21R1010_ 0001_sol.pdf
PDF 765 KB Posted
- Attached to
- CONSTRUCTION OF OPEN STORAGE FACILITY Federal contract opportunity
- Solicitation number
- N0016421R1010
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 21R1010_0001_ATT1.pdf | ||
| 21R1010_ATT1.zip | ZIP file | |
| 21R1010_sol.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The reason for this amendment is to update the draw ings included w ithin the Statement of Work (SOW). The original draw ings incorporated in the SOW have been deleted and a new draw ings package has been incorporated into Section J as an attachment.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 12
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Jul-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N0016421R1010
X 9B. DATED (SEE ITEM 11)
15-Jul-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-Jul-2021
CODE
NAVAL SURFACE WARFARE CENTER CRANE DIV
S. SWARTZENTRUBER (812-854-8153)
BLDG 121
300 HWY 361
CRANE IN 47522-5001
N00164 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N0016421R1010
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The Issued By organization has changed from
NAVAL SURFACE WARFARE CENTER CRANE DIV
A. YOO (812-854-8001)
BLDG 121
300 HWY 361
CRANE IN 47522-5001
to
NAVAL SURFACE WARFARE CENTER CRANE DIV
S. SWARTZENTRUBER (812-854-8153)
BLDG 121
300 HWY 361
CRANE IN 47522-5001
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
STATEMENT OF WORK
Statement of Work (SOW) Building 3699 Post Frame Storage Building
14 July 2021
1.0 SCOPE
The scope of this effort is to construct a 40’ x 50’ pole building for Naval Surface Warfare Center, Crane (NSWC Crane), Environmental Management (1023). This structure will be utilized to provide covered storage for containers of hazardous materials. The structure will provide protection from damaging weather elements preventing hazardous material spills due to container corrosion.
2.0 APPLICABLE DOCUMENTS
The following documents of the revision or issue in effect at the date of award, form a part of this SOW for reference. In the event of conflict between the documents referenced herein and the contents of this SOW, the contents of this SOW shall prevail.
EM385-1-1 U.S. Army Corps of Engineers Safety and Health Requirements Manual SECNAVINST 5370.2J Standards of Conduct and Government Ethics OPNAVINST 5102.1 Navy and Marine Corps Mishap and Safety Investigation, Reporting, and Record Keeping NSACRANEINST 5100.13A NSA Crane Smoking and Tobacco Use
3.0 PERFORMANCE REQUIREMENTS
The Contractor shall furnish the required material, equipment, labor, and build drawings (CDRL A008) to construct a 40’ x 50’ outdoor storage building with two ramps for entry and exit of material handling equipment. The storage shelter will be located at NSWC Crane, outside of building 3435. The Contractor shall utilize new material; no postconsumer or recovered material will be authorized for use. The Contractor shall adhere to all State and Federal building codes.
3.1 REQUIREMENTS
The alignment of the new wood frame structure with have a 10’ offset toward the southwest from the northern facing side of building 3435 (Figure 1). This alignment will have a 16’ offset to the north from the stationary storage connex box which is to the south of the new storage building location. Contractor shall include building number (3699) signage acquisition and installation. Physical building number signs locations TBD.
A) The build site will need to be graded and compacted with no less than 95% compaction. The existing grade is gently sloping from south to north with no major peaks or valleys. The build site currently has a stone base.
B) Post foundations will consist of a 50” x 16” hole with a 15” x 4” precast concrete cookie at the base of each hole. The Contractor shall use a minimum strength of 4,000 psi concrete mix for hole fill post foundations and backfill with aggregate and compact.
C) Overall building size requirement is 40’ x 50’ with 2 frame opening sizes centered on the 40’ sides: 20’ wide x 16’ tall (Figure 2 & 3). The structure shall be a wood frame with pre-fab trusses, 4” x 4” posts, 4/12” roof pitch, 2”x12” truss support girders, 2”x4” wall girders 2” OC, and 2”x4” roof purlins 2’ OC. The height of the structure will be 20’ from finished slab to bottom of truss chord (Figure 3).
F) Metal siding and roofing shall be no less than 29 gauge metal. Installed metal components will include: siding, roofing, ridge cap, drip edge, rake trim, and outside corner trim. The Contractor shall wrap both openings with bent metal to cover weather exposed framing and install hurricane ties to all trusses. The interior of the building will be unfinished with exposed framing. The exterior color of metal shall closely match the adjacent building 3435.
G) The concrete slab shall be 40’ x 50’ and maintain a 6” thickness throughout. The concrete mix shall be at or above a 4,000 psi strength. Polyethylene vapor barrier or equivalent with a 15 mil thickness and permeance rating of 0.04 perms minimum shall be used. The slab shall be reinforced with 6 gauge wire mesh. The control joints shall be finished according to industry/base standards. The slab shall have a steel trowel finish with a 2% slope.
H) The Contractor shall pour two 20’ concrete ramps adjacent to the 20’ openings on both ends of the structure (Figure 2). The ramps shall be 6” thick throughout, a minimum 4,000 psi strength, use polyethylene vapor barrier or equivalent with a 15 mil thickness and permeance rating of 0.04 perms, and must be reinforced with 6 gauge wire mesh. The control joints shall be finished according to industry/base standards. The slab to ramp connection shall be a foam expansion joint. The ramps shall have a broom finish and require a slope of 3% - 5%.
I) The Contractor shall clean the worksite at the end of each work day. The Contractor shall dispose of any scrap material and clean any spills that may occur.
J) The Contractor shall coordinate and schedule underground utility marking prior to digging.
The following requirements listed, but not limited to, are not applicable to this project:
A) There are no electrical, plumbing, HVAC, fire protection, or other utilities planned as part of this new facility.
B) There is no need for lightning protection needed as a permanent fixture of this facility.
C) There are currently no asbestos or lead based product concerns associated within the existing site.
3.2 Installation Access
Physical access to Government’s facility at Naval Support Activity (NSA), Crane or areas over which DoD, DoN, or U.S. Marine Corps shall be through the use of the Defense Biometric Identification System (DBIDS) and associated data processing/information services for purposes of protecting U.S./Coalition/allied government/national security areas of responsibility and information. The contractor shall obtain employee personal identity verification credentialing (badge) by submitting to the NSA Crane Visitor Center, form SECNAV 5512/1 (APR 2014), for each contractor employee. Upon Base Registrar authorization of form 5512/1 the contractor shall submit form NSA Crane 5512/47 DBIDS Badge Application Record to the NSWC Crane Security Division. The Contractor shall retrieve badges of employed personnel upon separation.
Each employee shall affix their badge on their person above the waste at all times while on the Activity.
Badges may only be removed for safety reasons and must be reaffixed when work is completed.
DBIDS information can be found at the following website: http://dbids.dmdc.mil/ For Contract employees or subcontractors requiring infrequent access to the Activity, one day temporary passes MAY be authorized. Requests for temporary passes shall be submitted to the COR at least 2 working days prior to base access.
Be advised that the DBIDS process and temporary pass process both involve a background check.
Persons with a Felony conviction in the last 10 years will not be issued badges or passes.
Individuals supporting these efforts shall comply with the latest security regulations applicable to the government facility/installation.
a. Depending on the facility/installation regulations, contractor personnel shall present a proper form of identification(s) and vehicle proof of insurance or vehicle rental agreement.
b. All contractor persons engaged in work while on government property shall be subject to inspection of their vehicles at any time by the government, and shall report any known or suspected security violations to the local host Security Department.
Failure to obtain entry approval will not affect the contract price or the time of completion.
3.3 Program Management
The Contractor shall comply with the manufacturer’s recommendations in installation of all materials and equipment. The Contractor shall be responsible for field verification of actual conditions prior to commencement of work. The Contractor shall be responsible for quality control of all work that is performed via this task order. The Contractor is responsible for compliance with the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, and shall maintain a safe working environment at all times during the performance of this task order. Although this document is intended to identify all significant features of work to be accomplished in the performance of this task order, it should not be considered absolutely inclusive of all minor tasks required for completion of the major work described herein.
3.3.1 Design and Construction Quality Control Plan
The Contractor shall establish and maintain a Quality Control program that is administered by a Design and Construction Quality Control organization, using Quality Control (Design and Construction) Plans, (CDRL A009) Commissioning Plans and Reports, meetings, a Coordination and Mutual Understanding Meeting, three phases of control, submittal review and approval, testing, completion inspections, and QC certifications, Inspections in accordance with Section 01 45 35.05 20 SPECIAL INSPECTIONS FOR
DESIGN-BUILD or Section 01 45 35.05 10 SPECIAL INSPECTIONS FOR DESIGN-BID-BUILD and documentation necessary to provide design, materials, equipment, workmanship, fabrication, construction and operations which comply with the requirements of this Contract. The QC program must cover on-site and off-site work. (CDRL A010) No construction work or testing may be performed unless the Contractor’s QC Manager is on the work site.
3.3.2 Inspection Benchmarks
A) Pre-foundation pour (Posts set in place ready to pour concrete) B) Framing completion inspection (at framing completion prior to installing metal) C) Pre-slab/ramp pour (Graded, formed, vapor barrier and reinforcing wire in place) D) Pre-Final The Government and QC Manager will perform this inspection to verify that the facility is complete and ready to be occupied. A Government "Pre-Final Punch List" will be documented by the QC Manager as a result of this inspection. The QC Manager will ensure that all items on this list are corrected prior to notifying the Government that a "Final" inspection with the Client can be scheduled. Any items noted on the "Pre-Final" inspection must be corrected in a timely manner and be accomplished before the contract completion date for the work or any particular increment thereof, if the project is divided into increments by separate completion dates.
E) Final (At completion) Notify the COR at least 5 working days prior to the date a final acceptance inspection can be held. State within the notice that all items previously identified on the pre-final punch list will be corrected and acceptable, along with any other unfinished Contract work, by the date of the final acceptance inspection. The Contractor must be represented by the QC Manager, the Project Superintendent, the CA, and others deemed necessary. Attendees for the Government may include the PCO, COR, Construction Management personnel, and personnel representing the Client.
3.4 Safety and Health
3.4.1 Activity Hazard Analysis (AHA)
Before beginning each activity, task or Definable Feature of Work (DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity must prepare an AHA. Format the AHA in accordance with EM 385-1-1, Section 1 or as directed by the COR. Submit the AHA for review at least 5 working days prior to the start of construction, or DFOW (CDRL A002). The Government reserves the right to require the Contractor to revise and resubmit the AHA if it fails to effectively identify the work sequences, specific anticipated hazards, site conditions, equipment, materials, personnel and the control measures to be implemented.
3.4.2 Standard Lift Plan (SLP)
Plan lifts to avoid situations where the operator cannot maintain safe control of the lift. Prepare a written SLP in accordance with EM 385-1-1, Section 16.A.03, and using Form 16-2 for every lift or series of lifts (if duty cycle or routine lifts are being performed). Submit SLP to the COR for approval within 5 working days in advance of planned lift (CDRL A005).
3.4.3 Accident Prevention Plan
Contractor shall provide a site-specific Accident Prevention Plan (APP), including Activity Hazard Analyses (AHA), in accordance with EM 385-1-1 Appendix A, paragraph 3.k for the design team to follow during site visits and investigations. For subsequent visits, update the form if there are changes in the personnel who will be attending, or the tasks to be performed. Submit the APP for review and acceptance by the Government at least 5 working days prior to the start of the design field work. (CDRL A003)
3.4.4 Accident/Incident Reporting
The Contractor shall maintain an accurate record of and shall report all accidents to the COR immediately after incident occurs. (CDRL A006)
For Navy Projects, complete (CDRL A006). Near miss reports are considered positive and proactive Contractor safety management actions The Contractor shall maintain an accurate record of and shall immediately report to the COR all damages to Government Furnished Equipment and Facilities as prescribed by OPNAVINST 5102.1. (CDRL A007)
3.5 Waste Management Plan
The Contractor shall submit a waste management plan within 5 working days after contract award. In accordance with UFGS 01 74 19 Construction and Demolition Waste Management. The plan must demonstrate how the project waste diversion goal is met and plan must include the following: (CDRL A011)
Ensure Hazardous Waste is labeled, handled and stored in accordance with the Safety Data Sheets (SDS) and regulations.
The Contractor shall contact the COR to set up a temporary hazardous waste storage area. This storage area shall not exceed 60 days.
The Contractor shall immediately (within minutes) notify the Fire department, and COR of any hazardous material spillage.
The Contractor shall be responsible for clean-up efforts in accordance with 40 CFR 300 and shall provide verbal and written notifications to the COR (CDRL A012) as required by 40 CFR 355.
Hazardous Waste Manifests shall be approved by the COR (CDRL A013) prior to transporting hazardous waste to the disposal site.
Any unforeseen hazardous material is found or suspected to be hazardous material the contractor shall notify the COR. (CDRL A004) Stop work and wait for the government for instructions.
3.6 Waste Management Records
The Contractor shall maintain records to document the quantity of waste generated. The contractor shall make the records available to the COR during construction, and a copy of the records must be delivered to the COR upon completion of the construction. (CDRL A014)
3.7 Environmental
3.7.1 This project will be constructed in an area where the ground has been previously disturbed. The site is not located in a Storm Water Management Unit (SWMU); however, the potential exists to encounter contaminated soils or buried debris. If, during construction anything suspicious (i.e., unusually colored soils, unsuspected debris, odors, etc.) is discovered, stop work immediately and contact the Contracting Officer. Burning is prohibited
3.7.2 The Contractor shall not use any asbestos containing material (ACM) at any time during the construction. The Contractor shall verify that all materials, including those supplied by third parties, are asbestos free.
A written certification letter shall be provided by the Contractor to the Contract Officer certifying that the finished work is asbestos free. A signed letter-head stating,” to the best of my knowledge, no ACBM was used as a building material in the building” may suffice, per 40 CFR part 763.99 (a)(7). (CDRL A015)
The Contractor shall submit SDS for any suspect materials to the Contract Officer.
3.7.3 Contractor shall notify the COR a minimum of 14 days prior to the use of nuclear density gauges on base. (CDRL A018) A temporary RCOMA will be applied for at the time of the notice of use.
3.8 Closeout Submittals
As-built drawings are developed and maintained by the Contractor and depict actual conditions, including deviations from the Contract Documents. These deviations and additions may result from coordination required by, but not limited to: contract modifications; official responses to Contractor submitted Requests for Information; direction from the COR; designs which are the responsibility of the Contractor, and differing site conditions. Maintain the as-built throughout construction as red-lined hard copies on site.
These files serve as the basis for the creation of the record drawings.
The record drawings are the final compilation of actual conditions reflected in the as-built drawings.
Provide and maintain two black line print copies of the PDF contract drawings for As-Built Drawings in accordance with FC 1-300-09N. At a minimum of 5 working days prior to Beneficial Occupancy Date (BOD), certify both sets of as-built drawings as correct, sign, and submit the As- Built Drawings for COR approval. (CRDL A017) Record Drawings on two separate CDs or DVDs.
3.9 Warranty Management Plan
Develop a warranty management plan which contains information relevant to FAR 52.246-21. At least 10 working days before the planned pre-warranty conference, submit one set of the warranty management plan. (CDRL A016) Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesmen, or of engineering background, not necessarily familiar with this contract. The term "status" as indicated below must include due date and whether item has been submitted or was accomplished. Warranty information made available during the construction phase must be submitted to the COR for approval prior to each pay estimate. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of project acceptance and continue for the full product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contractor, COR, and the Customer Representative.
3.10 Real Property Records
Near completion of the project, but a minimum of 30 working days prior to final acceptance of the work, complete the appropriate fields and submit an accounting of all installed property on the Government provided Draft DD FORM 1354. Furthermore, a minimum of 30 working days after final acceptance, complete the appropriate fields of the Government provided Interim DD FORM 1354 including any additional assets, improvements, and alterations from the Draft DD FORM 1354. Contact the Contracting Officer Representative for any project specific information necessary to complete the DD FORM 1354. Refer to UFC 1-300-08 for instruction on completing the DD FORM 1354. For convenience, a blank fillable PDF DD FORM 1354 may be obtained at the following link: www.esd.whs.mil/Portals/54/Documents/DD/forms/dd/dd1354.pdf
4.0 TECHNICAL DATA DELIVERABLES
CDRL DID Number DID Title Applicable
SOW
Paragraph
Deliverable Schedule
A001 DI-MGMT-81834 Contractor’s Personnel Roster 5.14 Post Award Kickoff
A002 DI-SAFT-81841 Operating, Support, Health, & Safety (OSH&S) Hazard Analysis Report
3.4.1 5 Days prior to the start of field work
A003 DI-MISC-80508B Accident Prevention Plan 3.4.3 5 Days prior to the start of field work
A004 DI-MISC-80508B Severe Hazard Exposure 3.5 ASREQ A005 DI-MISC-80508B Lift Plan 3.4.2 5 Working days prior to lift A006 DI-SAFT-81563 Accident/Incident Report 3.4.4, 5.7 ASREQ A007 DI-MISC-80508B Damage Reporting 3.4.4, 5.9 ASREQ A008 DI-MISC-80508B Approved Build Drawings 3.0 Post Award
Kickoff A009 DI-MISC-80508B Quality Control Plan 3.3.1 Post Award
Kickoff A010 DI-MISC-80508B Production Report / Schedule /
Checklist
3.3.1 Post Award
Kickoff A011 DI-MISC-80508B Waste Management Plan 3.5 5 Days after
Award A012 DI-MISC-80508B Hazardous Material Clean-Up
Report
3.5 ASREQ
A013 DI-MISC-80508B Uniform Hazardous Waste Manifests
3.5 Prior to transport
A014 DI-MISC-80508B Waste Management Report 3.6 ASREQ A015 DI-MISC-80508B Asbestos Containing Building
Material Report
3.7.2 ASREQ
A016 DI-MISC-80508B Warranty Management Plan 3.7.2, 3.9 10 days prior to pre-warranty conference
A017 DI-MISC-81489B Real Property Facilities As-Built Drawings
3.8 5 days prior to
BOD
A018 DI-MISC-80508B Temporary RCOMA Permit 3.7.3 14 Days prior to use
5.0 SPECIAL CONDITIONS
5.1 Contracting Officer’s Representative (COR)
The COR is the point of contact for non-substantiated communications of a technical nature. Only the Contracting Officer has the authority to change the requirements of this order(s).
5.2 Requiring Technical Activity (RTA)
The RTA contacts are Functional Managers, Task Managers, and project leads. RTAs do not have the authority to direct Contractor personnel or change the requirements of this order(s) or change the requirements of any TI(s). RTA’s shall be copied on each CDRL deliverable identified.
5.3 Safety and Health
The requirements of this order may require Contractor personnel to come in contact or be exposed to hazardous conditions. The Contractor shall abide by all applicable federal, local, and state occupational safety and health requirements. The Government will provide Standard Operating Procedures (SOP) when applicable. The Contractor must have on record a corporate safety plan and shall provide a copy to the COR when instructed. The Contractor shall ensure all employees have appropriate Personal Protection Equipment (PPE). The Contractor shall ensure employees have all required training and certifications related to Occupational Safety and Health Administration (OSHA) requirements.
Any Contractor employee exhibiting unsafe behavior may be removed from the NSWC Crane site. Such removal shall not relieve the Contractor from meeting its contractual obligations and shall not be considered an excusable delay as defined in FAR 52.249-14.
5.4 Hazardous Materials
The Contractor will provide a responsible party for the handling of the hazardous materials and the respective SDS. This responsibility includes proper training in the handling and disposal of the hazardous materials.
5.5 Control of Contractor Personnel
Contractor personnel shall physically access government facilities and installations for purposes of site visitation, meeting attendance, supervisory and work performance within government spaces (either temporary or permanent). Individuals supporting these efforts shall comply with the latest security regulations applicable to the government facility/installation.
a) Depending on the facility/installation regulations, Contractor personnel shall present a proper form of identification(s) and vehicle proof of insurance or vehicle rental agreement.
b) All Contractor persons engaged in work while on government property shall be subject to inspection of their vehicles at any time by the government, and shall report any known or suspected security violations to the local host Security Department.
c) All persons engaged in work while on Government property shall be subject to search of their persons (no bodily search) and vehicles at any time by the Government, and shall report any known or suspected security violations to the NSWC Crane Security Department.
d) Assignment, transfer, and reassignment of Contractor personnel shall be at the discretion of the Contractor. However, when the Government directs, the Contractor shall remove from contract performance any person who endangers life, property, or national security through improper conduct.
e) All Contractor personnel engaged in work while on Government property shall be subject to the Standards of Conduct contained in SECNAVINST 5370.2J (Standards of Conduct and Government Ethics).
f) Prior to conducting work under this contract, the Contractor shall provide a list of employees that will be working on site. The employee list shall contain full names, security clearance levels, social security numbers, job titles, and official birth certificates. This list shall be updated within forty-eight hours after changes occur.
g) Any photography on base is not permitted without prior approval and photography permit request submitted to the RTA. Permit request (NSWCCRANEINST 5500.1) must be approved and signed by the RTA prior to any photos being taken. All photos taken, after approval, must be analyzed and approved prior to release.
5.7 Accident Reporting
The Contractor shall maintain an accurate record of and shall report all accidents to the COR immediately after incident occurs. (CDRL A006)
5.8 Smoking Regulations
Smoking on NSWC Crane, Crane, IN premises shall be in approved areas only in accordance with NSACRANEINST 5100.13A (NSA Crane Smoking and Tobacco Use). Smoking in vehicles is prohibited.
5.9 Damage Reporting
The Contractor shall maintain an accurate record of and shall immediately report to the COR all damages to Government Furnished Equipment and Facilities as prescribed by OPNAVINST 5102.1. (CDRL A007)
5.10 Investigations
Contractor employees shall cooperate with Government investigative agencies conducting criminal or administrative investigations.
5.11 Government Observations
Government personnel, such as Inspector General or higher headquarters staff, are authorized to observe Contractor operations. Efforts will be made to minimize the degree of disturbance on Contractor performance.
5.12 Hours of Operation
NSWC Crane core duty hours for on-site Contractor personnel and the Contractor’s liaison facility personnel assigned to this effort are 0900 to 1430 hours, Monday through Friday, during regular Government workdays.
Government personnel are afforded a flextime schedule that allows a starting time between the hours of 0600 and 0900, with a quitting time between the hours of 1430 and 1800 depending on the applicable work schedule. Contractors are required to work during Government work hours in accordance with company timekeeping policies. Exceptions may be approved by the COR if requested by the Contractor.
5.12.1 Closed Days
All closed days will be designated by the Commander, NSWC Crane. Closed days will be associated with holidays, National Security, and/or inclement weather/dangerous conditions. The Contractor will not be allowed to work on NSWC Crane during designated closed days.
5.12.1.1 Inclement Weather
When the Government Agency is closed by the Commander because of inclement weather conditions and/or dangerous conditions, notification of the closing will be broadcast over local radio and television stations.
5.13 Licenses, Certifications, and Training
The Contractor shall provide capable personnel with qualifications, experience levels, security clearances, and necessary licenses, certifications, and training required by Federal, State, and Local laws and regulations. Training necessary to ensure that personnel performing under this contract maintain the knowledge and skills to successfully perform the required functions is the responsibility of the Contractor.
Training necessary to maintain professional certification is the responsibility of the Contractor.
5.14 Contractor Identification
This contract is for non-personal services as defined by FAR Subpart 37.104. As such, Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. In addition, Contractor personnel shall appropriately identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence. Contractor shall provide a Contractors Personnel Roster (CDRL A001).
5.15 Post Award Meetings
A Post Award Meeting with the successful offeror will be conducted within 15 working days after award of the contract. The Contractor will be given at least five working days’ notice of location and time of the meeting prior to the date of the meeting by the Contracting Officer. The requirement for a Post Award meeting shall, in no event, constitute grounds for excusable delay by the Contractor in performance of any provisions of the contract. A second post award meeting may, if necessary, be held after the receipt of the first invoice to assure that adequate documentation has been received to substantiate the validity of the invoice for the stated period of performance, in accordance with HQ G-2-0007. The Contractor will be given at least five working days’ notice prior to the date of the meeting by the Contract Specialist.
6.0 PLACE OF PERFORMANCE
The primary work site will be Naval Surface Warfare Center Crane Division, Crane, IN.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Exhibit A Exhibit A CDRLS A001 to A018
54 14-JUL-2021
Attachment 1 DBA WD IN20210008 070221
5 02-JUL-2021
Attachment 2 PPQ N0016421R1010 1 14-JUL-2021 to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Exhibit A Exhibit A CDRLS A001 to A018
54 14-JUL-2021
Attachment 1 DBA WD IN20210008 070221
5 02-JUL-2021
Attachment 2 PPQ N0016421R1010 1 14-JUL-2021 Attachment 3 Statement of Work
Drawings Figures
3 13-JUL-2021
(End of Summary of Changes)