RFP_SHAFTS_N0010418RF003.pdf
PDF 1 MB Posted
- Solicitation number
- N0010418RF003
About this file
N0010418RF003
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP_SHAFTS_N0010418RF003.U0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INFORMATION TO OFFERORS OR QUOTERS
SECTION A – COVER SHEET
Form Approved OMB No. 9000-0002 Expires Sep 30, 2000
The public reporting burden for his collection of information is estimated to average 35 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of the collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (9000-0002), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
PLEASE DO NOT RETURN YOUR FORM TO THE ABOVE ADDRESS. RETURN COMPLETED FORM TO THE ADDRESS IN BLOCK 4 BELOW.
1. SOLICITATION NUMBER 2 (X one) 3. DATE/TIME RESPONSE DUE
N00104-18-R-F003
a. INVITATION FOR BID (IFB) 6 July 2018 2:00 p.m.(local time) X b. REQUEST FOR PROPOSAL (RFP)
c. REQUEST FOR QUOTATION (RFQ)
INSTRUCTIONS
NOTE: The provision entitled “Required Central Contractor Registration” is applicable to most solicitations.
1. If you are not submitting a response, complete the information in Blocks 9 through 11 and return to the issuing office in Block 4 unless a different return address is indicated in Block 7.
2. Offerors or quoters must include full, accurate, and complete information in their responses as required by this solicitation (including attachments). “Fill-ins” are provided on Standard From 18, Standard Form 33, and other solicitation documents. Examine the entire solicitation carefully. The penalty for making false statements is prescribed in 18 U.S. C. 1001.
3. Offerors or quoters must plainly mark their responses with the Solicitation Number and the date and local time for bid opening or receipt of proposals that is in the solicitation document.
4. Information regarding the timeliness of response is addressed in the provision of this solicitation entitled either “Late Submission, Modification and Withdrawal of Bid” or “Instructions to Offerors – Competitive Acquisition”.
4. ISSUING OFFICE (Complete mailing address, including ZIP Code)
5. ITEMS TO BE PURCHASED (Brief description)
NAVSUP WSS - Mechanicsburg 5450 Carlisle Pike PO Box 2020 Mechanicsburg PA 17055-0788 POC: TAMMY LITTLE Code: N743.12
1 SHIP SET CONSISTING OF:
2S 2010-01-141-3639 (1) LSD CLASS PROP Shaft 2S 2010 01-141-3638 (1)
LSD CLASS STERN SHAFT
6. PROCUREMENT INFORMATION (X and complete as applicable)
a. THIS PROCUREMENT IN UNRESTRICTED
X
b. THIS PROCUREMENT IS 100 % SET-ASIDE FOR SMALL BUSINESS. THE APPLICABLE SIC CODE IS:
c. THIS PROCUREMENT IS % SET-ASIDE FOR HUB ZONE CONCERNS. THE APPLICABLE SIC CODE IS:
d. THIS PROCUREMENT IS RESTRICTED TO FIRMS ELIGIBLE UNDER SECTION 8(a) OF THE SMALL BUSINESS ACT.
7. ADDITIONAL INFORMATION
NOTE - IT IS POLICY OF THE DOD TO MAXIMIZE THE NUMBER OF SMALL AND SMALL DISADVANTAGED BUSINESS (SDB) CONCERNS PARTICIPATING IN DEFENSE PRIME AND SUBCONTRACTS. IT IS REQUIRED THAT PRIME CONTRACTORS' SUBCONTRACT PLANS, WHEN REQUIRED BY THE SOLICITATION, REFLECT A SDB GOAL OF 5%, OR GREATER.
NOTE - THE CLAUSE 52.232-25 ENTITLED "PROMPT PAYMENT" IN THE SOLICITATION.
8. POINT OF CONTACT FOR INFORMATION
a. NAME (Last, First, Middle Initial) b. ADDRESS (Include Zip Code) LITTLE, TAMMY, R.A. NAVSUP WSS - Mechanicsburg
5450 Carlisle Pike
PO BOX 2020
Mechanicsburg PA 17055-0788
c. TELEPHONE NUMBER (include Area Code and Extension)
d. E-MAIL ADDRESS
717-605-4056 Tammy.little@navy.mil
9. REASONS FOR NO RESPONSE (X all that apply)
a. CANNOT COMPLY WITH SPECIFICATIONS d. DO NOT REGULARLY MANUFACTURE OR SELL THE TYPE OF ITEMS INVOLVED
b. UNABLE TO IDENTIFY THE ITEM(S) e. OTHER (Specify)
c. CANNOT MEET DELIVERY REQUIREMENT
10. MAILING LIST INFORMATION (X one) WE DO DO NOT DESIRE TO BE RETAINED ON THE MAILING LIST FOR FUTURE PROCUREMENT OF THE TYPE OF INVOLVED 11a. COMPANY NAME b. ADDRESS (Include Zip Code)
c. ACTION OFFICER
(1) TYPED OR PRINTED NAME (Last, First, Middle Initial)
(2) TITLE
(3) SIGNATURE (4) DATE SIGNED
(YYYYMMDD)
DD FORM 1707, FEB 2002 (EG) PREVIOUS EDITION IS OBSOLETE
WHS/DIOR, Feb 99
DD FORM 1707 (BACK), FEB 2002
SOLICITATION, OFFER AND AWARD 1. THIS CONTRACT IS A RATED ORDER RATING PAGE OF PAGES
(4/2007) UNDER DPAS (15 CFR 700) DO-A3 1 31
2.CONTRACT NUMBER 3.SOLICITATION NUMBER 4.TYPE OF SOLICITATION 5.DATE ISSUED 6.REQUISITION/PURCAHSE NUMBER
N00104-18-R-F003
SEALED BID (IFB)
NEGOTIATED (RFP)
5 FEB 2018
7. ISSUED BY CODE N00104 8. ADDRESS OFFER TO (If other than Item 7)
NAVSUP WSS-MECHANICSBURG
5450 CARLISLE PIKE
P O BOX 2020
MECHANICSBURG PA 17055-0788
NAVSUP WSS - Mechanicsburg POC: Tammy Little Alternate POC: Preston Grant
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder”
SOLICITATION
9. Sealed offer in original and 1 copies for furnishing the supplies or service in the Schedule will be received at the place specified in Item 8, or if handicapped, uploaded electronically to the secure server located at:
www.neco.navy.mil. until 2:00 p. m. local time 18/02/23 (Hour) (YY/MMM/DD) CAUTION – LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
10. FOR
INFORMATION
CALL ►
A. NAME B. TELEPHONE (NO COLLECT CALLS) C. E-MAIL ADDRESS
AREA CODE NUMBER EXT
TAMMY LITTLE N743.12 717 605 4056 Tammy.little@navy.mil
11. TABLE OF CONTENTS
(X) SEC. DESCRIPTION PAGE(S) (X) SEC. DESCRIPTION PAGE(S)
PART I – THE SCHEDULE PART II – CONTRACT CLAUSES
A SOLICITATION/CONTRACT FORM 1 I CONTRACT CLAUSES
B SUPPLIES OR SERVICES AND PRICES/COSTS 2 PART III – LIST OF DOCUMENTS, EXHIBITS ANDOTHER ATTACH.
C DESCRIPTION/SPECS./WORK STATEMENT 6 J LIST OF ATTACHMENT
D PACKAGING AND MARKING 7 PART IV – REPRESENTATIONS AND INSTRUCTIONS
E INSPECTION AND ACCEPTANCE 13
K
REPRESENTATIONS, CERTIFICATIONS AND OTHER
STATEMENTS OF OFFERORS
F DELIVERIES OR PERFORMANCE 14
G CONTRACT ADMINISTRATION DATA 17 L INSTRS.,CONDS., AND NOTICES TO OFFERORS
H SPECIAL CONTRACT REQUIREMENTS 18 M EVALUATION FACTORS FOR AWARD
OFFER (Must be fully completed by offeror) NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s) within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT 10 CALENDAR DAYS (%) 20 CALENDAR DAYS (%) 30 CALENDAR DAYS(%) CALENDAR DAYS(%) (See Section I, Clause No.52.232-8
14. ACKNOWLEDGEMENT OF AMEND-
MENTS (The offeror acknowledges receipt of amendments to the SOLICITATION for offerors and related documents numbered and dated):
AMENDMENT NO. DATE AMENDMENT NO. DATE
15A. NAME AND
ADDRESS
OF OFFEROR
CODE FACILITY 16. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or Print)
15B. TELEPHONE NUMBER 15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE – ENTER SUCH
ADDRESS IN SCHEDULE.
17. SIGNATURE 18.OFFER DATE
AREA CODE NUMBER EXT
AWARD (To be completed by Government)
19.ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL ANDOPEN COMPETITION: 23. SUBMIT INVOICES TO ADDRESS SHOWN
IN(4 copies unless otherwise specified)
ITEM
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28.AWARD DATE
(Signature of Contracting Officer) IMPORTANT – Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
REFERENCE NO. OF DOCUMENT BEING CONTINUED
PAGE
OF
CONTINUATION SHEET
N00104-18-R-F003
(OPTIONAL FORM 336) 2 31
ITEM NO.
SECTION B - SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
0001 EVALUATE, REPAIR AND/OR MODIFY
NSN 2S 2010-01- 141-3638
LSD 41 CLASS STERN TUBE SHAFT
0001AA SAME AS ITEM 0001 1 EA
IN ACCORDANCE WITH SECTION “C” PART 1
SHIP TO:
SW3115, BARSTOW, CA OR
SW3126, CHEATHAM ANNEX
*The ship to will depend on the location of the awardee
INSPECTION AT ORIGIN
ACCEPTANCE AT ORIGIN
FOB DESTINATION
DELIVERY BY 1 APR 2019
0002 2S-2010-01-141-3639
1 EA
LSD CLASS PROP SHAFT
0002AA IN ACCORDANCE WITH SECTION “C” PART 2
SHIP TO: SAME AS 0001AA
INSPECTION AT ORIGIN
ACCEPTANCE AT ORIGIN
FOB DESTINATION
0003 CONTRACT DATA REQUIREMENTS LIST 1 LOT NSP NSP
SEE SECTION C and DD form 1423 exhibit A, 0003AA OVER AND ABOVE WORK, ONLY IF REQUIRED
NECO PROPOSAL WILL NOT BE CONSIDERED. PLEASE
EMAIL, FAX, OR MAIL PROPOSAL TO THE POC and
ALTERNATE POC.
FOR FURTHER INSTRUCTIONS, SEE NAVSUPWSSLA24
AND FAR 52.215-1.
ALL LARGE BUSINESSES ARE REQUIRED TO SUBMIT
A SMALL BUSINESS SUBCONTRACTING PLAN,
IF APPLICABLE.
PROGRESS PAYMENTS ARE AVAILABLE TO ELIGIBLE
CONTRACTORS.
This is a 100% SB-Set-Aside
THIS REQUIREMENT IS OPEN TO CURRENT
QUALIFIED REPAIR SOURCES.
PART I – THE SCHEDULE
SECTION C PART 1
STATEMENT OF WORK
Enclosures:
(1) Supplementary Split Sleeve Data and Instructions (FWD Sleeve)
(2) Supplementary Split Sleeve Data and Instructions (AFT Sleeve)
Application of Sherwin Williams’ Nova-Plate UHS Primer High Solids Epoxy Paint
A. Complete Pre-Repair in accordance with S9243-AW-TRS-011/SHAFT.
B. Prep for weld repair by machining as necessary up to 18 linear feet
(entire shaft circumference).
C. NDT all prepped areas prior to welding in accordance with NAVSEA Tech.
Pub. S9074-AR-GIB-010/278 and/or NAVSEA Tech. Pub. T9074-AS-GIB-010/271 as required by MIL-STD-2191.
D. Weld repair all prepped areas in accordance with NAVSEA Tech. Pub.
S9074-AQ-GIB-010/248 as required by MIL-STD-2191 up to 1 pass of 18 linear feet (entire shaft circumference) and up to an additional 6 linear feet (entire shaft circumference) of multilayer passes.
E. NDT weld repair areas, in accordance with NAVSEA Tech. Pub. S9074-AR- GIB-010/278 and/or NAVSEA Tech. Pub. T9074-AS-GIB-010/271 as required by MIL-STD-2191. Additional NDT will be required for multiple weld passes.
F. Stress relieve all welded areas in accordance with MIL-STD-2191.
G. Recheck concentricity after stress relieving; straighten if necessary in accordance with MIL-STD-2191.
H. Final machine welded areas to specifications in accordance with the applicable shaft detail drawing.
I. Machine/handwork as necessary not to exceed 32 man-hours and $500 in material to remove defects on other shaft surfaces in accordance with
S9243-AW-TRS-011/SHAFT.
J. Inspect shaft as required by S9243-AW-TRS-011/SHAFT prior to sleeve installation including MT, UT, hardness readings, dimensional, and concentricity.
K. Purchase sleeves and backing strips. Ensure sleeves are stress relieved at 875 (+/- 25) degrees F and satisfactory RT is performed and approved by the local DCMA QAR at sleeve manufacturer.
L. Prep machine and inspect sleeves prior to installation.
M. Install sleeves and weld in place in accordance with S9243-AW-TRS-
011/SHAFT including the use of strain gages to monitor stress during welding.
N. Final machine sleeves in accordance with the applicable shaft detail drawing specifications and inspect including dimensions, concentricity and PT.
O. Enclosures (1) and (2) shall be completed and submitted with the final repair report.
P. Skim cut the FWD and AFT flange vertical mating and non-mating faces within tolerances and surface finishes to remove defects maintaining tolerance in way of aligning spigot fits and counter bores.
Q. Shot peen FWD and AFT flange fillet if weld repaired – or –if fillet temperature exceeds 475 degrees F during weld repair and subsequent stress relief of adjacent areas – or – if there is no evidence of prior shot peen. Peening shall be in accordance with MIL-S-13165C and/or MIL-R-81841. When peening is conducted in accordance with MIL-S- 13165C, the peening gun shall not be manually manipulated, but shall comply with the requirements stated in Paragraph 3.2.1 of subject document. Peening shot media shall conform to SAE AMS 2431/1E. The peening intensity shall be 0.012 to 0.016 A with a nominal shot size of
0.033 inches. The peening shall include the entire curvature of the fillet and the entire circumference, thereby achieving 100% coverage.
R. Brush hone the shaft bore as necessary.
S. The shaft body area between the FWD and AFT sleeves shall receive the glass-reinforced plastic (GRP) covering system as detailed in MIL-STD- 2199 Change Notice 1 dtd. 05 October 1993 with the exception that surface prep shall be via abrasive blasting only. Chemical (solvent) cleaning is not an allowable/acceptable method of surface prep.
T. The shaft journal area FWD of the FWD coupling cover sleeve, including the flange fillet, non-mating face, and O.D., shall be preserved/painted as detailed in Enclosure (3). Do not paint the mating face, bolt holes, or bolt hole washer faces. If Nova-Plate primer is not able to be applied due to availability or procedure development, Mare Island paint (MIL-DTL-24441/29B, Type 4) or Euronavy paint, as currently approved for use on CG-47 and DDG-51 Classes, shall be applied in accordance with OEM application procedures.
U. If Nova-Plate primer is applied, once primer has cured, perform low voltage discontinuity (holiday) test in accordance with ASTM D5162-08, using low voltage wet sponge test equipment.
V. Die stamp FWD end of shaft to note NSN, UT inspection, stress relieve temperature, and shot peening after repairs and inspection.
W. Final inspect for customer acceptance.
X. Package and Preserve in accordance with MIL-DTL-2845E and International
Standards for Phytosanitary Measures (ISPM) No. 15, "Regulation of Wood Packaging Material in International Trade."
Y. Upon approval of all CDRLs, shaft repair vendor shall arrange for transportation via a MIL-DTL-2845E compliant trailer (including required permits) to the closest of the following two locations:
a) DODAAC SW3115
DEFENSE DISTRIBUTION DEPOT (DDBC-EOR)
YERMO ANNEX, BLDG 401 (WEST END)
MARINE CORPS LOGISTICS BASE
BARSTOW, CA 92311-5049
M/F: NAVSEA CSP-WEST
ATTN: EARNEST GARRETT/MATREP
PH: 760-577-6940
b) DODAAC SW3126
DLA DISTRIBUTION CHEATHAM
CHEATHAM ANNEX
1 C STREET
WILLIAMSBURG, VA 23185
M/F: NAVSEA CSP-EAST
ATTN: NAVSUP WSS MATREP (John Leonard)
PH: 757-887-7113
*NOTE: While skim cutting/hand working the shaft body between the FWD and
AFT sleeve areas, remove the minimum amount of metal required to clear/blend existing defects while maintaining design diameter.
NOTE: Measurement stations B and D are not required for sleeves less than 36” in length.
NOTE: At least 24 hours before taking measurements, place the sleeve in close proximity to the shaft to ensure that both are at the same temperature and that both shaft and sleeve are between 60°F - 80°F.
Tshaft __________°F Tsleeve __________°F
Measure and record the shaft outside diameter in way of the sleeve (ODshaft).
AFT End B C D FWD End 0°-180° 45°-225° 90°-270° 135°- 315°
AVERAGE
Measure and record the sleeve inside diameter prior to splitting into halves (IDsleeve). The average values should be within +/- 0.003” of the corresponding shaft OD average values at each station.
0°-180° 45°-225° 90°-270° 135°- 315°
Measure and record the average sleeve outside diameter (ODsleeve) in the rough turned condition prior to splitting into halves.
ODsleeve = _________
Signature __________________________________ Date
Machining of the weld joints shall be per DWG 803-2145807 (see excerpt above), with the following exceptions:
• To prevent weld burn-thru, as well as excessively thin welds in the way of GRP end preps, the backing strip thickness shall be 0.188” +0.000/-0.005”.
• To improve weld shrinkage, the 50° bevel angle in the weld joint detail (Detail 61-B) shall be changed to 60°.
• To ensure watertight integrity at the sleeve ends, the backing strip widths will be increased for the first 6” under the ends of the finished sleeve so as to reduce the fit-up gap to 0.019” +/- 0.003”, which will result in a nominal shrink fit at the sleeve ends of 0.012”. For the remainder of the joint between the 6” ends, the fit-up gap shall be 0.022” +/-0.003”, which will result in a nominal shrink fit of 0.014”. The transition in backing strip width shall have a generous corner break so as not to create a sharp step.
Measure and record the widths of the backing strips (Wstrip) and that of the respective slots (Wslot) prior to splitting the sleeve into halves.
WstripA
WslotA WstripB WslotB
Signature __________________________________ Date
During welded installation of the sleeves, strain gages shall be installed to monitor the stress due to weld shrinkage as follows:
• A welding procedure prepared by a welding engineer and approved by NAVSEA is required.
• Strain gages shall be located along the weld joints (both sides) and 90° from the weld joints along the length of the sleeve. The distance between the gages and the weld joints shall be sufficient to prevent gage damage, de-bonding, or false readings.
• All strain gages will measure uniaxial strain around the circumference of the sleeve, so as to indicate the measured shrink fit.
• The prior joint modifications require placement of strain gages within 3” of the sleeve ends and additional gages in between shall coincide with the dimensional measurement stations along the length of the sleeve to monitor the stress in areas of design and modified fit-up.
• The sleeves shall be accurately aligned and securely clamped to the shaft and appropriately grounded prior to welding. In no case shall the sleeve be welded to the shaft.
• Peening of welds shall only be accomplished as required to remove excessive stress, while optimizing residual stress within the allowable limits. Repair activities are cautioned against premature peening of welds in an effort to limit the in-process stress below the 16 ksi limit, as this typically leads to insufficient shrink fit in the final condition. Based on a modulus of elasticity of 21 x 106 psi, the threshold strain limit after final welding would be 762 x 10-6 in/in.
• Every weld layer will be subject to a liquid dye penetrant (PT) inspection with Class 2 acceptance criteria per MIL-STD-2035A(SH) in lieu of the RT requirements for M-1 Category A in S9074-AR- GIB-010/278. The final PT shall also use Class 2 acceptance criteria.
• After welding there shall be no gap between the sleeve groove and backing strip. If gaps remain, or if any of the strain gages indicate a shrink fit of less than 0.012”, a completed copy of this document shall be submitted for engineering evaluation prior to machining the sleeve.
Measure and record the final strain [e] values indicated by the strain gages.
e
After final welding, but prior to removing the runoff portion of the backing strips, measure and record the final widths of the backing strip by measuring the protruding portion of the backing strips immediately adjacent to the sleeve end at each end of each weld joint using dial calipers.
AFT End FWD End (WstripA)final (WstripB)final
Signature __________________________________ Date ________________
Prior to machining the sleeve, measure and record any gaps remaining after final installation, where GAPfinal for a particular sleeve end is the sum total of combined gaps remaining in both joints at that end, as determined by inspection with wire, cut-down feeler gages, etc.
GAPfinal
Upon completion of welding, and to ensure watertight integrity, the ends of the weld joints shall be ground after final machining to remove metal burrs that may have been forced into gaps remaining around the ends of the backing strips. Grinding is to be a minimum of 0.03” deep and is to include the outline of the backing strip to the maximum extent possible without damaging the shaft surface.
Incidental damage to the shaft must be evaluated for acceptability, faired smooth, and be subject to either MT or PT per NAVSEA Technical Publication T9074-AS-GIB-010/271.
Following grinding, repeat measurements and record any gaps remaining after final machining, where GAPmachined for a particular sleeve end is the sum total of combined gaps remaining in both joints at that end, as determined by inspection with wire, cut-down feeler gages, etc.
GAPmachined
Following grinding, the ends of the weld joints and the entire periphery of the sleeve ends and backing strip ends shall be sealed with a wicking grade thread sealant (Loctite 290 or equivalent).
NOTE: Measurement stations B and D are not required for sleeves less than 36” in length.
NOTE: At least 24 hours before taking measurements, place the sleeve in close proximity to the shaft to ensure that both are at the same temperature and that both shaft and sleeve are between 60°F - 80°F.
Tshaft __________°F Tsleeve __________°F
Measure and record the shaft outside diameter in way of the sleeve (ODshaft).
AFT End B C D FWD End 0°-180° 45°-225° 90°-270° 135°-315°
Measure and record the sleeve inside diameter prior to splitting into halves (IDsleeve). The average values should be within +/- 0.003” of the corresponding shaft OD average values at each station.
AFT End B C D FWD End 0°-180° 45°-225° 90°-270°
Measure and record the average sleeve outside diameter (ODsleeve) in the rough turned condition prior to splitting into halves.
Signature __________________________________ Date ______________
Machining of the weld joints shall be per DWG 803-2145807 (see excerpt above), with the following exceptions:
• To prevent weld burn-thru, as well as excessively thin welds in the way of GRP end preps, the backing strip thickness shall be 0.188” +0.000/-0.005”.
• To improve weld shrinkage, the 50° bevel angle in the weld joint detail (Detail 61-B) shall be changed to 60°.
• To ensure watertight integrity at the sleeve ends, the backing strip widths will be increased for the first 6” under the ends of the finished sleeve so as to reduce the fit-up gap to 0.019” +/- 0.003”, which will result in a nominal shrink fit at the sleeve ends of 0.012”. For the remainder of the joint between the 6” ends, the fit-up gap shall be 0.022” +/-0.003”, which will result in a nominal shrink fit of 0.014”. The transition in backing strip width shall have a generous corner break so as not to create a sharp step.
Measure and record the widths of the backing strips (Wstrip) and that of the respective slots (Wslot) prior to splitting the sleeve into halves.
AFT End B C D FWD End WstripA WslotA
During welded installation of the sleeves, strain gages shall be installed to monitor the stress due to weld shrinkage as follows:
• A welding procedure prepared by a welding engineer and approved by NAVSEA is required.
• Strain gages shall be located along the weld joints (both sides) and 90° from the weld joints along the length of the sleeve. The distance between the gages and the weld joints shall be sufficient to prevent gage damage, de-bonding, or false readings.
• All strain gages will measure uniaxial strain around the circumference of the sleeve, so as to indicate the measured shrink fit.
• The prior joint modifications require placement of strain gages within 3” of the sleeve ends and additional gages in between shall coincide with the dimensional measurement stations along the length of the sleeve to monitor the stress in areas of design and modified fit-up.
• The sleeves shall be accurately aligned and securely clamped to the shaft and appropriately grounded prior to welding. In no case shall the sleeve be welded to the shaft.
• Peening of welds shall only be accomplished as required to remove excessive stress, while optimizing residual stress within the allowable limits. Repair activities are cautioned against premature peening of welds in an effort to limit the in-process stress below the 16 ksi limit, as this typically leads to insufficient shrink fit in the final condition. Based on a modulus of elasticity of 21 x 106 psi, the threshold strain limit after final welding would be 762 x 10-6 in/in.
• Every weld layer will be subject to a liquid dye penetrant (PT) inspection with Class 2 acceptance criteria per MIL-STD-2035A(SH) in lieu of the RT requirements for M-1 Category A in S9074-AR- GIB-010/278. The final PT shall also use Class 2 acceptance criteria.
• After welding there shall be no gap between the sleeve groove and backing strip. If gaps remain, or if any of the strain gages indicate a shrink fit of less than 0.012”, a completed copy of this document shall be submitted for engineering evaluation prior to machining the sleeve.
After final welding, but prior to removing the runoff portion of the backing strips, measure and record immediately adjacent to the sleeve end at each end of each weld joint using dial calipers.
GAPfinal for a particular sleeve end is the sum total of combined gaps remaining in both joints at that end, as determined by inspection with wire, cut-down feeler gages, etc.
around the ends of the backing strips. Grinding is to be a minimum of 0.03” deep and is to include the outline of the backing strip to the maximum extent possible without damaging the shaft surface.
Incidental damage to the shaft must be evaluated for acceptability, faired smooth, and be subject to either MT or PT per NAVSEA Technical Publication T9074-AS-GIB-010/271.
Following grinding, repeat measurements and record any gaps remaining after final machining, where GAPmachined for a particular sleeve end is the sum total of combined gaps remaining in both joints at that end, as determined by inspection with wire, cut-down feeler gages, etc.
Following grinding, the ends of the weld joints and the entire periphery of the sleeve ends and backing
1. REFERENCES:
1.1 NSTM Chapter 631, Preservation of Ship's In Service
1.2 MSDS and manufacturer's ASTM F 718 sheets, Shipbuilders and Marine Paints and
Coating Product/Procedure Data Sheet for (Applicable QPL) Coating System Being Applied.
1.3 ASTM D4417, Method C, Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel
1.4 NAVSEA Standard Item 009-32
1.5 SSPC-VIS-1-89 Visual Standard for Abrasive Blast Cleaned Steel
1.6 SSPC-VIS-4 (I) Visual Reference Photographs for Steel Cleaned by Water Jetting
2. GENERAL REQUIREMENTS:
2.1 SAFETY: All work shall be accomplished in accordance with applicable shipyard safety instructions as well as applicable federal and state safety regulations.
2.2 QUALITY ASSURANCE REQUIREMENTS:
2.2.1 Surface preparation for high solids paints shall be accomplished by blasters qualified to the requirements in Reference 1.4, Section 3.9.
2.2.2 Application of high solids paints shall be performed by painters qualified to the requirements in Reference 1.4, Section 3.9.
2.2.3 Key checkpoints and final inspections shall be signed off by either Paint Shop Supervisors, or QA Inspectors independent of the Paint Shop. As a minimum, these individuals shall be certified and maintain certification to the National Association of Corrosion Engineers (NACE) Level I or the NAVSEA Basic Paint Inspector Course (NBPI).
2.3 ENVIRONMENTAL CONDITIONS:
2.3.1 Maintain environmental conditions as required by this procedure.
2.3.2 Surface temperature during blasting and mechanical surface preparation shall be at least 35°F and at least 5°F above the dew point.
2.3.3 Surface and ambient air temperatures during paint application and curing shall be within 50°F and 110°F. Surface temperature shall be at least 5°F above the dew point temperature.
2.3.4 Relative humidity during surface preparation, painting and curing shall be 85% maximum.
2.3.5 If environmental conditions are found to be outside the allowable ranges, stop work, reestablish conditions to be within the allowable ranges, inspect the work area for defects that may have occurred due to the out-of-spec condition(s), repair any defects faun and continue the process from the point where work was stopped.
2.4 PRE-SURFACE PREPARATION:
2.4.1 For surfaces that have been previously immersed in or wetted by sea water, prior to surface preparation perform a 3,000-psi minimum fresh water wash down. After the 3,000 psi fresh water wash down, continue to wash the area to be painted with fresh (city) water until a sheeting action is observed using approximately 40-50 psi water pressure. Contaminated areas as identified by the absence of sheeting action (i.e. water beading) shall be washed using clean lint free rags wetted with IPA or PF-145HP to remove organic surface contaminants. The solvent shall be allowed 60 minutes to flash off.
2.4.2 CHECKPOINT (SP-1 Cleanliness Prior to Preparation Inspection):
2.4.2.1 Verify that a freshwater wash down was performed as specified in Section 5.2.
Sign Table 3 after completion of fresh water wash down.
Perform a visual inspection to verify all surfaces to be blasted are free of hydrocarbons, and other contaminants such as sea salts, loose rust, mud, and marine growth, which could become imbedded in the surface to be prepared.
2.4.2.3 The SP-1 surface condition shall be met prior to abrasive blasting or mechanical surface preparation. Sign Table 3 when pre-surface preparation inspection is satisfactory.
2.4.2.4 Have the Abrasive Blasting Prerequisite List shown on Appendix A completed and signed by the appropriate departments.
2.4.3 Where doubt exists as to the adequacy of surface cleanliness prior to surface preparation, inspect the surface using a UV light (approx. 60 A) to detect hydrocarbons on the surface. The ultraviolet light will not allow the proper detection of hydrocarbons on the surface if the surface being inspected is exposed to day or artificial light. For proper UV light hydrocarbon detection, lights must be off for interior spaces, and the inspection must be conducted during darkness for surfaces exposed to sunlight. Take appropriate safety measures to prevent worker hazards in the darkened space. When hydrocarbons are present, the hydrocarbons will fluoresce as bright green, lime green, or blue/violet on the surface.
CAUTION
UV lights that contain mercury are prohibited from use in mercury exclusion areas.
2.4.4 To remove detected contaminants or hydrocarbons, perform a solvent wipe using clean lint free rags wetted with IPA or PF-145HP on affected areas to achieve a SP-1 surface condition.
2.4.5 If contaminants or hydrocarbons are detected on the surface after attempting to solvent spot repair, de-grease the surface again.
3. SURFACE PREPARATION:
3.1 Monitor environmental conditions during surface preparation operations to ensure they meet the requirements in paragraphs herein. All blasted surfaces shall meet the surface condition of "near white metal". "Near white metal" is defined as a surface from which all oil, grease, dirt, mill scale, rust, paint, hull fairing compound, and other foreign material have been removed except for very slight streaks or discolorations. The blasted steel surface shall have an appearance similar to or better than SNAME Bulletin #4-9, Figure 12, or Society for Protective Coatings: SSPC, surface preparation standard SSPC SP-10.
3.2 The average surface profile shall be 2.5 to 3.5 mils, with no profiles less than 2 mils or greater than 4 mils as measured using a Testex Inc. Replica Tape/Dial Indicator Profile measuring system (ASTM D4417, method C).
3.3 Blasted surfaces shall be blown down and/or vacuumed to remove all blasting residue prior to painting. Only dry, oil free compressed air shall be used for blasting and blowing down. Spent abrasive and paint particles shall be disposed of according to the latest waste disposal regulations of the federal, state and local governments.
3.4 CHECKPOINT (Surface Preparation):
3.4.1 Check the surface for compliance with the applicable surface preparation standard (SP-10). The record shall show the extent of the inspection and detailed results. Visual aids provided in Ref. 2.d or 2.e may be used to ensure quality standards are met.
3.4.2 Check and record the surface profile of abrasive blasted surfaces using TESTEX PRESS-0-FILM replica tape (X-course).
3.4.3 Perform surface cleanliness tests (tape test) in accordance with ISO 8502-3.
4. PAINTING REQUIREMENTS:
4.1 CHECKPOINT (Shelf life): Verify shelf life of material has not expired. Recording not required.
4.2 Verify that application of the first spray coat is complete within 24 hours of surface preparation. If more than 24 hours has passed, request QA to re-inspect unpainted areas to verify that the surface preparation is still satisfactory.
4.3 Apply the Sherwin Williams Nova plate UHS Primer to the prepared surfaces at 14-18 mils DFT to the shaft.
4.4 The SYSTEM DFTs shown above are target thicknesses. The overall average of the dry film thickness measurements shall not be less than the low end of the range for the System DFT shown above and may be up to 1.25 times the maximum thickness shown for the range.
4.5 Do not take dry film thickness measurements on runs, drips, sags or puddles, or (when a stripe coat is applied) directly on striped welds, striped edges, etc.
Note that depending on configuration, a 'spray-stripe' application may extend onto flat surfaces further than a typical brush applied stripe coat. In this case the stripe coat thickness may be captured while measuring total system DFT.
LSD 41 CLASS PROPELLER SHAFT
NSN 2S 2010-01-141-3639 P2
Repair Statement of Work (SOW)
4.6 During application, take random wet film thickness (WFT) measurements to ensure the specified dry film thickness (DFT) is achieved.
4.7 Comply with the paint manufacturer's directions for cure time between coats based on the environmental conditions in the tank or space.
4.8 Ensure paint is dry prior to all paint related checkpoints. Dry is defined as hard to moderate fingernail pressure and to the degree that walking on the coating will not cause damage.
4.9 The minimum and maximum allowable paint thicknesses are 14 and 18 mils, respectively. If paint thickness fails to meet the minimum thickness requirements, apply an additional coat or coats of paint to the deficient areas and re-inspect.
4.10 The job site temperature shall comply within the minimum and maximum range allowed by the paint manufacturer. The use of plural component spray equipment is required for application of the single coat primer and stripe (if applicable) coat of paint. Brushing is allowed for areas that cannot be sprayed.
4.11 Prior to loading each component (resin and hardener) into the plural component sprayer, mix each component thoroughly for a minimum of 5 minutes using a power mixer, in their individual containers to disperse pigments and assure homogeneity.
4.11.1 For manually mixing paints, proportion paints with graduated cups in accordance with the manufacturer's product data sheets. Sign-off on Table 4 for initial application or Table 8 for touch-up work. Do not re-use the graduated cups because residue left in the cups may cause an improper mix ratio. Combine and thoroughly mix the components together using a metal spatula for a minimum of 3 minutes for small volumes of paint, measured with the 4 oz. graduated cups, and a minimum of 5 minutes for large volumes of paint, measured with the 17 oz.
graduated cups, before use.
4.11.2 For plural component spray equipment (for example, the Graco Xtreme equipment), pour the thoroughly mixed individual components into their respective hoppers. Perform a pump ratio check both prior to application and after completion of the spraying operation. Do not proceed with the application if the pre-job mix ratio is not in accordance with the coating manufacturer's specified mix ratio.
WARNING
NEVER add thinner to any high solids paint.
5. SINGLE COAT APPLICATION:
5.1 Apply anticorrosive paint specified in Reference 1.2. During application, be prepared to immediately brush out any runs, drips, sags or puddles to the extent possible. After measuring for wet film thickness, brush out any areas where the paint did not level completely.
5.2 CHECKPOINT (Single Coat):
5.2.1 (Holiday Inspection): Perform a visual inspection of primer for holidays.
5.2.2 (Dry Film Thickness): Perform dry film thickness measurements and record. Verify compliance with Reference 1.2.
6. STRIPE COAT APPLICATION (if applicable):
6.1 Apply stripe coat specified in Reference 1.2 to: welds, edges, bases of studs and other difficult to spray areas. The stripe coat may be applied by spray equipment or by brush. During application, be prepared to immediately brush out any runs, drips, sags or puddles to the extent possible.
6.2 CHECKPOINT (Stripe Coat):
6.2.1 (Holiday Inspection): When applied, perform a visual inspection of stripe coat for proper paint and complete coverage.
6.2.2 (Dry Film Thickness): Perform dry film thickness measurements and record. Verify
DATA
CDRLs A001, A004, A005, A006, A008, A009, A010, A011, A012 and A014 apply.
Required Delivery Date: 1 APRIL 2019
SECTION C PART 2
STATEMENT OF WORK
Enclosures:
(3) Supplementary Split Sleeve Data and Instructions (FWD Sleeve)
(4) Supplementary Split Sleeve Data and Instructions (AFT Sleeve)
(5) Application of Sherwin Williams’ Nova-Plate UHS Primer High Solids Epoxy Paint
Z. Complete Pre-Repair in accordance with S9243-AW-TRS-011/SHAFT.
AA. Prep for weld repair by machining as necessary up to 20 linear feet (entire shaft circumference).
BB. NDT all prepped areas prior to welding in accordance with NAVSEA Tech. Pub. S9074-AR-
GIB-010/278 and/or NAVSEA Tech. Pub. T9074-AS-GIB-010/271 as required by MIL-STD- 2191.
CC. Weld repair all prepped areas in accordance with NAVSEA Tech. Pub. S9074-AQ-GIB- 010/248 as required by MIL-STD-2191 up to 1 pass of 20 linear feet (entire shaft circumference) and up to an additional 6 linear feet (entire shaft circumference) of multilayer passes.
DD. NDT weld repair areas, in accordance with NAVSEA Tech. Pub. S9074-AR-GIB-010/278 and/or NAVSEA Tech. Pub. T9074-AS-GIB-010/271 as required by MIL-STD-2191. Additional NDT will be required for multiple weld passes.
EE. Stress relieve all welded areas in accordance with MIL-STD-2191.
FF. Cold roll AFT sleeve fit area in accordance with MIL-STD-2191 if weld repaired or if temperature exceeds 475 degree F during weld repair and subsequent stress relief of adjacent areas.
GG. Recheck concentricity after stress relieving; straighten if necessary in accordance with
MIL-STD-2191.
HH. Final machine welded areas to design specifications in accordance with the applicable shaft detail drawing.
II. Machine/handwork as necessary not to exceed 32 man-hours and $500 in material to remove defects on other shaft surfaces in accordance with S9243-AW-TRS-011/SHAFT.
JJ. Inspect shaft as required by S9243-AW-TRS-011/SHAFT prior to sleeve installation including MT, UT, hardness readings, dimensional, and concentricity.
KK. Purchase sleeves and backing strips. Ensure sleeves are stress relieved at 875 (+/- 25) degrees F and satisfactory RT is performed and approved by the local DCMA QAR at sleeve manufacturer.
LL. Prep machine and inspect sleeves prior to installation.
MM. Install sleeves and weld in place in accordance with S9243-AW-TRS-011/SHAFT including the use of strain gages to monitor stress during welding.
NN. Final machine sleeves in accordance with the applicable shaft detail drawing and inspect including dimensions, concentricity and PT.
OO. Enclosures (1) and (2) shall be completed and submitted with the final repair report.
PP. Skim cut the FWD flange vertical mating and non-mating faces within tolerances and surface finishes to remove defects maintaining tolerance in way of aligning spigot fits and counter bores.
QQ. Shot peen FWD flange fillet if weld repaired – or –if fillet temperature exceeds 475 degrees F during weld repair and subsequent stress relief of adjacent areas – or – if there is no evidence of prior shot peen. Peening shall be in accordance with MIL-S-13165C and/or MIL-R-81841. When peening is conducted in accordance with MIL-S-13165C, the peening gun shall not be manually manipulated, but shall comply with the requirements stated in Paragraph 3.2.1 of subject document. Peening shot media shall conform to SAE AMS 2431/1E. The peening intensity shall be 0.012 to 0.016 A with a nominal shot size of
0.033 inches. The peening shall include the entire curvature of the fillet and the entire circumference, thereby achieving 100% coverage.
RR. Shot peen AFT flange fillet if weld repaired – or –if fillet temperature exceeds 475 degrees F during weld repair and subsequent stress relief of adjacent areas – or – if there is no evidence of prior shot peen. Peening shall be in accordance with MIL-S-13165C. The peening gun shall not be manually manipulated, but shall comply with the requirements stated in Paragraph 3.2.1 of subject document. Peening shot media shall conform to SAE AMS 2431/7. The peening intensity shall be 0.008 to 0.012 A with a nominal shot size of
0.033 inches. The peening shall include the entire curvature of the fillet and the entire circumference, thereby achieving 100% coverage.
SS. Brush hone the shaft bore as necessary.
TT. Restore AFT flange bolt and dowel pin holes to design specifications in accordance with the applicable shaft detail drawing.
UU. The shaft body area between the FWD and AFT sleeves shall receive the glass-reinforced plastic (GRP) covering system as detailed in MIL-STD-2199 Change Notice 1 dtd. 05 October 1993 with the exception that surface prep shall be via abrasive blasting only.
Chemical (solvent) cleaning is not an allowable/acceptable method of surface prep.
VV. The shaft journal area FWD of the FWD coupling cover sleeve, including the flange fillet, non-mating face, and O.D., shall be preserved/painted as detailed in Enclosure (3). Do not paint the mating face, bolt holes, or bolt hole washer faces. If Nova-Plate primer is not able to be applied due to availability or procedure development, Mare Island paint (MIL-DTL-24441/29B, Type 4) or Euronavy paint, as currently approved for use on CG-47 and DDG-51 Classes, shall be applied in accordance with OEM application procedures.
WW. If Nova-Plate primer is applied, once primer has cured, perform low voltage discontinuity (holiday) test in accordance with ASTM D5162-08, using low voltage wet sponge test equipment.
XX. Die stamp FWD end of shaft to note NSN, UT inspection, stress relieve temperature, and shot peening after repairs and inspection.
YY. Final inspect for customer acceptance.
ZZ. Package and Preserve in accordance with MIL-DTL-2845E and International Standards for
Phytosanitary Measures (ISPM) No. 15, "Regulation of Wood Packaging Material in International Trade."
AAA. Upon approval of all CDRLs, shaft repair vendor shall arrange for transportation via a MIL-DTL-2845E compliant trailer (including required permits) to the closest of the following two locations:
a) DODAAC SW3126
DLA DISTRIBUTION CHEATHAM
CHEATHAM ANNEX
1 C STREET
WILLIAMSBURG, VA 23185
M/F: NAVSEA CSP-EAST
ATTN: NAVSUP WSS MATREP (John Leonard)
PH: 757-887-7113
b) DODAAC SW3215
DEFENSE DISTRIBUTION DEPOT (DDBC-EOR)
YERMO ANNEX, BLDG 401 (WEST END)
MARINE CORPS LOGISTICS BASE
BARSTOW, CA 92311-5049
M/F: NAVSEA CSP-WEST
ATTN: EARNEST GARRETT/MATREP
PH: 760-577-6940
*NOTE: While skim cutting/hand working the shaft body between the FWD and AFT sleeve areas, remove the minimum amount of metal required to clear/blend existing defects while maintaining design diameter.
Enclosure (1)
SUPPLEMENTARY SPLIT SLEEVE DATA AND INSTRUCTIONS
(LSD-41 CLASS PROPELLER SHAFT – FWD SLEEVE)
Shaft S/N __________________________
NOTE: At least 24 hours before taking measurements, place the sleeve in close proximity to the shaft to ensure that both are at the same temperature and that both shaft and sleeve are between 60°F - 80°F.
Tshaft __________°F Tsleeve __________°F
Measure and record the shaft outside diameter in way of the sleeve (ODshaft).
AFT End B C D FWD End 0°-180° 45°-225° 90°-270°
Measure and record the sleeve inside diameter prior to splitting into halves (IDsleeve). The average values
AFT End B C D FWD End 0°-180° 45°-225° 90°-270°
Measure and record the average sleeve outside diameter (ODsleeve) in the rough turned condition prior
• To prevent weld burn-thru, as well as excessively thin welds in the way of GRP end preps, the backing strip thickness shall be 0.188” +0.000/-0.005”.
• To improve weld shrinkage, the 50° bevel angle in the weld joint detail (Detail 61-B) shall be changed to 60°.
• To ensure watertight integrity at the sleeve ends, the backing strip widths will be increased for the first 6” under the ends of the finished sleeve so as to reduce the fit-up gap to 0.019” +/- 0.003”, which will result in a nominal shrink fit at the sleeve ends of 0.012”. For the remainder of the joint between the 6” ends, the fit-up gap shall be 0.022” +/-0.003”, which will result in a
Measure and record the widths of the backing strips (Wstrip) and that of the respective slots (Wslot) prior
AFT End B C D FWD End WstripA WslotA
During welded installation of the sleeves, strain gages shall be installed to monitor the stress due to
• A welding procedure prepared by a welding engineer and approved by NAVSEA is required.
• Strain gages shall be located along the weld joints (both sides) and 90° from the weld joints along the length of the sleeve. The distance between the gages and the weld joints shall be sufficient to prevent gage damage, de-bonding, or false readings.
• All strain gages will measure uniaxial strain around the circumference of the sleeve, so as to indicate the measured shrink fit.
• The prior joint modifications require placement of strain gages within 3” of the sleeve ends and additional gages in between shall coincide with the dimensional measurement stations along the length of the sleeve to monitor the stress in areas of design and modified fit-up.
• The sleeves shall be accurately aligned and securely clamped to the shaft and appropriately grounded prior to welding. In no case shall the sleeve be welded to the shaft.
• Peening of welds shall only be accomplished as required to remove excessive stress, while optimizing residual stress within the allowable limits. Repair activities are cautioned against premature peening of welds in an effort to limit the in-process stress below the 16 ksi limit, as this typically leads to insufficient shrink fit in the final condition. Based on a modulus of elasticity of 21 x 106 psi, the threshold strain limit after final welding would be 762 x 10-6 in/in.
• Every weld layer will be subject to a liquid dye penetrant (PT) inspection with Class 2 acceptance criteria per MIL-STD-2035A(SH) in lieu of the RT requirements for M-1 Category A in S9074-AR- GIB-010/278. The final PT shall also use Class 2 acceptance criteria.
• After welding there shall be no gap between the sleeve groove and backing strip. If gaps
After final welding, but prior to removing the runoff portion of the backing strips, measure and record the final widths of the backing strip by measuring the protruding portion of the backing strips immediately adjacent to the sleeve end at each end of each weld joint using dial calipers.
AFT End FWD End
Prior to machining the sleeve, measure and record any gaps remaining after final installation, where GAPfinal for a particular sleeve end is the sum total of combined gaps remaining in both joints at that end, as determined by inspection with wire, cut-down feeler gages, etc.
Upon completion of welding, and to ensure watertight integrity, the ends of the weld joints shall be ground after final machining to remove metal burrs that may have been forced into gaps remaining around the ends of the backing strips.
Grinding is to be a minimum of 0.03” deep and is to include the outline of the backing strip to the maximum extent possible without damaging the shaft surface. Incidental damage to the shaft must be evaluated for acceptability, faired smooth, and be subject to either MT or PT per NAVSEA Technical Publication T9074-AS-GIB-010/271.
Following grinding, repeat measurements and record any gaps remaining after final machining, where GAPmachined for a particular sleeve end is the sum total of combined gaps remaining in both joints at that end, as determined by inspection with wire, cut-down feeler gages, etc.
Following grinding, the ends of the weld joints and the entire periphery of the sleeve ends and backing strip ends shall be sealed with a wicking grade thread sealant (Loctite 290 or equivalent).
Enclosure (2)
(LSD-41 CLASS PROPELLER SHAFT – AFT SLEEVE)
NOTE: At least 24 hours before taking measurements, place the sleeve in close proximity to the shaft to ensure that both are at the same temperature and that both shaft and sleeve are between 60°F - 80°F.
Tshaft __________°F Tsleeve __________°F
Measure and record the shaft outside diameter in way of the sleeve (ODshaft).
AFT End B C D FWD End 0°-180° 45°-225° 90°-270°
Measure and record the sleeve inside diameter prior to splitting into halves (IDsleeve). The average values
AFT End B C D FWD End 0°-180° 45°-225° 90°-270°
Measure and record the average sleeve outside diameter (ODsleeve) in the rough turned condition prior
• To prevent weld burn-thru, as well as excessively thin welds in the way of GRP end preps, the backing strip thickness shall be 0.188” +0.000/-0.005”.
• To improve weld shrinkage, the 50° bevel angle in the weld joint detail (Detail 61-B) shall be changed to 60°.
• To ensure watertight integrity at the sleeve ends, the backing strip widths will be increased for the first 6” under the ends of the finished sleeve so as to reduce the fit-up gap to 0.019” +/- 0.003”, which will result in a nominal shrink fit at the sleeve ends of 0.012”. For the remainder of the joint between the 6” ends, the fit-up gap shall be 0.022” +/-0.003”, which will result in a
Measure and record the widths of the backing strips (Wstrip) and that of the respective slots (Wslot) prior
AFT End B C D FWD End WstripA…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.