATERIALS (NAVSEA) (OCT 2018)

The use of asbestos, excelsior, newspaper or shredded paper (all types including waxed paper, computer paper and similar hygroscopic or non-neutral material) is prohibited. In addition, the use of yellow wrapping or packaging material is prohibited except where used for the containment of radioactive material. Loose fill polystyrene is prohibited for shipboard use.

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Origin Government Origin Government 0002 Origin Government Origin Government 0003 Origin Government Origin Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government

SECTION E NOTE

Final inspection and acceptance of supplies to be furnished under CLIN 0001 through CLIN 0003 shall be made by DCMA Office TBD at Award at the Contractor’s facility located at TBD at Award. The cognizant DCMA Office shall be notified by the Contractor when the supplies are available for inspection.

CLAUSES INCORPORATED BY REFERENCE

52.246-2 Inspection Of Supplies--Fixed Price AUG 1996

E-246-H013 INSPECTION AND ACCEPTANCE OF DATA (NAVSEA) (OCT 2018)

Inspection and acceptance of all data shall be as specified on the attached Contract Data Requirements List(s), DD Form 1423.

E-246-H022 INSPECTION AND TEST RECORDS (NAVSEA) (JAN 2019)

Inspection and test records shall, as a minimum, indicate the nature of the observations, number of observations made, and the number and type of deficiencies found. Data included in inspection and test records shall be complete and accurate, and shall be used for trend analysis and to assess corrective action and effectiveness. The data shall, on request, be identified and made available for on-site review by the Contracting Officer or designated Government representative.

E-246-W002

E-246-W002 CERTIFICATE OF COMPLIANCE (NAVSEA) (OCT 2018)

(a) A certification of material shall be provided by the Contractor, one (1) copy to accompany the shipment (in the packing list envelope) and (l) copy mailed to arrive at time of receipt of the shipment. Mark all certificates to the attention of Code GXP.

(b) The certificate shall state compliance of material with drawing specification and contract/order requirements. The certificate shall as a minimum state the company name, contract/order number, drawing or specification number, and date. The certificate shall state, above the signature of a legally authorized representative of the company, the following:

This certification concerns a matter within the jurisdiction of an agency of the United States and the making of a false, fictitious, or fraudulent certification may render the maker subject to prosecution under Title 18, United States Code, Section 1001.

(c) Failure to provide certification at the time of shipment may result in material being rejected and returned at the contractor's expense.

(d) The certificate shall read as follows:

I certify that on ______ [insert date], the ____ [insert Contractor’s name] furnished the supplies called for by the Order/Contract No._____ via ____ [Carrier] on ________ [identify the bill of lading or shipping document] in accordance with all applicable requirements. I further certify that the supplies or services are of the quality specified and conform in all respects with the contract requirements, including specifications, drawings, preservation, packaging, packing, marking requirements, and physical item identification (part number), and are in the quantity shown on this document.

Date of Execution: ________________________________ Signature: _______________________________________ Typed Name: ____________________________________ Title: ___________________________________________

Section F - Deliveries or Performance

DELIVERY INFORMATION

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 120 dys. ADC 12 NAVAL SURFACE WARFARE CENTER

CRANE DIV

M/F: CURT SULLIVAN (BLDG 41NE)

BLDG 41 SE CENTRAL RECEIVING

300 HWY 361

CRANE IN 47522-5001

812-854-4113

N00164

0002 One (1) Ship Set 120 dys.

ADC and One (1) Ship Set 90 dys. thereafter

(SAME AS PREVIOUS LOCATION)

0003 One (1) Ship Set 120 dys.

ADC and One (1) Ship Set 90 dys. thereafter

(SAME AS PREVIOUS LOCATION)

0004 IAW DD1423s IAW DD1423s IAW DD1423s N00164

0005 N/A N/A (SAME AS PREVIOUS LOCATION)

DELIVERY NOTE FOR ALL CLINS

ADC above stands for “After Date of Contract” but in the case of this Indefinite-Delivery, Indefinite Quantity (IDIQ) contract resulting from this solicitation, ADC will mean After Date of Delivery Order. Delivery for CLIN 0001 will be 120 days ADC. Delivery for CLINs 0002 and 0003 will be 120 days ADC thereafter. Please note that for Delivery Orders containing multiple quantities, the first Ship Set is due 120 days ADC, and each additional Ship Set is due 90 days thereafter. Initial deliveries under CLIN 0002 and 0003 shall be 120 days (and each additional Ship Set is due 90 days thereafter) after First Article Approval unless First Articles are waived. Delivery for CLIN 0004 is in accordance with (IAW) Contract Data Requirements Lists, DD 1423s, A001-A004 (Section J – Exhibit A).

Early deliveries are acceptable to the Government at no additional cost.

52.242-15 Stop-Work Order AUG 1989 52.242-17 Government Delay Of Work APR 1984 52.247-34 F.O.B. Destination NOV 1991

F-242-H001 CONTRACTOR NOTICE REGARDING LATE DELIVERY (NAVSEA) (OCT 2018)

In the event the contractor anticipates or encounters difficulty in complying with the contract delivery schedule or date, the contractor shall immediately notify, in writing, the Contracting Officer and the cognizant Contract Administration Services Office, if assigned. The notice shall give the pertinent details; however, such notice shall not constitute a waiver by the Government of any contract delivery schedule, or of any rights or remedies provided by law or under this contract.

F-247-H001 DELIVERY OF DATA (NAVSEA) (OCT 2018)

All data to be furnished under this contract shall be delivered prepaid to the destination(s) and at the time(s) specified on the Contract Data Requirements List(s), DD Form 1423.

Section G - Contract Administration Data

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause—

“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.

“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.

“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall—

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before…

This is the start of the file's text. The full file is on GovTribe.