21RJR82_SOL_0001.pdf
PDF 388 KB Posted
- Attached to
- Demolition Charges
- Solicitation number
- N0016421RJR82
About this file
This is an amendment to a solicitation for demolition charges. The amendment provides answers to industry questions, adds drawing number 8601940 for palletization, and modifies the list of documents, exhibits, and attachments to include the new drawing. The solicitation seeks offers for demolition charges to specifications OES-DTL-0123D and technical data packages 8324775H and 8324774H. The Navy Naval Sea Systems Command is the contracting agency. The response deadline remains unchanged. Offerors must acknowledge receipt of the amendment prior to the specified deadline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 21RJR82_SOL_0005.pdf | ||
| 21RJR82_SOL_0004.pdf | ||
| 21RJR82_SOL_0003.pdf | ||
| 21RJR82_SOL_0002.pdf | ||
| 21RJR82_SOL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This solicitation amendment is to answ er industry questions and to add Draw ing #8601940 for Palletization.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Sep-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N0016421RJR82
X 9B. DATED (SEE ITEM 11)
09-Aug-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Sep-2021
CODE
NAVAL SURFACE WARFARE CENTER CRANE DIV
S. GAINEY (812-854-4621)
BLDG 3373
300 HWY 361
CRANE IN 47522-5001
N00164 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N0016421RJR82
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES 1.0
INDUSTRY QUESTIONS:
Question: Can you send us the outer packaging and palletization direction?
Answer: Drawing #8215661 has been attached to this amendment.
Question: About Lot Acceptance Testing (LAT), is it possible for testing to be performed on-site at contractor facility, or will all testing be done at Crane? If testing were to be done at contractor facility, would acceptance be origin or destination?
Answer: All LATs will be performed at Crane. Acceptance is FOB Destination.
Question: On drawing 8324777, for Detail B, we would like to know the depth of the hole that is referenced, and also the center height from the bottom of the container.
Answer: Depth on 8324777 should just be a taper for tooling relief. Allowance is given so that 8324781 (Priming Well) can be assembled to the Container. The center height is approximately 1.450 inches from bottom of container.
Question: On Drawing 8324782, in item 6, a nominal weight value of 9.8 lbs. for PAX-47 is given. Is there a weight tolerance above and/or below the nominal value for the PAX-47 content by weight for the
MK-179?
Answer: The Drawing does not provide a tolerance. The way it is currently manufactured the PAX-47 is over filled slightly in the container prior to the curing process to ensure a full container. After the curing process, the excess is shaved off so the lid can be glued on the container. The weights may vary slightly from one to another but the PAX-47 should be close to 9.8 lbs. The main thing is to ensure a full fill of each container.
Question: On Drawing 8324776, in item 6, a nominal weight value of 5.2 lbs. was given for PAX-47. Is there also a weight tolerance above and/or below the nominal value for the PAX-47 content by weight for the MK-180?
Answer: The Drawing does not provide a tolerance. The way it is currently manufactured the PAX-47 is over filled slightly in the container prior to the curing process to ensure a full container. After the curing process, the excess is shaved off so the lid can be glued on the container. The weights may vary slightly from one to another but the PAX-47 should be close to 5.2 lbs. The main thing is to ensure a full fill of each container.
Question: On drawing 8324785, for Union DASH-2, we would like to know the thru hole diameter for the union.
Answer: It is approximately 0.266 inches.
Question: Instead of hardcopy and CD-ROM submittals, would submission via DoD Safe Link be acceptable for the proposal submission?
Answer: DoD SAFE is not an acceptable form for proposal submission.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Exhibit A CDRLs A0001-A0010 10 15-JUL-2020 Attachment 01 Statement of Work Rev
A
25 10-MAR-2021
Attachment 02 Specification OES-
DTL-0123D
17 11-AUG-2020
Attachment 03 ADL 53711-8324775H 6 19-AUG-2020 Attachment 04 ADL 53711-8324774H 6 19-AUG-2020 Attachment 05 Drawing Package
8324775H
16 14-AUG-2020
Attachment 06 Drawing Package 8324774H
14 14-AUG-2020
Attachment 07 Potential Shipping Addresses
1 07-JUL-2021
Attachment 08 Technical Compliance Matrix
1 07-JUL-2021
Attachment 09 Small Business Participation Data Form
1 07-JUL-2021
Attachment 10 Past Performance Questionnaire
2 07-JUL-2021
to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Exhibit A CDRLs A0001-A0010 10 15-JUL-2020 Attachment 01 Statement of Work Rev
A
25 10-MAR-2021
Attachment 02 Specification OES-
DTL-0123D
17 11-AUG-2020
Attachment 03 ADL 53711-8324775H 6 19-AUG-2020 Attachment 04 ADL 53711-8324774H 6 19-AUG-2020 Attachment 05 Drawing Package
8324775H
16 14-AUG-2020
Attachment 06 Drawing Package 8324774H
14 14-AUG-2020
Attachment 07 Potential Shipping Addresses
1 07-JUL-2021
Attachment 08 Technical Compliance Matrix
1 07-JUL-2021
Attachment 09 Small Business Participation Data Form
1 07-JUL-2021
Attachment 10 Past Performance Questionnaire
2 07-JUL-2021
Attachment 11 Drawing #8215661 1 17-SEP-2013
(End of Summary of Changes)