This is a Justification and Approval (J&A) document for use of other than full and open competition for a sole-source contract award.

The Department of the Navy, Portfolio Acquisition Executive Maritime, seeks to award a sole-source contract to Vigor Marine, LLC (1801 16th Ave SW, Seattle, WA 98134) for the Fiscal Year 2027 Depot Modernization Period (DMP) availability for the USS GRIDLEY (DDG 101). The scope of work includes repair, maintenance, and modernization requirements scheduled to complete between March 2027 and June 2029, encompassing installation of the AN/SLQ-32(V)7 Surface Electronic Warfare Improvement Program Block III, legacy combat systems and AEGIS modernization alterations, and mid-life maintenance and repair package. The procurement includes all labor, supervision, facilities, equipment, production, testing, and quality assurance necessary to accomplish the DMP. The estimated total procurement value is redacted; estimated funding comprises a to-be-determined split between Operations and Maintenance (O&MN) and Operations (OPN). The solicitation was initially issued on May 5, 2026, on a coast-wide competitive basis but is being converted to a sole-source award based on industrial mobilization requirements under 10 U.S.C. 3204(a)(3). Vigor is the only private shipyard in the Seattle/Everett, Washington homeport area with NAVSEA-certified dry dock capability and access required for DDG 51 class destroyer docking availabilities and is deemed critical to maintain core workforce capacity and industrial mobilization surge capability in the Pacific Northwest amid Operation Epic Fury. The contracting officer has determined anticipated costs to be fair and reasonable. PAE Maritime committed to conducting competitive acquisitions for future surface ship maintenance, modernization, and repair availabilities to the maximum extent possible.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

J&A Number: 43,210 began. Based on the uncertainties of wartime, it is critical to ensure that Vigor

On 20 Aug 2026, ability to

Based on the current industrial base environment, the need to execute the USS GRIDLEY DMP as an industrial mobilization award is required to maintain critical docking and core workforce capacity in the Pacific Northwest. Should Vigor not be awarded the USS

GRIDLEY DMP,

Beginning in February 2027, a contract award of USS GRIDLEY out of its homeport would drive

Without the award of the USS GRIDLEY to Vigor, the next available competitive docking availability homeported in the Pacific Northwest that Vigor can compete for is

As a result, PAE Maritime expects that Vigor not receiving the USS GRIDLEY DMP would have significant adverse impacts to the only private shipyard with access to a NAVSEA certified dry dock (which is required to complete DDG 51 class destroyer docking availabilities) in the Everett/Seattle homeport and its ability to mobilize in the event of a national emergency. The ability to capability to ensure immediate readiness that does not require moving ships and sailors. It supports the strategic laydown decisions for homeport vessels in the region.

Therefore, the Navy intends to award a sole source contract to Vigor to complete the USS GRIDLEY DMP. This action ensures that Vigor maintains its critical skills necessary to provide surface combatant maintenance, modernization and repair

J&A Number: 43,210 surge and industrial mobilization requirements in the event of a national emergency, especially in light of the ongoing active conflict of Operation Epic Fury.

6. Description of Efforts Made to Solicit Offers from as Many

Offerors as Practicable

A Sources Sought Synopsis was issued on 14 April 2026. The solicitation was initially competed on a coast wide basis. For the reasons cited above, PAE Maritime determined that Vigor Marine needs the workload from USS GRIDLEY to maintain Navy required industrial mobilization capability.

7. Determination of Fair and Reasonable Costs

The Contracting Officer has determined the anticipated cost to the Government of the supplies/services covered by this J&A will be fair and reasonable.

8. Actions to Remove Barriers to Competition

PAE Maritime will work to conduct competitive acquisitions for future surface ship maintenance, modernization and repair availabilities to the maximum extent possible. This is evident by the decision in February 2026 to competitively solicit this availability and revert back to an industrial mobilization when conditions changed.