USS AUGUSTA RFP.pdf
PDF 2 MB Posted
- Attached to
- USS AUGUSTA (LCS 34) FY26 DSRA
- Solicitation number
- N0002426R4420
About this file
This document is a Request for Proposals (RFP) for the USS AUGUSTA (LCS 34) Fiscal Year 2026 Docking Selected Restricted Availability (DSRA), issued by the Naval Sea Systems Command. The solicitation seeks a single fixed-price contract to prepare for and accomplish repair and alterations for the USS AUGUSTA, including multiple contract line items covering work such as ship alterations, missile launching system refurbishment, and various support services. The availability will include maintenance, modernization, and repair activities, with a total contract period targeting completion by August 6, 2027.
The RFP is not set aside for small businesses and is open to all responsible sources, with a proposal due date of January 9, 2026, at 2:00 PM Eastern Time. The government anticipates making an award in or before May 2026, with an estimated contract value covering base and option items, growth reservations, and additional services. Key evaluation factors include technical eligibility, physical resource capacity, manpower planning, small business participation, schedule execution approach, and past performance. Offerors must be registered in the System for Award Management (SAM) and submit proposals electronically through the Procurement Integrated Enterprise Environment (PIEE) platform.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AUGUSTA A0001 Modification Doc.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until local time
X
A X B X C X D
EX
X
G F 119 - 131
132 - 157 X H 158 - 168 jack.a.klipfel.civ@us.navy.mil
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
DO-A3 1 168
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
N00024 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
JACK KLIPFEL (202)781-2932
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 29
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
30 - 76 77 - 78
J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
79 - 81 82 - 84
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 85 - 92 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 93 - 95 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIONS AND INSTRUCTIONS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
96 - 117
PART II - CONTRACT CLAUSES
NAVAL SEA SYSTEMS COMMAND (HQ)
1333 ISAAC HULL AVE SE
WASHINGTON NAVY YARD DC 20376-2030
FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.
N0002426R4420
5. DATE ISSUED
10 Nov 2025
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
N0002426R4420
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
CLIN
Number
1 Lot
RESERVED
FFP
FOB: Destination
PURCHASE REQUEST NUMBER: N0002426R4420
NET AMT
1 Lot
RESERVED
FFP
1 Each
CDRLs
FFP
Contracts Data Requirements Lists (CDRLs) - Not Separately Priced (NSP)
Accomplishment of Availability
FFP
PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS
ONBOARD USS AUGUSTA (LCS 34) DURING FY26 DOCKING SELECTED
RESTRICTED AVAILABILITY (DSRA) (Non-prorated WIs – See attachment J- 4A for list)
The Contractor shall prepare for and accomplish repair and alterations during the Docking Selected Restricted Availability (DSRA) onboard USS AUGUSTA (LCS
34) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.
See Notes A, B, and D-G
Temporary Service; provide
FFP
PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS
ONBOARD USS AUGUSTA (LCS 34) DURING FY26 DOCKING SELECTED
RESTRICTED AVAILABILITY (DSRA) (Non-prorated WIs – See attachment J-4 for list)
The Contractor shall prepare for and accomplish repair and alterations during the Docking Selected Restricted Availability (DSRA) onboard USS AUGUSTA (LCS
34) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.
See Notes A, B, and D-G
PMS 321 Ship Alts -OPN
FFP
PMS 321 Ship Alts- OPN 93622, 93855, 92138, 93595, 95372, 99751, 98695, 86670, 95170
PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS
ONBOARD USS AUGUSTA (LCS 34) DURING FY26 DOCKING SELECTED
RESTRICTED AVAILABILITY (DSRA) (Non-prorated WIs – See attachment J-4 for list)
The Contractor shall prepare for and accomplish repair and alterations during the Docking Selected Restricted Availability (DSRA) onboard USS AUGUSTA (LCS
34) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and
Over-The-Horizon (OTH) Missile Launching
FFP
Over-The-Horizon (OTH) Missile Launching System (MLS) MK 87 MOD 0 Launch Mechanism Refurbishment; accomplish
PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS
ONBOARD USS AUGUSTA (LCS 34) DURING FY26 DOCKING SELECTED
RESTRICTED AVAILABILITY (DSRA) (Non-prorated WIs – See attachment J-4 for list)
The Contractor shall prepare for and accomplish repair and alterations during the Docking Selected Restricted Availability (DSRA) onboard USS AUGUSTA (LCS
34) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and
Regional Maintenance Center
FFP
Regional Maintenance Center (RMC) Office Space; provide
PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS
ONBOARD USS AUGUSTA (LCS 34) DURING FY26 DOCKING SELECTED
RESTRICTED AVAILABILITY (DSRA) (Non-prorated WIs – See attachment J-4 for list)
The Contractor shall prepare for and accomplish repair and alterations during the Docking Selected Restricted Availability (DSRA) onboard USS AUGUSTA (LCS
34) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and
OPTION Fuel Assistance & Defuel (Option Item)
FFP
Fuel Assistance and Towboat Service for Fuel Barge; provide (OPTION ITEM -
OUT OF HOMEPORT ONLY)
Defuel Ship; accomplish (OPTION ITEM - OUT OF HOMEPORT ONLY)
PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS
ONBOARD USS AUGUSTA (LCS 34) DURING FY26 DOCKING SELECTED
RESTRICTED AVAILABILITY (DSRA) (Non-prorated WIs – See attachment J-4 for list)
The Contractor shall prepare for and accomplish repair and alterations during the Docking Selected Restricted Availability (DSRA) onboard USS AUGUSTA (LCS
34) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and
See Notes A-G
OPTION Temporary Duty & Office (Option Item)
FFP
Temporary Duty Section Berthing Off-Ship; provide (OPTION ITEM - OUT OF
HOMEPORT ONLY)
Ship's Force Office Space; provide
PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS
ONBOARD USS AUGUSTA (LCS 34) DURING FY26 DOCKING SELECTED
RESTRICTED AVAILABILITY (DSRA) (Non-prorated WIs – See attachment J-4 for list)
The Contractor shall prepare for and accomplish repair and alterations during the Docking Selected Restricted Availability (DSRA) onboard USS AUGUSTA (LCS
34) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and
OPTION Barge Tow & Support (Option Item)
FFP
Berthing Barge Tow and Support Service; provide (OPTION ITEM - HOMEPORT
ONLY)
PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS
ONBOARD USS AUGUSTA (LCS 34) DURING FY26 DOCKING SELECTED
RESTRICTED AVAILABILITY (DSRA) (Non-prorated WIs – See attachment J-4 for list)
The Contractor shall prepare for and accomplish repair and alterations during the Docking Selected Restricted Availability (DSRA) onboard USS AUGUSTA (LCS
34) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and
PMAV Labor
FFP
PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS
ONBOARD USS AUGUSTA (LCS 34) DURING FY26 DOCKING SELECTED
RESTRICTED AVAILABILITY (DSRA) (Non-prorated WIs – See attachment J-4 for list)
The Contractor shall prepare for and accomplish repair and alterations during the Docking Selected Restricted Availability (DSRA) onboard USS AUGUSTA (LCS
34) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and
OPTION Growth Reservation for CLIN 0004
FFP
Growth Reservation Associated with CLIN 0004. See Attachment J-4.
See Notes A-G.
FFP
Growth Reservation Associated with CLIN 0004. See Attachment J-4.
See Notes A-G.
FFP
Growth Reservation Associated with CLIN 0004. See Attachment J-4.
See Notes A-G.
OPTION Growth Reservation for CLIN 0005
FFP
Growth Reservation Associated with CLIN 0005. See Attachment J-4.
See Notes A-G.
OPTION Growth Reservation for CLIN 0006
FFP
Growth Reservation Associated with CLIN 0006. See Attachment J-4.
See Notes A-G.
OPTION Growth Reservation for CLIN 0007
FFP
Growth Reservation Associated with CLIN 0007. See Attachment J-4.
See Notes A-G.
OPTION Growth Reservation for CLIN 0008
FFP
Growth Reservation Associated with CLIN 0008. See Attachment J-4.
See Notes A-G.
OPTION Growth Reservation for CLIN 0009
FFP
Growth Reservation Associated with CLIN 0009. See Attachment J-4.
See Notes A-G.
OPTION Growth Reservation for CLIN 0010
FFP
Growth Reservation Associated with CLIN 0010. See Attachment J-4.
See Notes A-G.
OPTION Growth Reservation for CLIN 0011
FFP
Growth Reservation Associated with CLIN 0011. See Attachment J-4.
See Notes A-G.
OPTION Incentive Reservation for CLIN 0013
FFP
Incentive Reservation Associated with CLIN 0013. See Attachment J-4.
See Notes A-G.
OPTION Incentive Reservation for CLIN 0014
FFP
Incentive Reservation Associated with CLIN 0014. See Attachment J-4.
OPTION Incentive Reservation for CLIN 0015
FFP
Incentive Reservation Associated with CLIN 0015. See Attachment J-4.
OPTION Incentive Reservation for CLIN 0016
FFP
Incentive Reservation Associated with CLIN 0016. See Attachment J-4.
OPTION Incentive Reservation for CLIN 0017
FFP
Incentive Reservation Associated with CLIN 0017. See Attachment J-4.
CLAUSES INCORPORATED BY FULL TEXT
B-215-H002 REFUNDS (SPARES AND SUPPORT EQUIPMENT) (NAVSEA) (OCT 2018)
(a) In the event that the price of a spare part or item of support equipment delivered under this contract significantly exceeds its intrinsic value, the Contractor agrees to refund the difference. Refunds will not be made to recoup the amount of cost decreases that occur over time due to productivity gains (excluding economic purchase quantity considerations) or changes in market conditions.
(b) For purposes of this requirement, the intrinsic value of an item is defined as follows:
(1) If the item is one which is sold or is substantially similar or functionally equivalent to one that is sold in substantial quantities to the general public, intrinsic value is the established catalog or market price, plus the value of any unique requirements, including delivery terms, inspection, packaging, or labeling.
(2) If there is no comparable item sold in substantial quantities to the general public, intrinsic value is defined as the price an individual would expect to pay for the item based upon an economic purchase quantity as defined in FAR 52.207-4, plus the value of any unique requirements, including delivery terms, inspection, packaging or labeling.
(c) At any time up to two years after delivery of a spare part or item of support equipment, the Contracting Officer may notify the Contractor that based on all information available at the time of the notice, the price of the part or item apparently exceeds its intrinsic value.
(d) If notified in accordance with paragraph (c) above, the Contractor agrees to enter into good faith negotiations with the Government to determine if, and in what amount, the Government is entitled to a refund.
(e) If agreement pursuant to paragraph (d) above cannot be reached, and the Navy's return of the new or unused item to the Contractor is practical, the Navy, subject to the Contractor's agreement, may elect to return the item to the Contractor.
Upon return of the item to its original point of Government acceptance, the Contractor shall refund in full the price paid.
If no agreement pursuant to paragraph (d) above is reached, and return of the item by the Navy is impractical, the Contracting Officer may, with the approval of the Head of the Contracting Activity, issue a Contracting Officer's final decision on the matter, subject to Contractor appeal as provided in the "Disputes" clause (FAR 52.233-1).
(f) The Contractor shall make refunds, as required under this requirement, in accordance with instructions from the Contracting Officer.
(g) The Contractor shall not be liable for a refund if the Contractor advised the Contracting Officer in a timely manner that the price it would propose for a spare part or item of support equipment exceeded its intrinsic value, and with such advice, specified the estimated proposed price, the estimated intrinsic value and known alternative sources or item, if any, that can meet the requirement.
(h) This requirement does not apply to any spare parts or items of support equipment whose price is determined through adequate price competition. This requirement also does not apply to any spare part or item of support equipment if the Contractor submitted, and certified the currency, accuracy and completeness of, cost or pricing data applicable to the item.
(End of text)
B-227-H001 PROVISIONING TECHNICAL DOCUMENTATION – WITHHOLDING OF PAYMENT
(NAVSEA) (OCT 2018)
The PTD is considered to be a part of the "Technical Data" specified to be delivered under this contract for the purposes of the "Technical Data--Withholding of Payment" (DFARS 252.227-7030) clause. The terms and conditions of the clause entitled "Limitation On Withholding of Payments (FAR 52.232-9), if included in this contract, shall not apply to withholding of payment for failure to make timely delivery of the PTD or delivery of deficient PTD.
B-231-H002 WORKSITE TRAVEL COSTS (NAVSEA) (OCT 2018)
(a) The contractor shall not charge, and the Government shall not pay, as an allowable cost under this contract, any manhour costs (whether straight-time or overtime) for contractor personnel or subcontractor personnel traveling to or from worksites, including travel to worksites other than the contractor's facility for performance of contract work.
(b) Workers being paid under this contract, as prime contractor personnel or subcontractor personnel, will complete a full shift at the worksite, and no compensation will be paid for travel time before or after the shift.
(c) This requirement pertains only to payments for travel time before or after these workers' regular shifts (commuting costs), and does not apply to legitimate travel costs incurred during normal working hours, provided that those costs are otherwise reasonable, allocable and allowable and approved in writing by the Government. This requirement does not apply to manufacturer's representatives or Original Equipment Manufacturer (OEM) representatives when specifically required by the Government work specifications.
(d) Additionally, the contractor shall not charge, and the Government shall not pay, any transportation costs under this contract associated with transporting contractor or subcontractor personnel between the contractor's facility (or subcontractor's facility), and any other worksite to perform ship repair, maintenance or modernization.
Transportation costs include, but are not limited to, bus fare, car fare, train fare, or boat fare, paid by the work force, or paid by the contractor on behalf of the work force.
NOTE A: LEVEL OF EFFORT TO COMPLETION – SHIP REPAIR
1. The Contractor agrees to provide the level of effort to completion (LOE to Completion) in the performance of growth CLINs in the execution of the USS AUGUSTA (LCS 34) FY 26 DSRA
a. 19,091 direct labor hours (labor hours) and $3,211,615 ($TBD fully burdened) materials to complete expected, within scope growth work on the USS AUGUSTA DSRA work package under CLINs 0013 – 0022.
2. The total LOE to Completion for the performance of the above growth CLINs shall be comprised of labor hours and the associated material required to support the expected, within scope growth. The mix of labor hours and material may be adjusted. Adjustments to the labor hour and material mix will be documented via weekly Technical Direction Letters (TDL) and subsequently unilaterally adjusted via contract modification. The Government reserves the right to reconcile the weekly TDLs via unilateral modification at the Administrative Contracting Officer’s (ACO) discretion.
3. LOE to Completion obligations specified above shall only include effort performed in direct support of this contract and shall not include time and effort expended on such things as local travel to and from an employee's usual work location, uncompensated effort while on travel status, truncated lunch periods, work (actual or inferred) at an employee's residence or other non-work locations.
4. LOE to Completion labor hours and material are within the scope and pricing of this contract and are not subject to an equitable adjustment under FAR 52.243-1 ‘Changes – Fixed Price’. The utilization of LOE to Completion is at the discretion of the Contracting Officer and subject to the schedule phasing identified in Note F.
5. If, in the opinion of the Contractor, any effort directed in the Growth Management Request Form (GMR) calls for effort outside the scope of the contract, the Contractor shall notify the Administrative Contracting Officer (ACO) in writing within two (2) working days after the receipt of any such direction. In the event of a cost dispute, the ACO may unilaterally authorize hours and material against LOE work. The Contractor shall not proceed with the work directed by the GMR unless and until the Contractor is notified by the ACO to proceed with the directed work. The Contractor is required to proceed with the directed work as directed by the ACO.
Thereafter, any remaining disagreement shall be addressed in accordance with FAR 52.233-1(Alt. 1) ‘Disputes.’
Additionally, if the cost of performing the disputed direction exceeds $100,000, the Contractor is required to comply with FAR 52.243-6 ‘Change Order Accounting.’
6. The labor hours and material requirements listed in Section B, Note A, paragraph 1 above are part of this contract. Prime contractor efforts shall be deducted from the labor hours allocated. Subcontractor efforts and materials shall be deducted from the materials allocated. The balance of labor hours and materials remaining in the LOE to Completion CLINs will be recouped by the Government via final contract modification at the end of the availability, when it is evident no additional growth work will be directed. The final contract modification shall amount to a credit to the Government that equals 100% of unused direct labor hours and material dollars.
7. Only authorized direct production labor hours shall be deducted from the LOE to Completion direct labor hour ceiling set forth in Section B, Note A, paragraph 1 above. Per Note B paragraph 2 below, all non-production labor shall be included in the Contractor’s fully burdened labor rate. Non-production hours shall not be included in pricing submitted in support of growth issued under the LOE to Completion CLINs. Additionally, Contractor LOE to Completion pricing shall not include any allowance for technical representatives or for any other Government directed source unless specifically directed by the Contracting Officer.
8. Only authorized material dollars shall be deducted from LOE to Completion material reservation set forth in Section B, Note A, paragraph 1 above. This material reservation consists of the total cost of materials and subcontractor efforts proposed. All subcontractor quotes shall be included in the Change Order Price Analysis (COPA) as per Section C, paragraph 1.14. Material dollars may include freight or duties if specifically itemized on the invoice for the material. The Contractor shall not be allowed to add material handling charges, overhead (including G&A), or profit into the settled cost of materials deducted from the material reservation.
The information received in the consolidated final report required by Section C paragraph 6.6 will be used by the ACO in the issuance of one contract modification based on the information received in the final report identified in Section C below, which will be a final settlement for all LOE to Completion labor hours and material dollars. Once the number of labor hours and materials for directed work has been settled, neither party shall be entitled to an adjustment because the expended labor hours and materials differ from the settled price. This shall not preclude an adjustment otherwise permitted by law and regulation; e.g. fraud, product substitution, defective workmanship or materials. Each directed work shall receive approval by the SUPERVISOR and the ACO. “SUPERVISOR” as defined in NAVSEA Standard Item (NSI) 009-001, paragraph 4.3, refers to the local Government activity responsible for the execution and contract administration of Navy maintenance and modernization work
NOTE B: FIXED SHIP REPAIR LABOR AND MATERIAL BURDEN RATES FOR GROWTH AND
NEW WORK
SCHEDULE OF PRICES / RATES: SHIP REPAIR LABOR RATE (FULLY BURDENED)
1. The Contractor’s fully burdened ship repair labor rate will be used for negotiating growth; and new work to be performed under this contract. The contractor agrees that the number of hours included in its price proposal submitted in response to Requests for Contract Changes (RCCs), Growth Management Requests (GMRs) and Reservation Task Requests (RTRs) shall include only direct production hours. For these purposes, direct production hours are for skilled labor at the journeyman level expended in direct production including but not limited to the following functions:
Abrasive cleaning/blasting Fire Watch Welding Burning Brazing Carpentry Machinists (inside and outside) Electrical Work Electronic Work Engineering Design Support Lagging Ship-fitting Boiler-making Painting Sheet-metal Work Pipefitting Rigging General Labor Staging/Scaffolding Diesel Mechanics
2. The fully burdened ship repair labor rate proposed by the contractor listed in paragraph 7 below shall include all costs associated with support functions (whether charged directly or indirectly by the offeror’s accounting systems) provided in support of the direct production functions listed in paragraph 1 above. Support functions shall be considered to be included in the offeror’s fully burdened ship repair labor rate for direct production hours. Labor hours for the below support functions shall not be separately proposed, including in support of subcontractors. Support functions include, and are not limited to, those types listed below:
Testing Quality Assurance Execution Planning Cleaning (except tank cleaning) Supervision (all types, including, but not limited to supervision of trades, support personnel and subcontractors) Security Surveying Administration Transportation Purchasing Staff Lofting Other indirect support Handling & Warehousing Safety/Environmental Program Management
3. The fully burdened ship repair labor rate is a fixed hourly rate that includes all wages, (i.e. straight time, overtime, shift differential, holiday time, etc.), overhead, all other indirect costs, general and administrative expenses, Facilities Capital Cost of Money (FCCOM) and profit. The fully burdened ship repair labor rate represents a blended rate including labor transferred between divisions, subsidiaries, or affiliates of the contractor under a common control.
4. Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc., that are consumed/used in the process of repair and do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor’s fully burdened ship repair labor rate and not separately priced.
5. Physical materials are goods that become incorporated into the repaired vessel in the course of the repair, such as replacement steel, pipes, paint, and fasteners. The material burden rate applies to physical materials but not to consumable materials. The material burden rate will be applied to the actual cost of the physical material. Actual cost does not include handling charges, general and administrative cost, overhead, profit, or any other indirect cost.
6. For growth and new work contract changes involving subcontractors, subcontractor quotes will be treated as
Other Direct Costs (ODCs) and will be subject to the contract material burden rate shown in paragraph (7) below. Subcontractor (competitive quotes if required by the ACO) quotes must be submitted with the contractor’s COPA in response to RCCs, GMRs and RTRs issued by the Contracting Officer. For new work only, these subcontractor quotes must be competitively acquired. At no time will the proposed total to be performed by the prime contractor combined with subcontractor quote, material quote, and applicable burdens be allowed to cost more than it would have, had the prime contractor directly provided all material and labor. The proposed total pricing restriction addressed in the preceding sentence does not apply in any case where the work is required to be performed by Original Equipment Manufacturers (OEMs), Government directed subcontractors, Government authorized vendors and/or when it is concurred with by the Government that the prime contractor does not possess the technical expertise to perform the subcontracted work. RCCs and RTRs that are subcontracted for material only (no associated labor required within the RCC) shall not be subject to the Material Burden Rate. Any material burden rate applied to new work shall be approved by the ACO, upon receipt of supporting documentation in accordance with FAR 15.404-3, Subcontract Pricing Considerations.
7. The contract fixed fully burdened ship repair labor rate and material burden rate are shown below. These fixed rates shall be used for negotiating growth, and new work during the availability and up to three (3) months after the Attachment J-3 (USS AUGUSTA, Contract Complete’ date as appropriate:
USS AUGUSTA FY26 DSRA
Fully Burdened Ship Repair Labor Rate Fill-In Material Burden Rate Fill-In
8. In the event of a one-bid or directed availability, the Contracting Officer may negotiate the Fully Burdened Ship Repair Labor Rate and Material Burden Rate (not to exceed the ceiling rate(s) identified above) with the offeror in accordance with FAR 15.4, Contract Pricing. The rates herein are not considered a Forward Pricing Rate Agreement (FPRA) and are identified solely for the purpose of establishing a ceiling.
In the event of an extension due to excusable delay to the delivery date for the USS AUGUSTA FY26 DSRA the Contractor’s fully burdened ship repair labor rate shall be escalated by 0.37 % commencing 3 months after the Attachment J-3 “Contract Complete” date. Following the “Contract Complete” date identified in Attachment J-3 USS AUGUSTA (Milestones), as appropriate, this rate shall be escalated quarterly through the 24th month, if necessary, and shall be used to negotiate all growth, and new work. Note, in the event of an excusable delay, this escalation rate shall be applied only to growth and new work not previously identified in Attachment J-4A USS AUGUSTA, J-4 (Pricing Workbook). The material burden rate shall not increase
NOTE C: OPTION ITEMS
Option item to which the option clause FAR 52.217-7 (NAVSEA Variation II) applies and which is to be supplied only if and to the extent said option is exercised.
NOTE D: SCHEDULE OF DAILY RATES FOR PIERSIDE AND DRY-DOCKING (FULLY BURDENED)
FOR PURPOSES OF A COMPENSABLE EXTENSION TO THE DRY-DOCKING OR DELIVERY DATE
1. In the event of a compensable extension to the dry-docking or delivery date, the Contractor’s fully burdened daily rates for additional dry-dock and/or pierside performance period at the Contractor’s facility will be evaluated by the ACO upon receipt of the Contractor’s certified or other than certified cost or pricing data (certification requirements are subject to FAR 15.403).
2. The Contractor agrees that the daily rates shall include all time-based costs incurred from additional performance days in accordance with the work package specification requirements of this availability. The daily rates shall include all costs associated with additional performance days (whether charged directly or indirectly by the offeror’s accounting systems) including but not limited to:
Temporary Services, including but not limited to:
o Decking services o Pumping services o Electricity
Internet Connectivity Air Conditioning
Support Services for the Navy, its agents and Contractors Facilities, including but not limited to:
o Piers o Dry-docks o Office spaces o Trailers o Parking o Flammable Liquid Storage and Hazardous Material Storage o Material Warehousing and Lay-down space
Project Management and other labor costs that run with time including but not limited to:
o Program Management o Supervision o Integration & Scheduling o Cleaning (except tank cleaning) o Quality Assurance o Execution Planning o Security o Administration o Contracts o Purchasing o Other indirect support o Safety/Environmental
Transportation
3. The fully burdened daily rates are fixed rates that include all wages, overhead, other indirect costs, general and administrative expenses, Facilities Capital Cost of Money (FCCOM) and profit.
4. The proposed, fully burdened daily rates for pierside and dry-docking may be used during the availability’s extension period, up to 24 months after the “Contract Complete” date identified in Attachment J-3 USS AUGUSTA, (Milestones). If the use of these extension rates is determined to be warranted by the ACO during execution, the Contractor shall submit certified or other than certified cost or pricing data to support the rates (certification requirements are subject to FAR 15.403).
USS AUGUSTA FY26
DSRA
Additional Day Requiring Availability Extension
Additional Day Does Not Require Availability Extension
Additional Dry-Docking Day Fill-In Fill-In
Additional Pierside Day Fill-In Fill-In
5. The Contractor bears the burden of proving the requested extension is compensable in accordance with this contract and establish the duration of compensability through schedule analysis utilizing the Production Schedule establishing impact to critical path and/or controlling work items. The Contractor agrees that, in the event of such an extension, a bilateral modification will be executed with the price of the extension calculated as follows:
Total Price of Extension = De * (P/D) De = Agreed Extension Days to the Delivery Date (P/D) = Price/Day
6. The (P/D) will be utilized for any modifications to extend the contract in the event of compensable delay impacting the pierside and dry-docking period, regardless of the number of modifications or the number of days required to meet the Schedule Milestone ‘Contract Complete’ within 24 months of the ‘Contract Complete’ date. If the Contracting Officer determines a delay in meeting the Schedule Milestone is not compensable, no modification will be executed, and the Contractor will be directed to continue work until certified ‘Contract Complete’ by the NSA.
7. In the event the Contracting Officer determines the delay is concurrent, but clearly apportioned, a bilateral modification will be executed with the price calculated as follows:
Total Price of Extension = (Dg - (Dc) * (P/D) Dg = Government Responsible Delay (measured in days) Dc = Contractor Responsible Delay (measured in days) (P/D) = Price/Day
The values for Dg and Dc will be determined by the Contracting Officer.
8. If the Contracting Officer determines the delay is excusable, a modification will be executed to extend the Delivery Date, however, the Contractor shall not be entitled to recover a Daily Extension Rates.
9. All terms and conditions under the contract apply to all modifications extending the delivery date. If the Contracting Officer and Contractor are unable to reach agreement regarding duration or compensability, the Government reserves the right to execute a unilateral modification utilizing the parameters outlined in paragraphs 5 through 8 above. Failure to agree on whether a compensable extension is appropriate, or the duration of any delivery date extension shall be a dispute subject to the requirements of FAR 52.233-1(Alt. 1) ‘Disputes.’
NOTE E: SPECIAL AGREEMENT FOR GROWTH WITH A PRICE OF $15,000 OR LESS
1. To make administration of small dollar value growth more efficient and less costly, both parties (Government and Contractor) agree to a pre-priced value for individual growth items with an estimated price of $15,000 or less. The Contract will include a firm fixed price for growth valued at $15,000 or less. Zero-dollar changes and administrative contract changes (for example, drawing revision change where no additional work is required) shall not be executed using the Small Dollar Value Growth procedures, but will follow the change process pursuant to FAR 52.243-1. Trade labor hours expended to review drawing revision changes and incorporate them into the existing schedule are considered to be part of Planning Execution and will not be separately charged under Small Dollar Value or any other change.
2. The amount included in this Contract for the growth described above shall be equal to a maximum quantity of:
a. 205 occurrences for growth work computed at a firm fixed price of $6,264 per occurrence, as associated with CLINS 0013 – 0022 for the USS AUGUSTA (LCS 34) FY26 DSRA.
3. A Waterfront Circuit Team comprised of a small group of Contractor and Government representatives shall administer the Special Agreement for Growth with a value of $15,000 or less. The Contractor shall establish a group of empowered representatives who will be located in proximity to the ship during the availability period and who will interact with a similar group of Government representatives (also to be located in close proximity to the ship and to be identified by the Naval Supervising Activity (NSA)). Specific arrangements for the Waterfront Circuit Team shall be mutually agreed between the Contractor and NSA.
4. The Contractor shall report proposed growth work through the normal Condition Found Report (CFR) process in accordance with Contract terms. The Government may also independently identify growth work. No later than 24 hours after the final approval of the CFR, the Waterfront Circuit Team shall use best efforts to determine if the proposed growth is $15,000 or less, and document the agreed to technical scope of work. The Contracting Officer or the authorizing official shall direct the commencement of all growth work. Directed growth will be followed by documentation to appropriately reflect specification changes.
5. If the Waterfront Circuit Team is not able to reach agreement that the price of the growth work is $15,000, or less, then it will be adjudicated through the LOE to Completion process identified in Section B, Note A.
However, if LOE to Completion negotiations reveal the value of growth work is $15,000, or less, the task will be settled in accordance with the Small Dollar Value Growth procedure at the pre-priced value per occurrence identified in Section B, Note E, Paragraph 2, above.
6. If the Contractor and Government (Contracting Officer) reach settlement in three (3) business days an incentive of $1,236 will be applied to the standard price per change of $6,264. The result in these instances would be a SDVG price per change of $7,500.
7. The Contractor and Government (Contracting Officer) shall develop a growth tracker to identify and record the number of directed occurrences under this Note. All growth meeting the criteria of paragraph 1 above shall be accepted under this clause without delay and disruption in ship redelivery.
8. When the quantity of occurrences for Small Dollar Growth is depleted, the Small Dollar Growth process shall revert to the LOE to Completion process for remaining growth.
9. Small Dolar Value Growth Incentive
A. Purpose:
To expedite the execution of contract changes on the USS AUGUSTA (LCS 34) FY26 DSRA the Government will incentivize the timely settlement of Small Dollar Value Growth (SDVG) occurrences. If the Contractor provides written agreement in response to the Government issued SDVG Growth Management form within three (3) business days, the Contractor will earn an incentive fee credit of $1,236. The total incentive fee earned will equal the number of incentive fee credits earned multiplied by $1,236.
B. Available Incentive Amount:
The total maximum incentive available pursuant to this Note is $1,236 per Small Dollar Value Growth occurrence and:
a. $253,380 across 205 approved occurrences for the USS AUGUSTA
(LCS 34) FY26 DSRA
10. Within 30 days after the end of the contract period of performance, the Contractor and Contracting Officer, utilizing the growth work tracker, shall determine the number of pre-priced occurrences not utilized under this contract. Accordingly, the Contracting Officer will decrease the contract price by an amount calculated by multiplying the remaining number of occurrences by the pre-established firm fixed price per occurrence.
NOTE F: AVAILABILITY SCHEDULE PERFORMANCE
1. The Contractor shall schedule the performance of all Base and Option items in the work package, so as to permit a contract scope increase up to the:
Total contract number of labor hours and material dollars to complete growth work as described in NOTE A: LEVEL OF EFFORT TO COMPLETION –SHIP REPAIR, paragraph 1.
Total contract number of Small Value Dollar Growth occurrences as described in NOTE E: SPECIAL AGREEMENT FOR GROWTH WITH A PRICE OF $15,000 OR LESS, paragraph 2.
The total number of labor hours and material dollars to complete the typical amount of new work as identified in Attachment J-4 (Pricing Workbook); and
The post-award supplemental work package identified in Note G: POST-AWARD SUPPLEMENTAL WORK PACKAGE shall be in addition to efforts identified under Notes A, E and new work identified above.
2. The Contractor agrees that the growth work identified in Section B, Note F, Paragraph 1, above, if tasked, shall be performed, purchased and installed concurrently with the work items, without impacting, accelerating, or causing delay or disruption to the work required by the base and option work items, to any other Government contract, or to any other work in progress for the Government.
3. The growth work described above, if required, shall be tasked during the contract period of performance, as may be modified, on the following schedule phasing:
No more than 50% of the hours or material following the 50% schedule point of the availability (as measured in days between the “Availability Start” and “Contract Complete” milestones in Attachment J-3), adjusted for delay to delivery date.
No more than 25% of the hours or material following the 75% schedule point of the availability (as measured in days between the “Availability Start” and “Contract Complete” milestones in Attachment J-3), adjusted for delay to delivery date.
NOTE G: POST AWARD SUPPLEMENTAL WORK PACKAGE
1. Within seven (7) days of award, the Government intends to solicit a supplemental work package to be incorporated into the availability. The total dollar value of the supplemental work package is expected to be no greater than $2 Million.
2. Within 10 days of receiving the supplemental package Request for Proposal (RFP), the contractor shall notify the Government, in writing, as to whether the work package can be completed within the schedule milestones listed in Attachment J-3. The Contractor agrees to provide objective evidence of any work that cannot be completed to include direct impact to the critical path.
3. The Contractor can submit requests for clarification up to 14 days after receiving the RFP. The proposal is due no later than 30 days after receiving the RFP. If the proposal is equal to or greater than the certified cost and pricing threshold (currently $2 Million) the proposal meets the requirement for certified cost and pricing data of FAR 15.403 and will be submitted in the format required by FAR 15.408, Table 15-2.
If the proposal is less than the certified cost and pricing threshold, the Contractor agrees to provide the data other than certified cost and pricing data as requested by the contracting officer. The data other than certified cost and pricing includes, but is not limited to:
Prime labor hours broken down by trade and paragraph level with a basis of estimate for each work item.
Detailed material list with the source, part number, description, unit cost, quantity, total cost, and vendor quotes Subcontractor quotes including labor hours broken down by paragraph and task, labor rate, full material quote including part number, description, unit cost, quantity, total cost, and vendor quotes.
4. The Contractor shall develop and provide an Integrated Production Schedule, created in full compliance with
Standard Item 009-060, in support of the WPER and updated prior to the finalization of the solicited work package revisions and the supplemental work package, reflecting the schedule constraints proposed in the contractor’s schedule.
The Integrated Production Schedule shall integrate Alteration Installation Teams (AIT), Government- Contracted Third Party Maintenance Providers, Ship's Force, Commercial Industrial Services (CIS), and Fleet Maintenance Activity (FMA) work to the maximum extent this information is available.
5. This post award supplemental package is subject to the fully burdened labor and material burden rates stated in Note B.
Section C - Descriptions and Specifications
SCOPE OF WORK
1. GENERAL REQUIREMENTS
1.1. The Contractor, under the direction of the Regional Maintenance Center (RMC) as an independent
Contractor and not as an agent of the Government, shall furnish the material, support (electrical, crane, rigging, etc.) and facilities (except those furnished by the Government under express provisions of this contract) and provide the management, technical, procurement, production, testing and quality assurance necessary to prepare and accomplish the repairs and alterations required to complete the USS AUGUSTA (LCS 34) FY26 Docking Selected Restricted Availability DSRA in accordance with the requirements stated in this Section, the Work Item Specifications and Work Item Plans, Drawings, and Other References, the Delivery Schedule, and all other terms and conditions set forth in this contract.
1.2. The Contractor shall lead or participate in periodic meetings, as required, to facilitate status reporting related to USS AUGUSTA FY26 DSRA. Forums will be conducted at a time mutually agreed to by primary participants. These meetings include, but are not limited to, the following:
1.2.1. Post Award Conference (Government Leads)
1.2.2. Contract Reading (Government Leads)
1.2.3. Integrated Project Team Development (IPTD) Post-Award Event (Government Leads)
1.2.4. Arrival Conference (Government Leads)
1.2.5. IPTD Work Package Execution Review (WPER) (Government Leads)
1.2.5.1. The IPTD WPER will take place at the RMC located at the vessel’s homeport at A-60.
If WPER cannot be conducted at A-60 due to late Award, the Naval Supervising Activity (NSA) Project Manager (PM) and Lead Maintenance Activity (LMA) will need to determine a reasonable time prior to avail start to conduct the event.
1.2.6. Schedule Model Review (SMR) (Contractor Leads)
1.2.6.1. The Schedule Model Review will take place at the LMAs designated location per the
J-Attachment requirement. The SMR will begin at A-59, or on first business day following the IPTD WPER. If SMR cannot be conducted at A-59 due to late Award, then NSA PM and LMA will need to determine a reasonable time prior to avail start to conduct the event.
1.2.7. Project Management Reviews such as the 25%, 50%, 75%, and other meetings required to manage the overall availability to completion (Government Leads)
1.2.8. Daily Production meetings (Contractor Leads)
1.2.9. Weekly Progress meetings (Contractor Leads)
1.2.10. Weekly Commanding Officer briefs (Government Leads)
1.2.11. IPTD Completion Event (formerly known as “IPTD C+21 Post-Completion Meeting”)
(Government Leads)
1.2.12. Additionally, the contractor shall provide all reports, required in accordance with NSI 009-01
1.3. Category I NSIs identified under Attachment J-1 are applicable to all items without further reference.
Category II NSIs are applicable when invoked and/or referenced in individual work items, or Category I NSIs, specified in Attachment J-1. NSIs may be found at:
http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI.aspx.
Contractor is obligated to submit all required reporting in accordance with applicable NSIs (See Contract Data Requirements List, DD 1423, CDRL A003).
1.3.1. All NAVSEA Standards items under this RFP and subsequent contract will be FY26 unless otherwise specified.
1.4. In addition to the Work Item Specifications and Work Item Plans, Drawings, and Other References and applicable NSIs, additional work item references not already in the possession of the Offerors, commercially available, listed under FAR 52.211-2. In addition, references are available through the following websites:
a) https://jedmics.net/
b) https://nmfom-prd.mfomls.navsea.cloud.navy.mil/mfom
c) http://www.coretl.com/help/shell.php
1.5. The Contractor shall accomplish planning and scheduling to ensure a rational, integrated and timely plan for receipt, storage and installation of Government Furnished Property (GFP) as identified in work item specifications, and for accomplishment of production work.
1.6. The Contractor shall provide an integrated milestone plan for the availability. These milestones will include a schedule of key events necessary to meet the contract delivery dates. A critical path analysis and a milestone schedule shall be used to measure schedule accomplishment of the functions and elements required to successfully complete the repair and alterations required to complete the USS AUGUSTA (LCS 34) FY26 DSRA within the availability dates herein.
1.7. INTEGRATED PRODUCTION SCHEDULE DEVELOPMENT, UPDATE, AND REVIEWS:
In support of NSI and CDRL requirements and to confirm the contractor has all available input for development of the IPS, including the development of the Integrated Work Package, Production Schedule, Integration of O, I and D level Work, Integration of AIT and SHIPALT requirements and any other contractor assigned or Third Party work scheduled for accomplishment concurrent with the CNO availability, the contractor shall, with the RMC, conduct the IPTD WPER and SMR. The RMC will schedule the IPTD at A-60 (event timeline may be shifted left or right as required to meet the needs of the Planning Team (PT) and the individual availability) for CNO availabilities. The SMR shall begin at A-59 or on the first business day following the WPER. All IPS requirements must be compliance with NSI 009- 060 during the course of contract performance.
1.7.1. The Contractor shall formally present its IPS to the NSA at the SMR, Start of the Availability, 25% complete conference, 50% complete conference, 75% complete conference, production completion meetings, and for pre Sea Trials requirements. The IPS shall include AIT, Government-Contracted Third Party Maintenance Providers, Ship's Force, Commercial Industrial Services (CIS), and Fleet Maintenance Activity (FMA) work to the maximum extent this information is available. At each meeting, the contractor shall present and explain, at minimum, the following information:
1.7.1.1. The Contractor's latest, Government approved, IPS created in full compliance with
NSI 009-60
1.7.1.2. The Contractor's current progress in preparing for and/or executing the Availability in accordance with its IPS. The Contractor shall provide an explanation and mitigation plan in the event of any preparation or execution delays in comparison to its IPS.
1.7.1.2.1. The Contractor's plan shall describe opportunities for schedule acceleration, associated costs, and potential risks and mitigations to remaining schedule attainment.
1.7.2. The Government hereby specifies that the contractor may complete the Availability utilizing other than a five-day work week.
1.8. LOGISTICS: The contractor shall develop and submit all logistics and technical data required, including but not limited to provisioning parts lists,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .