Questions and Answers/Comments. Additional questions and answers/comments will be posted at a later date. Amendment 1 will be posted as soon as the Standard Procurement System is back up.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Document / RFP Section or Attachment Number
Section/Paragraph Page Requirement Description / Clause or Definitive Citation Requiring Clarification Offeror’s Comment/Question Government’s Responses
1 RFP
Section I 52.215-9 120 Changes or Additions to Make-or-Buy
Program Please consider deletion of this clause as it is not applicable.
This clause is to be used in solicitations and contracts when it is contemplated that a make or buy plan will be incorporated in a firm fixed price FFP or cost plus fixed fee (CPFF) contract and Alt II when the plan will be incorporated in a cost plus incentive fee (CPIF) contract.
2 RFP
Section I 252.225-7038 123 Restriction on Acquisition of Air Circuit
Breakers
Please review applicability of this clause.
This clause has been deleted.
3 RFP
Section I 252.232-7007 124 Limitation of Government’s Obligation
Please consider deletion of this clause as FFP Orders CLIN would not be incrementally funded.
This clause has been deleted.
4 RFP
Section K 52.227-15 151 Representation of Limited Rights Data and
Restricted Computer Software Please delete as applicable DFAR clause(s) are included in the RFP.
“X” has been removed in Amendment 1.
5 RFP
Section L 52.215-20 165
Requirements for Cost or Pricing Data or Information Other Than Cost or Pricing Data
Request deletion of requirements for certified cost or pricing data given the expectation for adequate price competition in accordance with FAR 15.403-1.
This clause has been deleted.
6 RFP
Section L 52.222-46 165
Evaluation of Compensation for Professional Employees
Please indicate where in the proposal the total compensation plan should be provided. It is not evident in Section L.
This information should be captured within the Cost Volume of the proposal.
7 RFP
Section M
Section M paragraph 2.5 Small Business Subcontracting Plan and Participation (Sub-Factor)
Section M paragraph 2.5 Small Business Subcontracting Plan and Participation (Sub-Factor)
Please verify this section should be number 2.6 to be consistent with proposal structure.
RFP updated as paragraph “2.6”
8 RFP
Section B
Section B Small Business Participation and Small Business Subcontracting
64-65 The SBSIF described in this clause is available for Items 0001 and (if options are exercised) 0101, 0201, 0301, 0401 and
Should all references to the SBSIF applicability to CLIN 0001 be changed to reflect
RFP updated as “The SBSIF is applicable to Items 0001 and (if options are exercised) 0002, 0101, Incentive 0501), if and to the extent the option is exercised.
applicability to CLIN 0002? 0201, 0203, 0204, 0301, 0303, 0401, 0403, 0501, and 0503).”
9 RFP
Section C
Section C TI-20 OMS Systems for VA New Construction
When engineering changes are incorporated into production units, the Contractor is required to conduct Design Verification Tests and supportability analysis and provide updated source data to support the enhancements as identified in the Attachment 2.
DVT and analysis are required for Class 1 or Major Changes as defined by the CMP. We assume DVT and analysis are not required for Class 2 or Minor Changes. Is this correct?
DVT and supportability analysis are required for any engineering changes.
10 RFP
Section L
Section L, 3.0 Proposal Requirements, Volume I Section 1.5 Facilities
The Offeror shall state whether its facility is approved for ACCM (Alternative Compensatory Control Measures) and describe the network infrastructure setup to support ACCM requirements. If the Offeror’s facility is not approved for ACCM, the Offeror must demonstrate the ability to obtain approval for its facility security clearance to handle ACCM data for VA Class submarines and describe the network infrastructure setup to support ACCM requirements.
This contract requires work with VIRGINIA Class stealth performance data that falls under the protection of Alternative Compensatory control Measures (ACCMs). Access to this data is only authorized with specific prior permission from PMS450.
Additional handling requirements in accordance with NAVSEA
INSTRUCTION S5510.18
“SECURITY POLICY FOR
STEALTH PERFORMANCE
DATA WITH ALTERNATIVE
COMPENSATORY CONTROL
MEASURES (ACCMs)” apply.
Please identify how prospective offerors may obtain a copy of NAVSEA Instruction S5510.18 so that bidders may determine the specific additional handling requirements for ACCM and the process PMS450 approval.
This statement revised as “This contract requires work with SSN 774 Class submarines stealth performance data that falls under the protection of Alternative Compensatory Control Measures (ACCMs). In addition to possessing SECRET security clearance, personnel accessing classified information in the performance of this contract need also possess ACCM. Some data and associated information which may be provided by the Government as part of this contract will be subject to need-to-know validation and approval by designated Naval Sea Systems Command classification authorities.
Supplemental air-gapped segregation requirements will be enforced for electronic (computer) data and networks. Hard copy (paper) data will be subject to approved physical storage segregation. Such access and approvals will be provided as appropriate upon contract award and codified by modification of Form
DD254."
Updated in SOW Section 3.0 and Page 170 of the RFP, paragraph (b) of the HQ L-2-0003 FACILITY
SECURITY CLEARANCE
(NAVSEA) (FEB 2012) clause.
11 RFP
Section B
Section B SLIN 0503 55 “First Delivery TI20 OMS Spares” is incorrect. Amendment 1 updated as “Fourth Delivery TI20 OMS Spares”
12 RFP
Section F
Section F
CLIN 0204
13 & 96 “FOB: Destination” is incorrect. RFP updated as “FOB: Origin”
13 RFP
Section B CLIN 0503AM 55
FY22 TI20 OMS Production CPIF for VA New Construction First Delivery TI20 OMS Spares OPTION
YEAR - 5 (FY22)
It appears this may be incorrect referencing “First Delivery” with a first delivery spares being referenced under 0503AC. Should 503AM be updated to be “Fourth Delivery” which would align with the other associated deliveries of OMS system and Pre Cable Kits?
Yes, Amendment 1 updated as “Fourth Delivery TI20 OMS Spares”
14 RFP
Section B
Small Business Participation and Small Business Subcontracting Incentive
65 Paragraph (d) SBSIF Earned
The table at the top of page 65 appears to have an editorial error.
The rows containing percentage values should be shifted down one row.
Table has been updated in Amendment 1
15 Section L 1.1 179 Paragraph numbering
The instructions say “every paragraph … shall be numbered”.
Can Offeror interpret this to mean that every heading down to at least heading level 3 shall be numbered?
Yes
Section L
1.1
179 Font size and line spacing
The instructions stipulate that font size be no smaller than 12 Times New Roman and text line spacing shall be 1.5 lines. Do these requirement apply to figure captions and text within tables and diagrams?
Yes
17 Section L 1.1
The RFP references an OMS "performance specification" on the following pages:
- Page 184 "Demonstrate how the proposed OMS system meets the performance specification and provide supporting data, analysis, or a combination."
- Page 185 "Describe how the proposed OMS system will be integrated with A- RCI Sonar System and meet the OMS performance specification (GFI)."
- Page 186 " Describe the overall approach to satisfying the SOW and OMS performance specification based upon ..."
- Page 197 "... submit an initial Software Development Plan (SDP) that at a minimum addresses the requirements of the contract and achieves the performance specification."
- Page 216 "The degree to which the proposed common OMS system meets the performance specification."
Is the “performance specification” specified in the RFP synonymous with the Attachment 3 “System Requirements Specification” plus classified requirements in the NUWC reading room?
The "performance specification" being referenced is the "Attachment 3 - System Requirements Specification for the Ownship Monitoring System (PMS401- OMSSpec-01) (dated Oct 2014)".
18 Attachment 3 3.6.3.2.1.2.d 31
Control commands shall include (at a minimum) reboot, calibration and gain control commands.
Is “calibration control command” required for STP Message Services?
No
19 Attachment 3 3.8.2.2.c 63
LOFAR, Footprint, Sensor Waterfall, Sensor v. Level Data, and Hydrophone Source Localization Data.
Does “Sensor v. Level Data” mean “Sensor vs Level Data”? Yes